Azizi Gabriel
Azizi Gabriel in Downtown Jebel Ali: completion date 4 July 2028 on the DLD register, Q4 2028 on portals, 0% at the only DLD inspection. Studios from AED 564,000 on a 20/30/50 plan.
Short answer
Azizi Gabriel, a 15 storey Azizi Developments building of studios and 1 and 2 bedroom apartments in Downtown Jebel Ali, has a registered completion date of 4 July 2028 on the Dubai Land Department (DLD) register. Bayut and Propsearch show Q4 2028. The only DLD inspection published, on 17 November 2025, recorded 0%, and no later figure had appeared by 6 October 2026. It launched on 4 November 2025 with studios from AED 564,000 on a 20/30/50 plan.
- Status
- off-plan
- Handover date
- Registered completion date 4 Jul 2028 (DLD); Q4 2028 on Bayut and Propsearch
- Construction
- 0% (DLD inspection, 17 Nov 2025; no later inspection published)
- Payment plan
- 20% on booking, 30% in three 10% instalments, 50% on handover
- Starting price
- From AED 564,000 (studio, launch Nov 2025)
Registered completion date
4 Jul 2028
DLD register via Continental Club, updated 6 Oct 2026
Construction progress
0%
Only DLD inspection, 17 Nov 2025
Starting price at launch
AED564,000
Studio, Propsearch and OffPlan Insider
Median studio price paid
AED590,040
117 DLD sales, via Continental Club, Oct 2026
When will Azizi Gabriel be handed over?
The Dubai Land Department (DLD) register gives Azizi Gabriel a completion date of 4 July 2028. Portals show a later date: Bayut lists Q4 2028 and Propsearch estimates December 2028. Azizi did not state a completion date in its launch announcement of 4 November 2025. Continental Club records the developer-supplied date as Q3 2028, in line with the register.
The register entry for the project, number 4232, shows one DLD inspection, on 17 November 2025, which recorded 0%. No later inspection had been published by 6 October 2026. Construction start dates on third-party copies of the register differ, so the progress on site is not confirmed by any published DLD figure.
Building-by-building dates and how the date has changed: Azizi Gabriel handover date.
Azizi Gabriel construction update
Data Habibi lists a planned construction start of November 2025. The 17 November 2025 inspection, two weeks after launch, found the plot at 0%. The escrow account is held with Ajman Bank. Propsearch’s last update, on 13 November 2025, still described the building as planned. The declared project value is AED 74,542,000 (Propsearch).
Azizi Gabriel homes and sizes
Propsearch describes a 15 storey building with retail at the base. The DLD register holds 234 units.
| Home type | Units (DLD) | Size (DLD register) | Starting price |
|---|---|---|---|
| Studio | 162 | 333 to 340 sq ft | AED 564,000 |
| 1 bedroom | 56 | 596 to 675 sq ft | AED 829,000 |
| 2 bedroom | 7 | 1,090 sq ft | AED 1,580,000 |
Nine further units are listed as other types. Prices are from OffPlan Insider, 8 October 2026. Azizi lists separate gyms for men and women, pools for adults and children, a cinema, a gaming lounge and a multipurpose hall. The building sits near Jebel Ali Free Zone and the Life Pharmacy metro station on Sheikh Zayed Road.
Azizi Gabriel prices and resale
The DLD has registered 165 sales, all from the developer (Continental Club, October 2026). Median prices paid are AED 590,040 for studios (117 sales) and AED 877,920 for 1 bedrooms (47 sales). A 340 sq ft studio registered at AED 585,060 on 31 July 2026, or AED 1,722 per sq ft (Propsearch). Recent registered sales of studios and 1 bedrooms ranged from about AED 564,000 to AED 886,000. There have been no resales yet.
Azizi Gabriel payment plan
The plan is 20/30/50: 20% on booking, then three instalments of 10% at 300, 450 and 600 days after booking, and 50% on handover (OffPlan Insider, 8 October 2026). Bayut shows the same split. On a AED 564,000 studio, that is AED 112,800 at booking, AED 169,200 in instalments and AED 282,000 at handover, plus the 4% DLD fee of AED 22,560 at booking.
Azizi Gabriel developer and delivery record
Azizi says it has delivered more than 45,000 homes, handed over 7 projects in 2026 and targets 10 more by the end of the year (GDN, 15 September 2026). Several of its buildings finished months after the first date given, and its Azizi Venice buildings missed a Q1 2026 date. More detail is in the Azizi Developments review.
What to check before buying at Azizi Gabriel
- Evidence that work has started on site, such as a DLD inspection above 0%, before the 300 day instalment falls due.
- The completion date in the SPA, since the register says 4 July 2028 and portals say Q4 2028.
- Funding for the 50% handover payment, which is the largest single payment on this plan.
- The number of similar studios in the building: 162 of 234 units are studios of about 333 to 340 sq ft.
Azizi Gabriel location: Downtown Jebel Ali, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Azizi Gabriel handover date?
The DLD register lists a completion date of 4 July 2028. Bayut gives Q4 2028 and Propsearch estimates December 2028. Azizi's launch announcement of 4 November 2025 did not give a date (DLD register via Continental Club, inspection 17 Nov 2025).
What is the Azizi Gabriel completion date?
4 July 2028 on the DLD register for project 4232. Continental Club records the developer-supplied date as Q3 2028, which matches.
What is the Azizi Gabriel price?
Studios start from AED 564,000, 1 bedrooms from AED 829,000 and 2 bedrooms from AED 1.58 million (OffPlan Insider, 8 Oct 2026). Median DLD registered prices are AED 590,040 for studios and AED 877,920 for 1 bedrooms.
What is the Azizi Gabriel payment plan?
20% on booking, then three instalments of 10% at 300, 450 and 600 days from booking, and 50% on handover (OffPlan Insider, 8 Oct 2026; Bayut).
Has construction started at Azizi Gabriel?
The only DLD inspection published, on 17 November 2025, recorded 0%. Data Habibi gives a planned construction start of November 2025, but no DLD progress figure above zero had been published by 6 October 2026.