When was Azizi Mirage 1 handed over?
Short answer
Azizi Mirage 1 was handed over from December 2025. The Dubai Land Department (DLD) register recorded the project 100% complete at an inspection on 14 October 2025, against a registered completion date of 30 April 2025 (Mitchells Commercial Realty; Continental Club). The register entry, 762 homes in two buildings, matches Beach Oasis I, which Azizi built on the plot first launched as Azizi Mirage 1 and began handing over on 24 December 2025 (Azizi via TradeArabia; Propsearch).
Construction progress (DLD inspection, 14 Oct 2025)
100%
DLD register, project 2034
Registered completion date (DLD)
30 Apr 2025
DLD register, via Mitchells Commercial Realty
Handover began
24 Dec 2025
Azizi, Beach Oasis I, 762 homes, via TradeArabia
Dates given before completion
Q1 2025, then Q2 and Q3 2025
Azizi updates for Beach Oasis, via Propsearch
Azizi Mirage 1 handover date: the latest position
Azizi Mirage 1 is finished and handed over. The Dubai Land Department register lists it as Completed, with 100% recorded at a site inspection on 14 October 2025. Azizi began handing over the 762 homes on the plot on 24 December 2025, under the Beach Oasis I name. Prices and sizes are on the Azizi Mirage 1 page.
The registered completion date on file is 30 April 2025, which is the date portals such as Property Finder show. It passed about six months before the building reached 100%, and the register has not replaced it. Continental Club’s copy of the register, updated 5 October 2026, lists the project as ready to move in.
Azizi Mirage 1 handover date by building
The DLD holds Azizi Mirage 1 as one project, number 2034, with two buildings on a shared ground floor and two basement levels.
| Building | Construction progress (DLD) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Tower 1 (ground, 9 floors, roof) | 100%, inspection 14 Oct 2025 | 30 Apr 2025 | Handover from 24 Dec 2025 (Azizi, Beach Oasis I) |
| Tower 2 (ground, 8 floors, roof) | 100%, inspection 14 Oct 2025 | 30 Apr 2025 | Handover from 24 Dec 2025 (Azizi, Beach Oasis I) |
The DLD publishes one figure for both towers. Its count of 762 homes in two buildings is the same as Azizi’s count for Beach Oasis I: 508 studios, 218 one bedroom and 36 two bedroom homes. Propsearch records that Beach Oasis was built on the plot first intended for Azizi Mirage 1, and gives a lower count of 712 units.
How the Azizi Mirage 1 handover date has changed
The plot has a long history. Azizi announced Mirage 1 in March 2018 as an eight storey building of 186 one, two and three bedroom apartments. The scheme was later replanned as Beach Oasis, a mostly studio project, which held a sales event on 14 October 2022.
| Date | What was reported | Source |
|---|---|---|
| 1 Feb 2018 | Registered construction start | DLD register |
| 20 Mar 2018 | Mirage 1 announced, 186 apartments | Azizi, via FM Middle East |
| 14 Oct 2022 | Beach Oasis sales event on the same plot | Propsearch |
| May 2024 | 20% complete, handover planned Q1 2025 | Azizi, via Propsearch |
| Aug 2024 | 33% complete, handover Q2 2025 | Azizi, via Propsearch |
| Nov 2024 | 55% complete, handover Q3 2025 | Azizi, via Propsearch |
| Aug 2025 | 94% complete | Propsearch |
| 14 Oct 2025 | 100% at DLD inspection | DLD register |
| 24 Dec 2025 | Azizi begins handover of 762 homes | Azizi, via TradeArabia |
Measured against the Q1 2025 date Azizi gave in May 2024, handover came about nine months late.
What the Azizi Mirage 1 handover date meant for payments
Two plans are on record for this plot. Property Finder and Continental Club list the 2018 Mirage 1 plan of 1% down, 49% during construction and 50% on handover. Propsearch records the Beach Oasis plan as 40% during construction and 60% on handover. Under either plan, half or more of the price fell due when keys were handed over from December 2025. No post-handover plan has been published for either.
What to check when buying a resale unit at Azizi Mirage 1
- Which name the title deed uses. The DLD records the project as Azizi Mirage 1, while Azizi markets the same homes as Beach Oasis I. Listings may use either.
- That the unit is in project 2034, not Beach Oasis 2. Beach Oasis 2 is a separate DLD project next door that was still under construction in September 2026.
- The seller’s handover date. Keys were handed over from 24 December 2025, so service charges and the defects liability period run from that unit’s handover, not from the 30 April 2025 date on file.
- That the handover payment was made. A seller with a title deed has paid the developer in full; one with only an Oqood may not have.
Questions buyers also ask
What is the Azizi Mirage 1 handover date?
It has been handed over. The DLD recorded the project 100% complete on 14 October 2025, and Azizi began handing over the 762 homes on this plot, marketed as Beach Oasis I, on 24 December 2025 (DLD register via Mitchells; Azizi via TradeArabia).
What is the Azizi Mirage 1 completion date?
The registered completion date on the DLD register is 30 April 2025. That date passed before the building was finished; the DLD inspection of 14 October 2025 recorded it 100% complete. Property Finder shows 30 April 2025 as its expected completion.
Is Azizi Mirage 1 the same as Azizi Beach Oasis?
The DLD project called Azizi Mirage 1 matches Beach Oasis I. Both are two buildings with 762 homes on the same Studio City plot, and Propsearch records that Beach Oasis was built on the plot first intended for Azizi Mirage 1. Beach Oasis 2 is a separate DLD project, still under construction.
Was Azizi Mirage 1 delivered late?
Yes. Azizi announced Mirage 1 in March 2018. For the Beach Oasis scheme built on the plot, Azizi gave Q1 2025 in May 2024, Q2 2025 in August 2024 and Q3 2025 in November 2024. The DLD recorded 100% in October 2025 and handover began in December 2025.