Handover date

When was Azizi Pearl handed over?

Updated 6 October 2026 Azizi Pearl

Short answer

Azizi Pearl was handed over in June 2024. The Dubai Land Department (DLD) register gives a registered completion date of 5 June 2024 and records the building 100% complete at an inspection on the same day (Mitchells Commercial Realty, register as at 4 Oct 2026). Azizi had said in December 2023 that the building was 80% built and due in Q1 2024, so it finished a few months late, nearly seven years after construction started in July 2017.

Registered completion date (DLD)

5 Jun 2024

DLD register, via Mitchells Commercial Realty and Continental Club

Construction progress (DLD inspection, 5 Jun 2024)

100%

DLD register, project 1917

Developer's last stated date

Q1 2024

Azizi, Dec 2023 update at 80% built, via Propsearch

Time from construction start to completion

About 7 years

Registered start 1 Jul 2017 (DLD)

Azizi Pearl handover date: the latest position

Azizi Pearl is finished and handed over. The Dubai Land Department register gives it a registered completion date of 5 June 2024, and a DLD site inspection on the same day recorded the building 100% complete. Property Finder shows 5 June 2024 as its completion date, and fäm Properties lists Q2 2024. Prices, sizes and rents are on the Azizi Pearl page.

The building is now a resale and rental market only. Every sale registered at the DLD between May 2025 and August 2026 was recorded as a sale after completion, at a median AED 1,503 per sq ft across 27 sales (Mitchells Commercial Realty, register as at 4 Oct 2026).

Azizi Pearl handover date by building

Azizi Pearl is one DLD project, number 1917, with one building in the Jabal Ali First planning area of Al Furjan.

Building Construction progress (DLD) Registered completion date Developer or portal date
Azizi Pearl 100%, inspection 5 Jun 2024 5 Jun 2024 Q1 2024 (Azizi, Dec 2023); Q2 2024 (fäm Properties)

The register files it as a hotel apartment building of ground, 2 podium levels, 7 floors and a roof, with 223 homes. Azizi’s marketing and Propsearch give 260 units, so the counts differ. DLD transaction records list units in the building as hotel apartments.

How the Azizi Pearl handover date has changed

Azizi Pearl took almost seven years from the registered start to completion. Most of the building went up in its last 12 months.

Date Event Source
1 Jul 2017 Registered construction start DLD register
Aug 2023 31% complete, 70% of units sold Azizi, via Propsearch
Oct 2023 50% complete, structure 99% done Azizi, via Propsearch
Dec 2023 80% complete, completion due by end of Q1 2024 Azizi, via Propsearch
5 Jun 2024 100% at DLD inspection; registered completion date DLD register
Sep 2024 Azizi reports all units sold Day of Dubai, 24 Sep 2024

Against the Q1 2024 date Azizi gave in December 2023, completion came about two months late.

What the Azizi Pearl handover date meant for payments

Most of the price fell due at handover. Propsearch records the launch plan as 30% during construction and 70% on handover, and Property Finder also lists 70% on handover. For buyers on that plan, the final 70% became payable around June 2024. No post-handover plan was published for Azizi Pearl, so the handover payment was the last developer instalment.

What to check when buying a resale unit at Azizi Pearl

  1. How the unit is classed. The DLD lists units in Azizi Pearl as hotel apartments, not ordinary flats. That classification can affect mortgage terms and how the unit may be let.
  2. That the developer price is fully paid. With 70% due at handover in 2024, a seller should hold a title deed, not an Oqood (the off-plan registration certificate).
  3. The unit count behind any yield figure. The DLD’s 223 homes and the 260 in marketing material give different pictures of supply in the building.
  4. The defects liability period. Snagging claims on common parts and the unit are tied to the June 2024 completion date.

Questions buyers also ask

What is the Azizi Pearl handover date?

Azizi Pearl has already been handed over. Its registered completion date on the DLD register is 5 June 2024, and a DLD inspection on that date recorded the building 100% complete (Mitchells Commercial Realty; Continental Club, accessed 6 Oct 2026).

What is the Azizi Pearl completion date?

5 June 2024, per the DLD register. Property Finder shows the same date as its completion date, and fäm Properties lists completion as Q2 2024.

Was Azizi Pearl delivered on time?

A few months late. Azizi said in December 2023, with the building 80% complete, that it was due by the end of Q1 2024. The DLD recorded completion on 5 June 2024 (Propsearch; DLD register).

When did construction of Azizi Pearl start?

The DLD register gives a registered start of 1 July 2017. Progress was slow for years: Azizi reported 31% in August 2023, then 50% in October 2023 and 80% in December 2023 (Propsearch).

How many units are in Azizi Pearl?

Sources differ. The DLD register lists 223 homes in one building, while Azizi's marketing and Propsearch give 260 units. The register describes it as a hotel apartment building of ground, 2 podium, 7 floors and roof.

Sources

  1. Propsearch, Azizi Pearl (opens in a new tab)propsearch.ae · updated 15 Jul 2026, accessed 6 Oct 2026
  2. fäm Properties, Azizi Pearl (opens in a new tab)famproperties.com · accessed 6 Oct 2026
Request a Unit Review