Handover date

When was Azizi Central handed over?

Updated 6 October 2026 Azizi Central

Short answer

Azizi Central was handed over from July 2026, when Azizi announced it had begun handing over the 97 apartments. The Dubai Land Department (DLD) inspection of 8 June 2026 recorded the building as 100% complete. Azizi had given Q4 2025 through 2025 and Q1 2026 in January 2026, so completion came about two quarters after the first date.

Registered completion (DLD)

100%, 8 Jun 2026

DLD register, project 2721, via Continental Club; finished status recorded 9 Jun 2026 (Real Estate Club Dubai)

Latest construction progress

100%

DLD inspection, 8 Jun 2026

Developer's stated date

Handover began Jul 2026

Azizi Developments, July 2026

Date change since 2025

Q4 2025 to Q2 2026

Azizi, 24 Jan 2025; DLD, 8 Jun 2026

Azizi Central handover date: the latest position

Azizi Central in Al Furjan is complete and handed over. The DLD inspection of 8 June 2026 recorded 100% for project number 2721 (Continental Club), and the finished status was recorded in the register on 9 June 2026 (Real Estate Club Dubai). Azizi announced in July 2026 that it had officially begun handing over the 97 apartments. Prices, rents and unit sizes are on the Azizi Central page.

The building finished later than Azizi’s 2025 target of Q4 2025, and later than the Q1 2026 it gave in January 2026. Resales and the first rental contracts were registering by August 2026.

Azizi Central handover date by building

Azizi Central is a single building.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Azizi Central (UG+G+2P+9+R, 97 apartments) 100%, 8 Jun 2026 Finished status recorded 9 Jun 2026 Handover began July 2026 (Azizi); Q2 2026 (Continental Club)

How the Azizi Central handover date has changed

Date What happened Source
3 Aug 2023 Registered construction start. DLD register, via Continental Club
29 Dec 2023 Project registered with the DLD. DLD register, via Homesearch
24 Jan 2025 21% complete; handover expected Q4 2025. Azizi, via Zawya
2 May 2025 35% complete; handover scheduled Q4 2025. Azizi, via CBNME
31 Jan 2026 77% complete; handover scheduled Q1 2026. Azizi, via Mid-East.info
10 Apr 2026 98% complete, finishes at 99%. Azizi, via Mid-East.info
8 Jun 2026 100% at the DLD inspection. DLD register, via Continental Club
Jul 2026 Handover officially begins. Azizi, via Mid-East.info, 22 Jul 2026

The last stretch moved quickly. In January 2026 Azizi reported tiling at 81%, MEP at 85% and finishes at 67%, with 322 workers on site. By April 2026 MEP was at 98%, the façade at 97% and finishes at 99%, with 320 workers. Azizi described Azizi Central as its 21st completed project in Al Furjan (Azizi, 24 July 2026), and it handed over in a year in which Azizi says it completed seven projects by mid September (GDN, 15 September 2026).

What the Azizi Central handover date means for payments

Continental Club lists a 40/60 plan: 10% on booking, 30% during construction and 60% on handover at 100% completion. The delay from Q4 2025 to mid 2026 pushed that 60% payment back by about two quarters. With handover under way since July 2026, the payment is now due for buyers on this plan. There is no post-handover portion listed.

What to check before relying on the Azizi Central date

  1. Whether the seller has paid the 60% handover instalment, when buying a resale unit soon after handover.
  2. That the Oqood has been converted to a title deed, which is needed for a transfer or a mortgage.
  3. The unit count in any listing. Azizi and the DLD give 97 apartments; one tracker shows 257, which does not match.

Questions buyers also ask

What is the Azizi Central completion date?

The DLD inspection of 8 June 2026 recorded 100%, and the finished status was recorded in the DLD register on 9 June 2026 (Continental Club; Real Estate Club Dubai). Azizi began the handover in July 2026.

Is Azizi Central finished?

Yes. The building is complete on the DLD register, and Azizi announced in July 2026 that it had officially begun handing over units and welcoming its first residents.

Was the Azizi Central handover delayed?

Yes, by about two quarters. Azizi gave Q4 2025 in January and May 2025, then Q1 2026 in January 2026, when the building was 77% complete. Completion was recorded in June 2026.

How much was due at the Azizi Central handover?

On the plan listed by Continental Club, 60% of the price was due on handover, after 10% on booking and 30% during construction.