
When is the Azizi Zain handover date?
Short answer
Azizi Zain has a registered completion date of 11 October 2027 with the Dubai Land Department (DLD), and portals now show Q4 2027. The latest DLD inspection, on 30 June 2026, recorded 66.21% complete. Earlier marketed dates of Q4 2025 (Property Finder) and Q1 2026 (Data Habibi) have passed, so SPAs signed early may carry an older date.
Registered completion date (DLD)
11 Oct 2027
DLD register via Continental Club, project 3335
Construction progress
66.21%
DLD inspection, 30 Jun 2026
Developer date, latest
Q4 2027
Data Habibi, accessed 11 Oct 2026
Original promise
Q1 2026
Data Habibi; Property Finder shows Q4 2025
Azizi Zain handover date: the latest position
Azizi Zain has a registered completion date of 11 October 2027 on the DLD project register, and Data Habibi shows Q4 2027 as the current developer target. Prices, sizes and the plan are on the Azizi Zain page.
The latest DLD inspection, on 30 June 2026, recorded 66.21% complete, up from 53.40% on 28 January 2026. At that pace, about 2.6 percentage points a month, the remaining work would take about 13 months from June 2026, which fits the registered date.
Azizi Zain handover date by building
Azizi Zain is one 12 storey building with 115 apartments, registered as a single DLD project. The register lists 18 one bedroom, 79 two bedroom and 18 three bedroom units, in the land registry area of Jabal Ali First.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Azizi Zain (project 3335) | 66.21% (30 Jun 2026); 53.40% (28 Jan 2026) | 11 Oct 2027 | Q4 2027 (Data Habibi); Oct 2027 (Projects Scout); Q4 2025 (Property Finder summary) |
How the Azizi Zain handover date has changed
| Date | Event | Source |
|---|---|---|
| Before 2024 | Earlier version of the project on the plot, estimated handover once January 2022 | Propsearch |
| 11 Oct 2024 | Registered construction start; completion filed for 11 Oct 2027 | DLD register via Mitchell’s |
| At launch | Marketed for Q4 2025 (Property Finder) or Q1 2026 (Data Habibi) | Property Finder; Data Habibi |
| 28 Jan 2026 | DLD inspection records 53.40% | DLD register via Continental Club |
| 30 Jun 2026 | DLD inspection records 66.21% | DLD register via Continental Club |
| Oct 2026 | Portals show Q4 2027 | Data Habibi |
The marketed date has moved by about 21 months, from Q1 2026 to Q4 2027, according to Data Habibi. The registered date has stayed at 11 October 2027 since the 2024 registration, so the earlier marketed dates were always ahead of the register.
What the Azizi Zain handover date means for payments
Under the 10/40/50 plan, half of the price is due on handover (Data Habibi). For a 2 bedroom at the DLD median of AED 1,515,360, that is about AED 758,000, now likely to fall due in late 2027 rather than the 2025 or 2026 dates some buyers were first given. Buyers on older SPAs may find that their contract handover date has already passed.
What to check before relying on the Azizi Zain date
- The date in the SPA against 11 October 2027. Contracts signed when Q4 2025 or Q1 2026 was marketed may differ from the register.
- Any rights in the SPA once its stated date has passed, including the grace period it allows.
- The next DLD inspection after 30 June 2026, through DLD’s project status service, to confirm the pace has held.
Questions buyers also ask
Is Azizi Zain finished?
No. The latest DLD inspection, on 30 June 2026, recorded 66.21% complete. The registered completion date is 11 October 2027.
What is the Azizi Zain completion date?
11 October 2027 on the DLD register, three years after the registered start on 11 October 2024 (Mitchell's, register as at 4 October 2026).
Has the Azizi Zain handover date been delayed?
Yes, against earlier marketed dates. Data Habibi records a postponement of 21 months from Q1 2026 to Q4 2027, and Property Finder's summary still shows Q4 2025. The registered date of 11 October 2027 is the one now shown by most portals.
Will Azizi Zain be ready before October 2027?
Possibly, but no early date has been announced. Progress rose by about 2.6 percentage points a month in the first half of 2026; at that pace the remaining work would take about 13 months from June 2026.


