When is the Azizi Arian handover date?
Short answer
The Azizi Arian handover date is 16 January 2028, the registered completion date on the Dubai Land Department (DLD) register, and Property Finder gives the same January 2028. The DLD site inspection of 24 March 2026 put construction at 2% complete, and no later inspection had been published by 26 September 2026. Some broker pages still show the launch target of Q4 2026, which DataHabibi records as moved back 15 months to Q1 2028.
Registered completion date (DLD)
16 Jan 2028
DLD register, via Mitchells, 23 Sep 2026
Latest construction progress
2%
DLD site inspection, 24 Mar 2026
Portal date
Q1 2028
Property Finder, accessed 1 Oct 2026
Date change since launch
Q4 2026 to Q1 2028
15 months later, DataHabibi, accessed 1 Oct 2026
Azizi Arian handover date: the latest position
Azizi Arian is due for completion on 16 January 2028. That is the registered completion date the Dubai Land Department holds for the tower, and Property Finder gives the same January 2028. The DLD site inspection of 24 March 2026 recorded the building 2% complete, 14 months after the registered construction start of 16 January 2025. More on prices and the tower itself is on the Azizi Arian page.
The earlier inspection on 21 January 2025 recorded no progress, so the 2% figure is the only movement on the register so far (Continental Club, DLD data). No newer inspection had been published by 26 September 2026. Azizi has not given its own date, and some broker pages still show the Q4 2026 date used at launch.
Azizi Arian handover date by building
Azizi Arian is a single tower. The DLD register describes it as three basements, a ground floor, a mezzanine, five podium levels, 15 residential floors and a roof, with 555 homes. Property Finder gives a higher count of 623 apartments.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Azizi Arian (one tower, 555 homes) | 2%, 24 Mar 2026 | 16 Jan 2028 | Q1 2028 (Property Finder, 1 Oct 2026); Q4 2026 (Propsearch, 20 Nov 2025) |
How the Azizi Arian handover date has changed
Launch listings gave Q4 2026. The registered date has stayed at 16 January 2028 in every register check since, and the main portals now match it.
| Date | What happened | Source |
|---|---|---|
| 16 Jan 2025 | Booking opened and the DLD registered construction start. Launch listings gave Q4 2026. | Property Finder; DLD register; DataHabibi |
| 21 Jan 2025 | DLD inspection records no progress. | DLD data, via Continental Club |
| Apr 2025 | Azizi says 75% of units have sold. | Azizi, via Propsearch |
| 20 Nov 2025 | Propsearch still shows Q4 2026. | Propsearch |
| 24 Mar 2026 | 2% complete at the DLD site inspection. | DLD register, via Mitchells |
| Sep 2026 | Registered completion date 16 January 2028. Property Finder shows January 2028; DataHabibi records a 15 month move from Q4 2026 to Q1 2028. | Mitchells, 23 Sep 2026; Property Finder; DataHabibi |
What the Azizi Arian handover date means for payments
Property Finder lists three plans, all with 10% at launch. Two put 40% into construction, one of them in four instalments, and 50% on handover. The third puts 30% into construction in three instalments and 60% on handover. Half or more of the price is therefore due at handover. On the median registered price of AED 613,000 (Mitchells, DLD sales to 7 September 2026), the handover payment is AED 306,500 on the 50% plans and AED 367,800 on the 60% plan. If the 16 January 2028 date moves, that payment moves with it.
What to check before relying on the Azizi Arian date
- Which date your SPA states. Units sold early in 2025 were marketed with Q4 2026, while the register holds 16 January 2028. The SPA date and its grace period are what apply.
- What triggers the construction instalments. Ask whether the 30% or 40% construction payments are tied to calendar dates or to DLD progress milestones, since the tower was at 2% in March 2026.
- The escrow bank for project number 3510. Mitchells reproduces Commercial Bank International from the DLD register, while Continental Club shows ADCB. Confirm the account in the Dubai REST app before paying.
- Whether a newer DLD inspection exists. The 2% figure is from 24 March 2026, more than six months old by October 2026.
Questions buyers also ask
What is the Azizi Arian completion date?
16 January 2028. This is the registered completion date on the DLD register for project number 3510, and Property Finder lists the same expected completion date of 16 January 2028 (Mitchells, 23 Sep 2026; Property Finder, accessed 1 Oct 2026).
Is Azizi Arian finished?
No. The DLD register records construction starting on 16 January 2025, and its site inspection of 24 March 2026 put the tower at 2% complete. No newer inspection had been published by 26 September 2026 (Continental Club, DLD data).
Has the Azizi Arian handover date been delayed?
Against the launch marketing, yes. Early listings gave Q4 2026, and DataHabibi records the target moving to Q1 2028, a 15 month change. Azizi has not published a statement on the change. The registered date of 16 January 2028 is three years after the registered construction start.
When will Azizi Arian be ready?
On the DLD register, by 16 January 2028. With the tower at 2% in March 2026, nearly all of the building was still to be built at that inspection, so the next DLD figures are the best guide to whether that date holds.
How much is due at the Azizi Arian handover?
50% or 60% of the price, depending on the plan. Property Finder lists 10% at launch, 40% during construction and 50% on handover, and a second option of 10%, 30% and 60% (accessed 1 Oct 2026).