When is the Azizi Milan handover date?
Short answer
Azizi Milan has no single handover date: the Dubai Land Department (DLD) register gives each tower its own registered completion date, from 26 March 2027 for Milan 51 to 8 September 2028 for Milan Heights, and Property Finder lists June 2028 (Q2 2028) for the district. The last DLD inspections on record for these towers, from April to September 2025, each recorded 0%, and no newer DLD figure had been published by September 2026. Azizi said on 18 June 2026 that 16 buildings with close to 10,000 homes were advancing on schedule, but it has not published dates or percentages for them.
Registered completion dates (DLD)
26 Mar 2027 to 8 Sep 2028
8 towers, DLD register via Mitchells, status as at 23 Sep 2026
Latest construction progress
0%
Last DLD inspections on record, 2 Apr to 10 Sep 2025
Developer's stated date
Not published
Azizi, 18 Jun 2026, said 16 buildings were on schedule without giving dates
Portal estimate
Jun 2028 (Q2 2028)
Property Finder, district page, accessed 1 Oct 2026
Azizi Milan handover date: the latest position
Azizi Milan has no single handover date. The Dubai Land Department (DLD) register gives each tower its own registered completion date, from 26 March 2027 for Milan 51 to 8 September 2028 for Milan Heights, and Property Finder lists June 2028, or Q2 2028, for the district. Prices, sizes and payment plans are on the Azizi Milan page.
The register shows no construction progress for these towers. The last DLD inspections on record, from 2 April to 10 September 2025, each recorded 0%, and no newer inspection had been published by September 2026. On 18 June 2026 Azizi’s project director said 16 buildings with close to 10,000 homes were advancing on schedule and that the project structure had evolved, without giving dates or percentages.
Azizi Milan handover date by tower
The towers below are the Azizi Milan buildings found on the DLD register, all filed by Azizi Developments in Wadi Al Safa 4.
| Tower (DLD project, homes) | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Milan 51 (3643, 579) | 0%, 2 Apr 2025 | 26 Mar 2027 | Not published |
| Milan 30 (3656, 629) | 0%, 7 Apr 2025 | 4 Apr 2027 | Not published |
| Milan 18 (3694, 1,541) | 0%, 23 Apr 2025 | 16 Apr 2027 | Not published |
| Milan 20 (3662, 741) | 0%, 8 Apr 2025 | 30 Apr 2027 | Not published |
| Milan 53 (3695, 306) | 0%, 21 Apr 2025 | 30 Apr 2027 | Jun 2028 (Property Finder) |
| Milan 9 (3735, 991) | 0%, 6 May 2025 | 30 May 2027 | Q2 2027 (Continental Club) |
| Milan 28 (3817, 629) | 0%, 10 Jun 2025 | 3 Jun 2027 | Not published |
| Milan Heights (4079, 2,852 in 5 buildings) | 0%, 10 Sep 2025 | 8 Sep 2028 | May 2028 (Propsearch) |
Each registered completion date sits about two years after its registered construction start, except Milan Heights, at three years. These eight entries hold 8,268 homes, against the 81,200 Azizi announced for the district in April 2025 and the close to 10,000 in 16 buildings it described in June 2026.
How the Azizi Milan handover date has changed
No change to a registered completion date has been recorded, but the dates in circulation have spread.
| Date | What happened | Source |
|---|---|---|
| 26 Mar 2025 | Milan 51 construction start registered, due 26 March 2027. | DLD register, via Mitchells |
| 23 Apr 2025 | Azizi launched Milan: 81,200 homes, AED 75 billion. | Azizi, via Business Wire |
| Apr to Jun 2025 | Six more towers registered, due April to June 2027. All inspected at 0%. | DLD register, via Mitchells |
| 8 Sep 2025 | Milan Heights registered, due 8 September 2028. Inspected at 0% on 10 September 2025. | DLD register, via Mitchells |
| 1 Oct 2025 | Construction start for the district on Property Finder, with completion on 1 June 2028. | Property Finder |
| 18 Jun 2026 | Azizi: 16 buildings and close to 10,000 homes advancing on schedule; project structure has evolved. | Azizi |
| Sep 2026 | Register still shows the 2025 inspections at 0% and the original dates. | DLD register, via Mitchells |
What the Azizi Milan handover date means for payments
Plans differ by tower. Property Finder lists 10% at launch, 50% during construction and 40% on handover for some towers, and 10%, 60% and 30% for others. Continental Club lists Milan 9 at 10% on booking, 40% during construction and 50% on handover at 100% completion. On a studio from AED 560,000, a 40% handover payment is AED 224,000, and a 50% one is AED 280,000. With 30% to 50% tied to handover, a large share of the price moves with the completion date.
What to check before relying on the Azizi Milan date
- Which tower your unit is in and its DLD project number. Registered dates run from 26 March 2027 to 8 September 2028.
- Whether your tower is among the 16 buildings Azizi says are under way, since Azizi said in June 2026 that the project structure had evolved.
- The completion date and grace period in your SPA, compared with the registered date, since the 2027 dates fall 6 to 8 months after October 2026, with 0% recorded at the last inspections.
- A current DLD inspection figure, through DLD’s project status enquiry service, before paying the next construction instalment.
Questions buyers also ask
What is the Azizi Milan completion date?
It depends on the tower. The DLD register gives 26 March 2027 for Milan 51, 4 April 2027 for Milan 30, 16 April 2027 for Milan 18, 30 April 2027 for Milan 20 and Milan 53, 30 May 2027 for Milan 9, 3 June 2027 for Milan 28 and 8 September 2028 for Milan Heights. Property Finder lists June 2028 for the district.
When will Azizi Milan be ready?
Azizi has not published a handover date. Seven of the eight towers checked have registered completion dates in March to June 2027, but their last DLD inspections, from 2025, recorded 0%. Property Finder gives June 2028 for the district and for Milan 53.
Has construction started at Azizi Milan?
The DLD register lists construction starts from 26 March 2025 to 8 September 2025, and Property Finder gives 1 October 2025 for the district. The DLD inspections on record all recorded 0%, the newest on 10 September 2025. Azizi said on 18 June 2026 that 16 buildings were advancing on schedule.
Has the Azizi Milan handover date been delayed?
No change to any registered date has been recorded. Portals already show later dates than the register, for example June 2028 for Milan 53 on Property Finder against a registered 30 April 2027, and Azizi said in June 2026 that the project structure had evolved.
How much is due at the Azizi Milan handover?
It depends on the tower. Property Finder lists plans with 40% or 30% due on handover, and Continental Club lists 50% on handover for Milan 9. On a studio from AED 560,000, a 40% handover payment is AED 224,000.