When is the Azizi Beach Oasis handover date?
Short answer
Azizi Beach Oasis 2, the phase still to hand over, has a registered completion date of 30 April 2026 on the Dubai Land Department (DLD) register, and Azizi gave Q2 2026 when sales opened in April 2024. The DLD inspection of 7 September 2026 recorded it 53.22% complete, and no revised date has been published. Beach Oasis 1, the first phase, is finished: Azizi began its handover in December 2025.
Registered completion date, Beach Oasis 2 (DLD)
30 Apr 2026, passed
DLD register, via Mitchells, 23 Sep 2026
Latest construction progress, Beach Oasis 2
53.22%
DLD site inspection, 7 Sep 2026
Developer's stated date, Beach Oasis 2
Q2 2026
Developer supplied, via Continental Club, registry 25 Sep 2026. No revised date published
Beach Oasis 1
Handed over
Handover began Dec 2025 (Azizi via TradeArabia, 24 Dec 2025)
Azizi Beach Oasis handover date: the latest position
Beach Oasis 2, the phase still to hand over, has a registered completion date of 30 April 2026, and that date has passed. The DLD site inspection of 7 September 2026 recorded the project 53.22% complete, and Azizi has not published a revised date. Beach Oasis 1, on the neighbouring plot, is finished and handed over. More on prices and the payment plan is on the Azizi Beach Oasis page.
Progress on phase 2 has been steady but slow against the original date. The DLD recorded 40.65% at its inspection of 3 February 2026 and 53.22% on 7 September 2026, a gain of 12.57 points in about seven months, or roughly 1.8 points a month. Azizi’s own figures run lower than the DLD’s: it reported 32% on 3 February 2026 and 43% on 22 April 2026, with the structure 99% complete.
Azizi Beach Oasis handover date by building
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Beach Oasis 2, Tower A | 53.22%, whole project, 7 Sep 2026 | 30 Apr 2026 | Q2 2026 (developer, via Continental Club); Apr 2026 (Property Finder) |
| Beach Oasis 2, Tower B | 53.22%, whole project, 7 Sep 2026 | 30 Apr 2026 | Q2 2026 (developer, via Continental Club); Apr 2026 (Property Finder) |
| Beach Oasis 1 | Complete | Not applicable | Handover began Dec 2025 (Azizi); completed Jan 2026 (Propsearch) |
The DLD register holds Beach Oasis 2 as one project, number 3043, with 704 homes in two towers of 8 floors on a shared 2 basement and ground level. It publishes one progress figure for both towers. Azizi gives the phase 2 mix as 452 studios, 209 one bedroom and 33 two bedroom homes. For phase 1, sources disagree on size: Azizi’s handover release counts 762 homes, Propsearch 712.
How the Azizi Beach Oasis handover date has changed
| Date | What happened | Source |
|---|---|---|
| 14 Oct 2022 | Beach Oasis 1 sales event. | Propsearch |
| 15 Apr 2024 | Beach Oasis 2 booking opened. Registered completion date 30 April 2026. | Property Finder; DLD register |
| May 2024 to Nov 2024 | Phase 1 handover given as Q1 2025, then Q2 2025, then Q3 2025. | Azizi, via Propsearch |
| 17 Nov 2025 | Phase 2 at 18%, structure 69%. | Azizi |
| 24 Dec 2025 | Azizi began handing over Beach Oasis 1. Phase 2 at nearly 20%. | Azizi via TradeArabia |
| 3 Feb 2026 | Phase 2 at 40.65% (DLD inspection); Azizi gave 32% the same day. | DLD register; Azizi |
| 22 Apr 2026 | Phase 2 at 43%, structure 99%. Azizi said it was on schedule. | Azizi |
| 30 Apr 2026 | Registered completion date for phase 2 passed. | DLD register |
| 7 Sep 2026 | Phase 2 at 53.22% (DLD inspection). Register still shows 30 April 2026. | DLD register, via Mitchells and Continental Club |
What the Azizi Beach Oasis handover date means for payments
Property Finder lists the phase 2 plan as 10% down payment, 40% during construction and 50% on handover. On the AED 604,000 launch price it lists, half the price, AED 302,000, falls due at handover, so the later handover also moves the largest payment later. Phase 1 launched on a different plan, 40% during construction and 60% on handover (Propsearch). With phase 1 handed over, that final 60% has now fallen due for its owners.
What to check before relying on the Azizi Beach Oasis date
- Which phase the unit is in. Beach Oasis 1 is ready and occupied; a Beach Oasis 2 unit in Tower A or Tower B is still about half built.
- The completion date and grace period in the SPA. The registered date of 30 April 2026 has passed, so the grace period written into the SPA decides what applies until Azizi sets a new date.
- Which payment plan the unit was sold on. The 50% or 60% handover share sets how much is due when keys are released.
- The inspection figure for project 3043, through DLD’s project status service. Dubai Handover notes that DLD’s daily headline figure for the project showed an invalid 188.8% in September 2026, so the dated inspection figure is the one to read.
Questions buyers also ask
When will Azizi Beach Oasis 2 be ready?
No new date has been published. The registered completion date on the DLD register is 30 April 2026, which has passed, and the DLD inspection of 7 September 2026 recorded Beach Oasis 2 at 53.22% complete. Azizi's last update, on 22 April 2026, gave 43% and said the project was on schedule.
What is the Azizi Beach Oasis completion date?
Beach Oasis 1 is complete. Azizi began its handover in December 2025, and Propsearch records completion in January 2026. Beach Oasis 2 has a registered completion date of 30 April 2026 (DLD project 3043), but was 53.22% built on 7 September 2026.
Is Azizi Beach Oasis finished?
Phase 1 is finished and occupied. Phase 2, two 8 floor towers with 704 homes, is still under construction, at 53.22% on 7 September 2026 (DLD register, via Continental Club).
Has the Azizi Beach Oasis handover date been delayed?
Both phases have run late. Phase 1 was first estimated for Q1 2025, revised to Q3 2025 and finished in January 2026 (Propsearch). Phase 2 passed its 30 April 2026 registered completion date at about half built, and the register had not been updated by 25 September 2026.
How much is due at the Azizi Beach Oasis 2 handover?
Property Finder lists a 10/40/50 plan for phase 2: 10% down payment, 40% during construction and 50% on handover. On the AED 604,000 launch price it lists, the handover payment is AED 302,000 (accessed 1 Oct 2026).