When is the Binghatti Haven handover date?
Short answer
The Binghatti Haven handover date on record is 31 March 2026, the registered completion date on the Dubai Land Department (DLD) register, and Binghatti's own page still lists Q1 2026. The last published DLD site inspection, on 7 May 2026, put the tower at 76.13% complete, and no newer inspection was on the register by 23 September 2026. That date has passed, the building is not yet handed over, and Binghatti has not published a revised date.
Registered completion date (DLD)
31 Mar 2026, passed
DLD register, via Mitchells, 23 Sep 2026
Latest construction progress
76.13%
DLD site inspection, 7 May 2026
Developer's stated date
Q1 2026
Binghatti, accessed 28 Sep 2026
Revised date published
None
Binghatti, Property Finder, accessed 1 Oct 2026
Binghatti Haven handover date: the latest position
Binghatti Haven was due for completion on 31 March 2026. That is the registered completion date on the Dubai Land Department register, Property Finder lists the same date, and Binghatti’s own page still gives Q1 2026. The date has passed. The last published DLD site inspection, on 7 May 2026, recorded the tower 76.13% complete, and Binghatti has not published a revised date. More on prices and the payment plan is on the Binghatti Haven page.
By 1 October 2026 the registered date was six months behind. The register had not recorded a newer inspection by 23 September 2026, so there is no public figure for progress since May. Among Binghatti projects still under construction, Haven had the highest DLD figure on the register viewed on 24 September 2026 (Real Estate Club Dubai).
Binghatti Haven handover date by building
Binghatti Haven is a single tower, filed with the DLD as a basement, ground floor, two podium levels and 26 residential floors. The register lists 501 homes: 117 studios, 154 one bedroom, 217 two bedroom and 13 three bedroom units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Haven (single tower) | 76.13%, 7 May 2026 | 31 Mar 2026, passed | Q1 2026 (Binghatti); 31 Mar 2026 (Property Finder) |
Propsearch’s page for the building shows an estimated handover of July 2018, which does not match any other source. Propsearch also notes that the plot was first meant for Sports One Commercial Tower, a cancelled project.
How the Binghatti Haven handover date has changed
The published date has stayed at Q1 2026 while the building fell behind it.
| Date | What happened | Source |
|---|---|---|
| 17 Dec 2024 | Sales launch and DLD registered start. Expected completion 31 March 2026. | Property Finder; DLD register |
| 24 Dec 2024 | 9.6% complete at the first recorded DLD inspection. | Dubai Handover, DLD data |
| 31 Mar 2026 | Registered completion date passes without a handover. | DLD register |
| 7 May 2026 | 76.13% complete at the DLD site inspection. | DLD register, via Mitchells |
| 27 Aug 2026 | Register reading unchanged at 76%. | Real Estate Club Dubai tracker |
| 28 Sep 2026 | Binghatti’s page still lists Q1 2026, with no new date. | Binghatti |
What the Binghatti Haven handover date means for payments
Binghatti publishes a plan of 20% at booking, 50% during construction and 30% on completion. Under this plan the final 30% is linked to completion, not to the March 2026 date that has passed. On a studio at Binghatti’s AED 715,000 starting price, that final payment is AED 214,500. Portals quote different starting prices for the building, so the SPA figure is the one that sets the amount.
What to check before relying on the Binghatti Haven date
- What your SPA says about delay past 31 March 2026, including any grace period and whether it has already run out.
- A revised completion date in writing from Binghatti, since none has been published to replace Q1 2026.
- Whether a newer DLD inspection has been recorded for project number 3442, through DLD’s project status enquiry service, since the May 2026 figure is the latest public one.
- When the 30% completion payment will be called, and what notice your SPA gives before it is due.
Questions buyers also ask
Is Binghatti Haven finished?
No. The last published DLD site inspection, on 7 May 2026, put the tower at 76.13% complete, and the register still listed it as under construction on 23 September 2026 (Mitchells, DLD data).
What is the Binghatti Haven completion date?
The registered completion date is 31 March 2026, and Property Finder lists the same expected completion date. Binghatti's own page gives Q1 2026. All three have passed without a handover (accessed 1 Oct 2026).
Has the Binghatti Haven handover date been delayed?
Yes, against its own date. The 31 March 2026 completion date passed with the tower about three quarters built, and by 1 October 2026 it was six months past that date. Binghatti has not announced a replacement date.
When will Binghatti Haven be ready?
No new date has been published. The DLD register showed 76.13% on 7 May 2026 and the reading was unchanged through 27 August 2026 (Real Estate Club Dubai tracker), because no newer inspection had been recorded.