Handover date

When was Binghatti Onyx handed over?

Updated 12 October 2026 Binghatti Onyx

Short answer

Binghatti Onyx was handed over in December 2024. Binghatti announced the delivery of Onyx with five other Jumeirah Village Circle towers on 12 December 2024, and the Dubai Land Department (DLD) register records the building 100% complete with a status date of 13 December 2024. The registered completion date was 1 October 2024, so handover came about ten weeks later. Portals still disagree on the month, giving Q3 2024 (Bayut), October 2024 (Propsearch) or December 2024 (Property Finder).

Handed over

Dec 2024

Binghatti via Khaleej Times, 12 Dec 2024

Latest construction progress (DLD)

100%

DLD status date 13 Dec 2024, via Continental Club

Registered completion date (DLD)

1 Oct 2024

DLD register, project 2610, via Continental Club

Portal dates

Q3 to Dec 2024

Bayut Q3 2024; Propsearch Oct 2024; Property Finder Dec 2024

Binghatti Onyx handover date: the latest position

Binghatti Onyx was handed over in December 2024. On 12 December 2024 Binghatti announced the delivery of six Jumeirah Village Circle towers, Orchid, Amber, Onyx, House, Lavender and Venus, adding 2,062 homes in total. The Dubai Land Department register records Onyx 100% complete with a status date of 13 December 2024 and lists it as ready to move in. Prices, rents and service charges are on the Binghatti Onyx page.

The completion date Binghatti registered with DLD was 1 October 2024, so delivery came about ten weeks after it. Portals still give three different months for the same handover.

Binghatti Onyx handover date by building

Onyx is a single tower in JVC District 15, with a basement, ground floor, four podium levels and 36 typical floors, according to the DLD description.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Onyx, JVC District 15 (DLD project 2610) 100%, 13 Dec 2024 1 Oct 2024 Delivered Dec 2024 (Binghatti); Q3 2024 (Bayut); Oct 2024 (Propsearch); Dec 2024 (Property Finder)

Unit counts differ by source. The DLD register lists 507 units, made up of 342 one bedroom, 154 two bedroom and 11 other units, which are the shops. Binghatti describes 438 apartments plus 11 shops, Propsearch 449 homes, and Binghatti’s December 2024 delivery release 495 homes.

How the Binghatti Onyx handover date has changed

Date What happened Source
28 Feb 2023 Sales started, with a delivery date of 30 September 2024 and handover in Q4 2024. GI Properties broker listing
23 Mar 2023 Construction start registered with DLD. DLD register, via Continental Club
1 Oct 2024 Registered completion date. DLD register, via Continental Club
12 Dec 2024 Binghatti announced delivery of Onyx and five other JVC towers. Khaleej Times
13 Dec 2024 DLD status date at 100% complete. DLD register, via Continental Club

From sales launch to delivery took under two years. The date did not move formally; the building was finished about ten weeks after the date on file.

What the Binghatti Onyx handover date meant for payments

The developer plan was 50% down, 20% during construction and 30% on handover (Continental Club, developer supplied; Property Finder). Bayut describes a simpler 50/50 split. Either way, the final instalment fell due at handover in December 2024, and no post-handover plan was offered, so there are no developer instalments still running on Onyx units.

What to check when buying a resale unit at Binghatti Onyx

  1. The title deed against the unit type. The DLD register’s 507 units include 11 shops, and its counts of one and two bedroom homes differ from Binghatti’s, so match the deed to the layout being sold.
  2. Recent registered prices for the same layout. The DLD median for 1 bedroom units is AED 868,500 across 491 deals since 2019 (Continental Club, October 2026), and a 686 sq ft 1 bedroom sold for AED 920,000 on 17 September 2026 (Propsearch). Some rows on transaction lists are mortgage registrations, not sales.
  3. Service charge arrears. The 2026 rate is AED 17.95 per sq ft a year (DLD service charge index), and any unpaid charges pass with the unit.
  4. Snagging since 2024. Units have been occupied or let for almost two years, so the condition of fittings and balconies varies by unit.

Questions buyers also ask

What was the Binghatti Onyx handover date?

December 2024. Binghatti announced the delivery of Binghatti Onyx on 12 December 2024 (Khaleej Times), and the DLD register shows 100% complete with a status date of 13 December 2024. The completion date registered with DLD was 1 October 2024.

Is Binghatti Onyx ready to move in?

Yes. The DLD register lists the building as ready (registry updated 25 September 2026), Binghatti's own page calls it complete and ready to move, and 1 bedroom rental contracts were registering at AED 60,000 to AED 85,000 a year in September 2026 (Continental Club).

Was the Binghatti Onyx handover delayed?

Only slightly. Sales started in February 2023 with a delivery date of 30 September 2024 on broker listings, and the registered completion date was 1 October 2024. The building was delivered in December 2024, about ten weeks later.

Why do Bayut, Propsearch and Property Finder show different handover dates for Binghatti Onyx?

The portals do not say how each date was set. Bayut shows Q3 2024, close to the launch target. Propsearch shows October 2024, the month of the registered completion date. Property Finder shows December 2024, the month Binghatti announced delivery.