When is the Azizi Gabriel handover date?
Short answer
Azizi Gabriel has a registered completion date of 4 July 2028 on the Dubai Land Department (DLD) register, while Bayut and Propsearch show Q4 2028. The only DLD inspection published, on 17 November 2025, recorded 0%, and no later figure had appeared by 6 October 2026. With no published progress almost a year after launch, the July 2028 date is untested.
Registered completion date (DLD)
4 Jul 2028
DLD register via Continental Club, updated 6 Oct 2026
Latest construction progress
0%
DLD inspection, 17 Nov 2025
Developer's stated date
Q3 2028
Developer-supplied date via Continental Club; none in the launch release
Portal estimate
Q4 2028
Bayut; Propsearch estimates Dec 2028
Azizi Gabriel handover date: the latest position
The Dubai Land Department (DLD) register lists Azizi Gabriel’s completion date as 4 July 2028. Bayut shows Q4 2028 and Propsearch estimates December 2028, so the portals sit later than the register. See the Azizi Gabriel project page for prices, sizes and the payment plan.
The register shows a single inspection, on 17 November 2025, at 0%. No later inspection had been published when the register was updated on 6 October 2026, so there is no independent figure for any work since launch.
Azizi Gabriel handover date by building
Azizi Gabriel is one 15 storey building in Downtown Jebel Ali with 234 registered units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Azizi Gabriel (DLD project 4232) | 0% (17 Nov 2025) | 4 Jul 2028 | Q3 2028 (developer-supplied, via Continental Club); Q4 2028 (Bayut); December 2028 (Propsearch) |
How the Azizi Gabriel handover date has changed
| Date | What happened | Source |
|---|---|---|
| 4 Nov 2025 | Azizi launches Gabriel; no completion date in the release | MENAFN (Mid-East Info) |
| Nov 2025 | Planned construction start on the DLD record | Data Habibi |
| 13 Nov 2025 | Propsearch lists the building as planned, estimated handover December 2028 | Propsearch |
| 17 Nov 2025 | DLD inspection: 0% | Continental Club |
| 6 Oct 2026 | Register shows completion 4 July 2028, no newer inspection | Continental Club |
| 8 Oct 2026 | Broker listing gives the handover date as “on request” | OffPlan Insider |
The date has not moved, but it has not been tested either: the register shows no progress since launch. Azizi’s wider guidance is that handovers across its projects run “through 2026 and into 2027” (GDN, 15 September 2026), and its Azizi Venice buildings missed the Q1 2026 date given in October 2025.
What the Azizi Gabriel handover date means for payments
Half the price is due at handover. The plan is 20% on booking, three 10% instalments at 300, 450 and 600 days after booking, and 50% on handover (OffPlan Insider, 8 October 2026). On a AED 564,000 studio, AED 282,000 falls due at handover. For buyers who booked at launch in November 2025, the 300 day instalment fell due around September 2026 and the 600 day instalment falls around June 2027, regardless of progress on site.
What to check before relying on the Azizi Gabriel date
- Whether a DLD inspection above 0% has been published, through DLD’s project status service, before paying the next instalment.
- The completion date and grace period in the SPA, compared with the register date of 4 July 2028.
- How the 300, 450 and 600 day instalments line up with progress, since they are tied to the booking date, not to construction stages.
- Mortgage options for the 50% handover payment, since banks lend against the finished unit.
Questions buyers also ask
When will Azizi Gabriel be ready?
The DLD register gives 4 July 2028. Bayut lists Q4 2028 and Propsearch estimates December 2028.
What is the Azizi Gabriel completion date?
4 July 2028 is the completion date on the DLD register for project 4232.
Has the Azizi Gabriel handover date been delayed?
No change has been announced. Azizi gave no date in its launch release of 4 November 2025, and the register date has stayed at 4 July 2028. The concern is progress: the only DLD inspection published recorded 0%.
Has construction started at Azizi Gabriel?
No DLD figure shows it. The inspection of 17 November 2025 recorded 0%, and no later inspection had been published by 6 October 2026. Data Habibi lists a planned construction start of November 2025.