Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Azizi Rose handover date?

Updated 11 October 2026 Azizi Rose

Short answer

Azizi Rose has a registered completion date of 4 July 2028 with the Dubai Land Department (DLD); portals including Data Habibi and DirectDXB now show Q4 2028. The only published DLD inspection, on 16 February 2026, recorded 0% complete, before the registered construction start of 4 July 2026. Published dates range from Q1 2028 to Q4 2028, so the SPA date for each unit is the one that applies.

Registered completion date (DLD)

4 Jul 2028

DLD register via Mitchell's, as at 4 Oct 2026

Construction progress

0%

DLD inspection, 16 Feb 2026

Developer date, latest

Q4 2028

Data Habibi; DirectDXB, 23 Sep 2026

Change since launch

Q3 2028 to Q4 2028

Data Habibi

Azizi Rose handover date: the latest position

Azizi Rose has a registered completion date of 4 July 2028 on the DLD project register, and portals now show Q4 2028 as the developer’s handover date. Details of the building, prices and plan are on the Azizi Rose page.

The register gives a construction start of 4 July 2026, but the only published DLD inspection, on 16 February 2026, recorded 0% complete. No newer inspection had appeared by 11 October 2026, so there is no public figure yet showing how far work has moved since the registered start.

Azizi Rose handover date by building

Azizi Rose is one 14 storey building with 226 studios and 1 bedroom apartments, registered as a single DLD project (number 4403) to Azizi Developments. Its DLD area is Jabal Ali Industrial Second, the land registry name for Downtown Jebel Ali.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Azizi Rose (project 4403) 0% (16 Feb 2026) 4 Jul 2028 Q4 2028 (Data Habibi; DirectDXB, 23 Sep 2026); Q3 2028 (Continental Club); Q1 2028 (Propsearch, 29 Jun 2026)

How the Azizi Rose handover date has changed

Date Event Source
7 Jan 2026 Azizi announces the launch, studios from about AED 607,000 Azizi
16 Feb 2026 DLD inspection records 0% DLD register via Continental Club
29 Jun 2026 Propsearch lists Q1 2028 Propsearch
4 Jul 2026 Registered construction start DLD register via Mitchell’s
Sep 2026 Developer date shown as Q4 2028, up from Q3 2028 Data Habibi; DirectDXB

The registered completion date has stayed at 4 July 2028. The marketed date has moved one quarter later, from Q3 2028 to Q4 2028, according to Data Habibi.

What the Azizi Rose handover date means for payments

Half of the price is due on handover under the 10/40/50 plan. The four construction instalments are tied to time, not progress: they fall at 30, 300, 450 and 600 days from booking (OffPlan Insider, 8 October 2026). A buyer who booked at launch in January 2026 would have paid 50% by about September 2027, with the final 50% due at completion in 2028. On a studio at the DLD median of AED 617,760, that final payment is about AED 309,000.

What to check before relying on the Azizi Rose date

  1. The date written in the SPA, since sources range from Q1 2028 to Q4 2028 and the register says 4 July 2028.
  2. The next DLD inspection result after the registered 4 July 2026 start, through DLD’s project status service.
  3. Whether the grace period in the SPA would push the handover payment into 2029 if the Q4 2028 date also moves.

Questions buyers also ask

What is the Azizi Rose completion date?

The DLD register holds 4 July 2028 for project 4403, two years after the registered construction start of 4 July 2026 (Mitchell's, register as at 4 October 2026).

Has construction started at Azizi Rose?

The register lists the project as under construction, but the only published inspection, on 16 February 2026, recorded 0%. No later inspection had been published by 11 October 2026.

Has the Azizi Rose handover date been delayed?

Data Habibi records the developer's date moving from Q3 2028 to Q4 2028, a change of one quarter. The DLD registered date of 4 July 2028 has not changed.

Why do Propsearch and other portals show different Azizi Rose dates?

Propsearch, last updated on 29 June 2026, shows Q1 2028. Continental Club shows Q3 2028 as the developer date, and Data Habibi and DirectDXB show Q4 2028. Each portal updates at different times.

Sources

  1. DLD project register via Mitchell's, Azizi Rose (opens in a new tab)mitchellscommercialrealty.com · register as at 4 Oct 2026
  2. Data Habibi, Azizi Rose (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026
  3. Propsearch, Azizi Rose (opens in a new tab)propsearch.ae · updated 29 Jun 2026
Request a Unit Review