Handover date

When is the Binghatti Vintage handover date?

Updated 7 October 2026 Binghatti Vintage

Short answer

The Binghatti Vintage handover date is 31 March 2027, the registered completion date on the Dubai Land Department (DLD) register as at 4 October 2026. Binghatti, Property Finder and Propsearch give Q1 2027 or March 2027, and one broker listing updated on 1 September 2026 gives 31 May 2027. The only DLD inspection published, on 23 September 2025, recorded 0% before construction started, and no later percentage had been published by 4 October 2026. Four other Binghatti towers due in the first half of 2026 missed those dates and were 53% to 90% built at their last inspections, which is the main reference point for how firm the March 2027 date is.

Registered completion date (DLD)

31 Mar 2027

DLD register, project 4102, via Mitchells, 28 Sep 2026

Latest construction progress

0%

DLD inspection, 23 Sep 2025, at registration. No later figure published

Developer's stated date

Q1 2027

Developer supplied, via Continental Club, Sep 2026

Other Binghatti towers due H1 2026

4 of 4 missed

Elite, Haven, Hills, Starlight: 53% to 90% built at last DLD inspection, Apr to Jul 2026

Binghatti Vintage handover date: the latest position

Binghatti Vintage is due for completion on 31 March 2027. That is the registered completion date the Dubai Land Department holds for the tower, and Binghatti gives the same Q1 2027, with Property Finder and Propsearch listing March 2027. The register still showed that date on 4 October 2026 and no delay had been announced. One broker listing, Takween Aldar’s, updated on 1 September 2026, gives 31 May 2027 instead, two months later. Prices, plans and the building itself are covered on the Binghatti Vintage page.

What is missing is a progress figure. The DLD register shows a single inspection, on 23 September 2025, which recorded 0% eight days before construction started on 1 October 2025. No later DLD percentage had been published by the register update of 4 October 2026, and Binghatti’s site videos for May and June 2026 give no figure. With under six months left to the registered date, there is no public measure of how far the building has come.

Binghatti Vintage handover date by building

Binghatti Vintage is a single tower, so one date and one progress figure apply to every unit.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Vintage, 3 basements, ground, 4 podium and 36 residential floors, 1,572 homes (project 4102) 0%, 23 Sep 2025 (at registration, no later figure) 31 Mar 2027 Q1 2027 (developer, via Continental Club); March 2027 (Property Finder; Propsearch, 13 Aug 2026)

The register lists 1,291 studios, 238 one bedroom and 43 two bedroom homes. The registered schedule gives 18 months from construction start to completion for a building of this size.

How the Binghatti Vintage handover date has changed

The registered date has stayed at 31 March 2027 since sales opened; one broker now lists a later date.

Date What happened Source
23 Sep 2025 DLD inspection at registration recorded 0%. DLD register, via Continental Club
1 Oct 2025 Sales launched and construction start registered. Studios from AED 674,999. DLD register; Property Finder
25 Nov 2025 Bayut’s launch feature gave Q1 2027. MyBayut
5 Dec 2025 Project registered with DLD, escrow at Dubai Islamic Bank. DLD data, via HomeSearch
May to Jul 2026 Binghatti released site update videos for May and June 2026, with no percentage. JRE Dubai
1 Sep 2026 Broker listing gave an expected completion of 31 May 2027. Takween Aldar
Sep 2026 Register still showed 31 March 2027 and no new inspection. 1,192 sales registered since December 2025. DLD register, via Mitchells
4 Oct 2026 Register update: still 31 March 2027, still no inspection after registration. DLD register, via Continental Club and Mitchells

How other Binghatti handover dates have held up

With no progress figure for Vintage, the clearest guide to its date is how Binghatti’s recent towers have done against theirs. Of the four Binghatti towers with a DLD figure that were due in the first half of 2026, none was finished by its date.

Binghatti project Date given Latest DLD progress Outcome
Binghatti Elite Q2 2026; registered 30 Jun 2026 53.25%, 20 Apr 2026 Date passed
Binghatti Starlight Q1 2026; registered 31 Mar 2026 63.11%, 14 May 2026 Date passed
Binghatti Haven Q1 2026; registered 31 Mar 2026 76.13%, 7 May 2026 Date passed
Binghatti Hills Q2 2026 90%, 24 Jul 2026 Date passed
Binghatti Ghost Q1 2026 Handed over Recorded handed over 24 Sep 2026, about six months late
Binghatti Onyx Registered 1 Oct 2024 100%, 13 Dec 2024 Delivered December 2024, about ten weeks late

Vintage’s registered schedule is 18 months from construction start, for a 44 level tower with 1,572 homes. At their last inspections before or around their dates, Elite, Starlight and Haven were still 24 to 47 points short of completion. The full list of Binghatti projects and dates is on the Binghatti handover tracker.

What the Binghatti Vintage handover date means for payments

Both published plans leave 40% of the price to handover. Property Finder and Propsearch give 10% on booking, 50% during construction and 40% on handover. Bayut’s building guide of 16 January 2026 gives 14% on booking, 46% during construction and 40% on handover. On the AED 674,999 launch price for a studio, the handover payment is about AED 270,000. The 40% is tied to handover, so it moves with the completion date rather than falling on a fixed calendar date.

What to check before relying on the Binghatti Vintage date

  1. The DLD progress for project 4102, through DLD’s project status enquiry service, since no figure after registration has been republished.
  2. Which of the two payment plans your SPA follows, since they differ on the booking and construction shares.
  3. The completion date and grace period in your SPA, which is the date that applies if 31 March 2027 moves.
  4. How many similar units complete on the same date, since the tower holds 1,291 studios under one registered completion date, which can affect rents in the first months after handover.

Questions buyers also ask

What is the Binghatti Vintage completion date?

31 March 2027. This is the registered completion date on the DLD register for project 4102, and Property Finder and Propsearch list March 2027 (accessed 28 Sep and 13 Aug 2026).

Is Binghatti Vintage finished?

No. Construction started on 1 October 2025 and the building was still listed as under construction on the DLD register on 27 September 2026. The only DLD inspection published, on 23 September 2025, recorded 0%, and Binghatti's site videos from May and June 2026 give no percentage.

When will Binghatti Vintage be ready?

Binghatti and the DLD register give Q1 2027, with a registered completion date of 31 March 2027. No delay has been announced. Your SPA sets the completion date and any grace period that applies to your unit.

Has the Binghatti Vintage handover date been delayed?

No change has been published by Binghatti or on the DLD register, which still showed 31 March 2027 on 4 October 2026. One broker listing (Takween Aldar, updated 1 September 2026) gives 31 May 2027, two months later than the registered date.

Have other Binghatti projects been handed over on time?

Recent Binghatti dates have mostly slipped. Binghatti Elite, Haven, Hills and Starlight were all due in the first half of 2026 and were 53% to 90% built at their latest DLD inspections between April and July 2026. Binghatti Ghost, due Q1 2026, was recorded handed over on 24 September 2026, and Binghatti Onyx was delivered in December 2024, about ten weeks after its registered date.

How much is due at the Binghatti Vintage handover?

40% under both published plans. Property Finder and Propsearch give 10% on booking, 50% during construction and 40% on handover; Bayut's building guide of 16 January 2026 gives 14% on booking, 46% during construction and 40% on handover.

Sources