Handover date

When is the Azizi Emerald handover date?

Updated 11 October 2026 Azizi Emerald

Short answer

Azizi Emerald has a registered completion date of 13 February 2028, and the developer date is Q1 2028. The Dubai Land Department inspection of 24 March 2026 recorded it 3% complete. The date is about eight months later than the June 2027 handover marketed at launch, and the pace so far is far below what the registered date needs.

Registered completion date

13 Feb 2028

DLD project register via Continental Club and Mitchells

Latest construction progress

3%

DLD inspection, 24 Mar 2026

Developer's stated date

Q1 2028

Developer supplied, via Continental Club

Handover marketed at launch

June 2027

Prelaunch.ae (15 May 2025), Propsearch

Azizi Emerald handover date: the latest position

Azizi Emerald is registered with the Dubai Land Department (DLD) for completion on 13 February 2028, and the developer date shown by Continental Club is Q1 2028. Prices, unit sizes and the payment plan are on the project page: Azizi Emerald.

The last DLD inspection, on 24 March 2026, recorded 3%. The building gained 3 points in the 13 months after the first inspection on 3 March 2025. To reach 13 February 2028 it would need about 4.3 points a month from March 2026. No newer DLD reading had been published by early October 2026.

Azizi Emerald handover date by building

Azizi Emerald is one office and retail building registered as “Azizi Emerald” with 102 units in Umm Hurair Second, the DLD district for Dubai Healthcare City (DHCC).

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Azizi Emerald (DLD project 3566, 102 units, 3B+G+4P+11+R) 3% (24 Mar 2026) 13 Feb 2028 Q1 2028 (developer, via Continental Club); June 2027 (Propsearch, FHI Global); Q2 2027 (Tanami Properties)

How the Azizi Emerald handover date has changed

Date Event Source
30 Jan 2025 Azizi announces the launch of Azizi Emerald, its first commercial building Zawya
13 Feb 2025 Registered construction start; completion registered for 13 Feb 2028 DLD register via Mitchells
3 Mar 2025 DLD inspection: 0% DLD register via Continental Club
15 May 2025 Marketed with handover in June 2027 Prelaunch.ae
24 Mar 2026 DLD inspection: 3% DLD register via Continental Club
25 Apr 2026 Propsearch still shows June 2027 Propsearch
Oct 2026 Developer date Q1 2028; registered date unchanged Continental Club

The registered date of 13 February 2028 was on file from the start of construction, so the June 2027 date used in 2025 marketing was always earlier than the DLD record. Buyers who relied on broker pages may have expected handover about eight months sooner.

What the Azizi Emerald handover date means for payments

The plan is 10% on booking, four instalments of 10% at about 60, 240, 420 and 600 days after booking, and 50% on handover at 100% completion (Top Luxury Property). On an office at the AED 5.28 million launch price, the handover payment is about AED 2.64 million. The construction instalments are fixed by date, so the full 50% before handover falls due within about 20 months of booking, whatever the building’s progress.

What to check before relying on the Azizi Emerald date

  1. The completion date written in the SPA, compared with the June 2027 date used by brokers and the registered 13 February 2028.
  2. The next DLD reading. At 3% in March 2026, the register will show whether the tower has moved past basement works.
  3. That the listing is for Azizi Emerald in DHCC (DLD project 3566). Some broker pages describe an “Azizi Emerald” with apartments in Al Jaddaf, which does not match the commercial building on the register.

Questions buyers also ask

Is Azizi Emerald finished?

No. The DLD inspection of 24 March 2026 recorded 3%. The registered completion date is 13 February 2028.

What is the Azizi Emerald completion date?

13 February 2028 on the DLD register (project 3566), three years after the registered construction start of 13 February 2025.

Has the Azizi Emerald handover date been delayed?

Against the launch marketing, yes. Brokers advertised June 2027 or Q2 2027 in 2025. The register and the developer date now point to Q1 2028. Azizi has not published a statement on the change.

When will Azizi Emerald offices be ready to use?

Not before completion, registered for 13 February 2028. After completion, owners still need the unit handed over and any DHCC licensing for their business.

Sources

  1. DLD project register via Continental Club, Azizi Emerald (opens in a new tab)continentalclub.ae · inspection 24 Mar 2026; registry updated 8 Oct 2026
  2. Mitchells, Azizi Emerald: DLD registry and registered sales (opens in a new tab)mitchellscommercialrealty.com · registry as at 4 Oct 2026
  3. Propsearch, Azizi Emerald (opens in a new tab)propsearch.ae · updated 25 Apr 2026
  4. FHI Global, Azizi Emerald (opens in a new tab)fhiglobal.ae · accessed 11 Oct 2026