Handover date

When was Azizi Vista handed over?

Updated 6 October 2026 Azizi Vista

Short answer

Azizi Vista was handed over in October 2025. Azizi announced the start of handover on 22 October 2025, after the Dubai Land Department (DLD) recorded the building 100% complete at an inspection on 30 August 2025 and logged completion on 30 September 2025 (Mitchells Commercial Realty, register as at 23 Sep 2026). The date moved several times before that: Azizi gave Q3 2024 in January 2024, Q2 2025 later that year and Q3 2025 in March 2025, and the registered completion date on file is 30 April 2025.

Handover began

22 Oct 2025

Azizi, via Zawya

Construction progress (DLD inspection, 30 Aug 2025)

100%

DLD register, project 2650; completion recorded 30 Sep 2025

Registered completion date (DLD)

30 Apr 2025

DLD register, via Mitchells Commercial Realty

Earliest date Azizi gave

Q3 2024

Azizi, Jan 2024, via Propsearch

Azizi Vista handover date: the latest position

Azizi Vista is finished and handed over. Azizi announced the start of handover on 22 October 2025. The Dubai Land Department register had recorded the building 100% complete at a site inspection on 30 August 2025 and logged its completion on 30 September 2025. Prices, sizes and rents are on the Azizi Vista page.

The register also still carries a registered completion date of 30 April 2025, the date filed before the last delay. That date was not met, but it no longer matters for buyers: the project status is Completed, and 78 sales were registered from May 2025 to September 2026, at a median AED 1,375 per sq ft (Mitchells Commercial Realty, register as at 23 Sep 2026).

Azizi Vista handover date by building

Azizi Vista is one DLD project, number 2650, with a single building of a basement, ground, 8 floors and roof in the Al Hebiah Second area of Dubai Studio City.

Building Construction progress (DLD) Registered completion date Developer or portal date
Azizi Vista (163 homes) 100%, inspection 30 Aug 2025; completion recorded 30 Sep 2025 30 Apr 2025 Handover from 22 Oct 2025 (Azizi); Q4 2025 (Property Finder)

How the Azizi Vista handover date has changed

Azizi moved its target three times before the building was finished. Each update came with a higher construction figure but a later date.

Date What was reported Source
27 Apr 2023 Registered construction start DLD register
Jan 2024 23% complete, on track for Q3 2024 Azizi, via Propsearch
Sep 2024 56% complete, completion due Q2 2025 Azizi, via Propsearch
Dec 2024 71% complete, handover expected Q2 2025 Azizi, via Propsearch
Mar 2025 86% complete, handover moved to Q3 2025 Azizi, via Propsearch
30 Aug 2025 100% at DLD inspection DLD register
30 Sep 2025 Completion recorded DLD register
22 Oct 2025 Azizi begins handover Azizi, via Zawya

Propsearch also records Q4 2024 as the estimated handover at launch, which differs from the Q3 2024 date in Azizi’s January 2024 update. Either way, handover came about a year after the first target. From the registered start in April 2023, the building took two and a half years.

What the Azizi Vista handover date meant for payments

Azizi sold Vista on a 40% during construction, 60% on handover plan (Propsearch; Property Finder). The larger share was therefore tied to the handover, which moved from 2024 into late 2025. On a studio bought at the AED 585,000 launch price recorded by Propsearch, AED 234,000 was paid during construction and AED 351,000 fell due at handover in October 2025. No post-handover instalments were published, so the handover payment closed out the developer plan.

What to check when buying a resale unit at Azizi Vista

  1. The handover date on the seller’s documents. Handover ran from 22 October 2025, so the seller’s handover certificate shows when service charges and the defects liability period started for that unit.
  2. That the 60% handover payment was made. A seller who has paid it should hold a title deed rather than an Oqood.
  3. Which launch price a listing compares against. Propsearch gives AED 585,000 and Property Finder AED 1.2 million, so a quoted gain since launch depends on which figure is used.
  4. The DLD project status for project 2650, through the DLD project status enquiry, which shows the Completed status and the inspection photos.

Questions buyers also ask

What is the Azizi Vista handover date?

Azizi Vista is already handed over. Azizi began the handover on 22 October 2025 (Zawya). The DLD register records the building 100% complete at its 30 August 2025 inspection and completed on 30 September 2025.

What is the Azizi Vista completion date?

The DLD register holds two dates. The registered completion date on file is 30 April 2025, and the recorded completion is 30 September 2025, after the 100% inspection of 30 August 2025 (Mitchells Commercial Realty). Propsearch dates completion to October 2025.

Was Azizi Vista delayed?

Yes, by about a year against the earliest date. Azizi said Q3 2024 in January 2024, Q2 2025 in September and December 2024, and Q3 2025 in March 2025. Handover started on 22 October 2025 (Propsearch; Zawya).

What was the Azizi Vista payment plan at handover?

40% during construction and 60% on handover (Propsearch; Property Finder). On a AED 585,000 launch price, that put AED 351,000 due at handover in late 2025. No post-handover plan was published.