When is the Azizi Riviera handover date?

Updated 1 October 2026 Azizi Riviera

Short answer

Azizi Riviera has no single handover date: Phases 1 to 3 were completed between 2019 and 2023, Azizi gives Q4 2026 for Rêve, and the newer numbered towers have registered completion dates of 13 March 2027 or 30 May 2027. At DLD inspections between 30 July and 7 September 2026, those newer towers were between 54.40% (Riviera 49) and 91.02% (Riviera 66) complete, and Riviera 55, 56 and 58 were recorded as 100% complete, while Azizi put Rêve at 79% on 16 July 2026. Rêve was first due in October 2024, and Azizi's August 2025 target of Q2 2026 for all remaining buildings was not met.

Registered completion date (DLD), newer towers

13 Mar or 30 May 2027

Riviera 49 to 68, DLD register via Mitchells Commercial Realty, Sep 2026

Latest construction progress, Rêve

79%

Azizi, 16 Jul 2026

Developer's stated date, Rêve

Q4 2026

Azizi, 16 Jul 2026

Rêve date change since launch

Oct 2024 to Q4 2026

Property Finder (launch date); Azizi (current date)

Azizi Riviera handover date: the latest position

Azizi Riviera is a community of 75 buildings in Meydan One, so the handover date depends on the building. Phases 1 to 3 were completed between 2019 and 2023, and Propsearch counted 55 buildings as completed on 23 September 2026. The two groups still being built are Rêve, which Azizi gives for Q4 2026, and a set of newer numbered towers with registered completion dates of 13 March 2027 or 30 May 2027. Prices, rents and service charges are on the Azizi Riviera page.

Azizi reported Rêve at 79% complete on 16 July 2026. At DLD inspections between 30 July and 7 September 2026, the newer towers still under construction ranged from 54.40% (Riviera 49) to 91.02% (Riviera 66). Riviera 55, 56 and 58 were recorded at 100%, ahead of their registered 2027 dates.

Azizi Riviera handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Phases 1 to 3 Completed Passed Completed 2019 to 2023 (Propsearch)
Riviera 61, 63, 65, 67, Azure Completed Passed Handed over Mar to Aug 2025 (Azizi)
Riviera 69, Beachfront I Completed Passed Handed over Mar 2026, 667 homes (Azizi)
Riviera 55 100%, 19 Jan 2026 13 Mar 2027 Listed as handed over (Real Estate Club Dubai tracker, 28 Sep 2026)
Riviera 56 100%, 28 Apr 2026 13 Mar 2027 Listed as handed over (Real Estate Club Dubai tracker, 28 Sep 2026)
Riviera 58 100%, 17 Aug 2026 30 May 2027 May 2027 (Property Finder)
Riviera 66 91.02%, 7 Aug 2026 30 May 2027 May 2027 (Property Finder)
Riviera 62 90.80%, 30 Jul 2026 13 Mar 2027 Not listed
Riviera 64 83.82%, 7 Sep 2026 30 May 2027 May 2027 (Property Finder)
Riviera 54 74.64%, 7 Aug 2026 30 May 2027 May 2027 (Property Finder)
Riviera 68 74.56%, 7 Aug 2026 30 May 2027 May 2027 (Property Finder)
Riviera 53 63.19%, 30 Jul 2026 13 Mar 2027 Early 2027 (Property Finder)
Riviera 49 54.40%, 7 Aug 2026 13 Mar 2027 Mar 2027 (Property Finder)
Rêve (3 towers) 79%, 16 Jul 2026 (Azizi figure) Not published Q4 2026 (Azizi)

DLD figures are from the register as republished by Mitchells Commercial Realty. Rêve’s figure is Azizi’s own. Data Habibi lists Rêve at 77%, without an inspection date.

How the Azizi Riviera handover date has changed

Date What happened Source
11 Sep 2017 Launch: Phases 1 and 2 due in the second half of 2018 The Gulf Time
18 Mar 2022 Crystal lagoon due as early as Q1 or Q2 2023 Azizi via Gulf News
1 Jul 2022 Rêve launched, completion listed for 30 Oct 2024 Property Finder
24 Aug 2022 First seven Phase 1 buildings inaugurated, 1,164 homes Azizi via Zawya
8 Aug 2025 53 of 75 buildings handed over; remaining 22 due by Q2 2026 Azizi
27 Sep 2025 Rêve 56% complete Azizi via UAE Insider
31 Mar 2026 Riviera 69 and Beachfront I handed over; Phase 4 at 74% Azizi
5 Jun 2026 Rêve 65% complete Azizi via Invest Dubai Today
16 Jul 2026 Rêve 79% complete, due Q4 2026 Azizi via Zawya
23 Sep 2026 55 buildings completed, 18 under construction, 2 planned Propsearch

Rêve’s date has moved about two years from its launch listing. The newer numbered towers were registered with DLD in March and May 2025, and several are ahead of their 2027 registered dates.

What the Azizi Riviera handover date means for payments

Riviera plans put most of the price at handover, so the date matters for cash flow. Property Finder lists Rêve on 10% down, 30% during construction and 60% on handover, or 10%, 40% and 50%. The newer numbered towers list 10% down with 70% to 75% on handover, and some units use 20% down with 80% on handover (Property Finder; Propsearch, 2026). On a Rêve unit at AED 1.5 million, the launch entry price reported by Propsearch, 60% is AED 900,000 due at handover.

What to check before relying on the Azizi Riviera date

  1. The building number on the SPA. Riviera 49 and Riviera 55 share the same registered date, 13 March 2027, but were 54% and 100% built at their latest 2026 inspections.
  2. For Rêve, the SPA date and grace period. The launch listing gave 30 October 2024, so the time since then counts against any grace period in older Rêve contracts.
  3. For towers at 100%, the handover notice. A 100% inspection is not the same as keys. The large handover payment falls due with the notice.
  4. Lagoon-facing units. The lagoon’s completion has not been confirmed by Azizi, so views and access described at sale may not yet be in place.

Questions buyers also ask

Is Azizi Riviera finished?

Not all of it. Propsearch counted 55 of Riviera's 75 buildings as completed, 18 under construction and 2 planned on 23 September 2026. Phases 1 to 3 are complete, and Riviera 69 and Beachfront I were handed over in March 2026 (Azizi, 31 Mar 2026).

When will Azizi Riviera Rêve be completed?

Azizi gives Q4 2026. It reported Rêve at 79% complete on 16 July 2026, with the structure finished and façade works at 69%. Property Finder lists the original completion date as 30 October 2024.

What is the Azizi Riviera lagoon completion date?

In March 2022 Azizi said the 2.7 km crystal lagoon would be delivered as early as Q1 or Q2 2023 (Gulf News, 18 Mar 2022). Azizi's 27 September 2025 Rêve update still described the lagoon in the future tense, and its 2026 Riviera releases do not report it as complete. The Rêve towers and the Beachfront buildings sit on the lagoon, and Rêve is due in Q4 2026.

Has the Azizi Riviera handover date been delayed?

For some buildings, yes. Phases 1 and 2 were due in the second half of 2018 at launch and completed from 2019. Rêve moved from October 2024 to Q4 2026. In August 2025 Azizi said the remaining 22 buildings would complete by Q2 2026, and Propsearch still counted 18 under construction in September 2026.

Which Azizi Riviera buildings are still under construction?

On the DLD register in September 2026: Riviera 49, 53, 54, 62, 64, 66 and 68, plus Rêve. Riviera 55, 56 and 58 were recorded at 100% (DLD inspections, January to August 2026).

Sources