When is the Azizi Lina handover date?
Short answer
The Dubai Land Department (DLD) register holds a completion date of 30 September 2028 for Azizi Lina in Downtown Jebel Ali, and Property Finder shows the same date. The latest DLD inspection, on 18 March 2026, recorded 2% construction progress. Some broker pages still show Q4 2027, nine months earlier than the register.
Registered completion date (DLD)
30 Sep 2028
DLD register via Mitchell's, 4 Oct 2026
Latest construction progress
2%
DLD inspection, 18 Mar 2026
Developer's stated date
Q3 2028
Developer supplied, via Continental Club, Oct 2026
Earlier broker date
Q4 2027
JRE, ezre.ae and A1 Properties, accessed 11 Oct 2026
Azizi Lina handover date: the latest position
The Dubai Land Department (DLD) project register holds 30 September 2028 as the completion date for Azizi Lina (project number 4141). The latest published DLD inspection, on 18 March 2026, recorded 2% construction progress. Prices, sizes and the payment plan are on the Azizi Lina page.
Property Finder lists the same September 2028 date, and Continental Club records Q3 2028 as the developer supplied date. Some broker pages, such as JRE, ezre.ae and A1 Properties, still show Q4 2027.
Azizi Lina handover date by building
Azizi Lina is a single building of 242 registered units. It is registered separately from Azizi’s other towers in Downtown Jebel Ali. For comparison, Azizi Arian nearby has a registered completion date of 16 January 2028 and was also 2% complete at its DLD inspection on 24 March 2026.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Azizi Lina | 2%, 18 Mar 2026 | 30 Sep 2028 | Q3 2028 (developer, via Continental Club); Sep 2028 (Property Finder); Q4 2027 (JRE, ezre.ae) |
How the Azizi Lina handover date has changed
| Date | Event | Source |
|---|---|---|
| 22 Sep 2025 | Azizi launches Azizi Lina; no handover date in the published release | Mid-East.info |
| 14 Oct 2025 | First DLD inspection, no progress recorded | DLD register via Continental Club |
| 3 Feb 2026 | Registered construction start; Property Finder lists bookings from this date | DLD register; Property Finder |
| 18 Mar 2026 | DLD inspection, 2% complete | DLD register via Mitchell’s |
| Oct 2026 | Register and Property Finder show 30 Sep 2028; some broker pages still list Q4 2027 | Mitchell’s; Property Finder; JRE; ezre.ae |
The Q4 2027 date on those listings would have meant a build of under two years from the February 2026 start. The registered date allows about 32 months. From the 18 March 2026 inspection, the remaining 98% would need about 3 percentage points a month to finish by 30 September 2028.
What the Azizi Lina handover date means for payments
The common plan is 10% on booking, 40% during construction in four 10% instalments, and 50% on handover. Half of the price is therefore tied to completion. On the AED 601,000 launch price studio, the handover payment is AED 300,500. A buyer who planned for that payment in late 2027 would, on the registered date, make it in late 2028 instead. No post-handover plan is listed.
What to check before relying on the Azizi Lina date
- Which date the SPA states, Q4 2027 or 30 September 2028.
- Whether the four construction instalments are linked to progress or to calendar dates. With 2% recorded in March 2026, this decides how quickly they fall due.
- Azizi’s recent delivery pace. Azizi reported 7 projects handed over in 2026 by mid September, with 10 more targeted by year end (GDN, 15 September 2026).
- The next DLD inspection for project 4141 on the Dubai REST app, since no figure newer than March 2026 had been published by early October.
Questions buyers also ask
When will Azizi Lina be completed?
The DLD registered completion date is 30 September 2028. Construction was registered as starting on 3 February 2026 and was 2% complete at the DLD inspection of 18 March 2026.
Is the Azizi Lina handover in 2027 or 2028?
The register and Property Finder say 30 September 2028. Q4 2027 still appears on broker pages such as JRE, ezre.ae and A1 Properties, but it does not match the register.
Has the Azizi Lina handover date been delayed?
Azizi has not announced a change. Some broker pages show Q4 2027, while the register, with construction starting in February 2026, gives 30 September 2028.
Is Azizi Lina part of another Azizi project?
No. It is a single building registered on its own (DLD project 4141). Azizi has several separate towers in Downtown Jebel Ali, including Azizi Arian, registered for 16 January 2028.