Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Binghatti Skyrise handover date?

Updated 12 October 2026 Binghatti Skyrise

Short answer

The Binghatti Skyrise handover date is 31 December 2026, the registered completion date on the Dubai Land Department (DLD) register, and Binghatti and Property Finder give the same Q4 2026. The last published DLD site inspection, on 23 April 2026, put construction at 22.4% complete, and no newer inspection was on the register by 30 September 2026. Binghatti has not revised the date, but it applies to all three towers and a large share of the build was still to be done at the last inspection.

Registered completion date (DLD)

31 Dec 2026

DLD register, via Mitchells, 8 Sep 2026

Latest construction progress

22.4%

DLD site inspection, 23 Apr 2026

Developer's stated date

Q4 2026

Binghatti, accessed 28 Sep 2026

Date change since launch

None published

Property Finder, Propsearch, DLD register, accessed 1 Oct 2026

Binghatti Skyrise handover date: the latest position

Binghatti Skyrise is due for completion on 31 December 2026. That is the registered completion date the Dubai Land Department holds for the project, and Binghatti, Property Finder and Propsearch all give the same date. The last published DLD site inspection, on 23 April 2026, recorded the project 22.4% complete, 18 months after construction started on 15 October 2024. More on prices and unit sizes is on the Binghatti Skyrise page.

At that inspection, about eight months remained to the registered date and 77.6% of the work was still to be done. No newer inspection had been added to the register by 30 September 2026, three months before the registered date, and Binghatti has not published a percentage since. It posted a site update in May 2026 without a figure.

Binghatti Skyrise handover date by building

Bayut names the three towers A, B and C, and Propsearch calls them Towers 1, 2 and 3. The DLD register counts 4 buildings, filed as three towers of 48 residential floors over a five level podium, and it publishes one figure for the whole project.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Tower A 22.4%, whole project, 23 Apr 2026 31 Dec 2026 Q4 2026 (Binghatti; Bayut)
Tower B 22.4%, whole project, 23 Apr 2026 31 Dec 2026 Q4 2026 (Binghatti; Bayut)
Tower C 22.4%, whole project, 23 Apr 2026 31 Dec 2026 Q4 2026 (Binghatti; Bayut)

The register lists 3,358 homes (as at 4 October 2026), and Binghatti’s launch release gave a mix of 2,256 studios, 996 one bedroom units, 24 two bedroom units, 26 three bedroom units and 31 shops.

How the Binghatti Skyrise handover date has changed

The date has not changed on any source checked. What has changed is the time left to meet it.

Date What happened Source
15 Oct 2024 Booking opened and the DLD registered construction start. Expected completion 31 December 2026. Property Finder; DLD register
30 Oct 2024 Public launch in Dubai. Binghatti said 50% of units sold within 24 hours. Khaleej Times; Binghatti via Zawya
9 Nov 2024 Second phase launched at an event in Giza, Egypt. Binghatti
23 Apr 2026 22.4% complete at the DLD site inspection. DLD register, via Mitchells
30 Sep 2026 Registered completion date still 31 December 2026, with no newer inspection published. Continental Club, DLD data

What the Binghatti Skyrise handover date means for payments

Binghatti and Property Finder publish a plan of 20% at booking, 50% during construction and 30% on handover, which Bayut describes as 70/30. The 30% handover payment is the largest single instalment. On a studio at the AED 975,000 launch price, it comes to AED 292,500. If handover moves beyond December 2026, that payment moves with it, while the 50% construction share is paid as the build progresses.

What to check before relying on the Binghatti Skyrise date

  1. The latest DLD percentage for project number 3349, through DLD’s project status enquiry service, since the last published figure dates from April 2026.
  2. The completion date and grace period in your SPA, which set what applies if 31 December 2026 is missed.
  3. Which tower your unit is in, because Binghatti has not said whether Towers A, B and C will be completed together.
  4. What triggers the 30% handover payment in your SPA, such as a completion notice, and how much notice it gives.

Questions buyers also ask

What is the Binghatti Skyrise completion date?

31 December 2026. This is the registered completion date for DLD project number 3349, and Binghatti, Property Finder and Propsearch give the same date (accessed 1 Oct 2026).

Is Binghatti Skyrise finished?

No. The last published DLD site inspection, on 23 April 2026, recorded 22.4% complete. The register still listed the project as under construction on 30 September 2026 (Continental Club, DLD data).

Has the Binghatti Skyrise handover date been delayed?

Not officially. Binghatti launched Skyrise on 30 October 2024, and its own page, Property Finder and the DLD register all still give 31 December 2026. No revised date had been published by 1 October 2026.

Do all three Binghatti Skyrise towers hand over together?

The DLD register holds one completion date and one progress figure for the whole project, which it describes as three 48 floor towers on a shared podium. Binghatti has not published separate dates for each tower.

How much is due at the Binghatti Skyrise handover?

30% of the price, under the 20/50/30 plan published by Binghatti and Property Finder. On a studio at the AED 975,000 launch price, that is AED 292,500.

Sources

  1. Propsearch, Binghatti Skyrise (opens in a new tab)propsearch.ae · updated 13 Aug 2026
Request a Unit Review