Handover date

When is the Azizi Neila handover date?

Updated 11 October 2026 Azizi Neila

Short answer

Azizi Neila in Al Furjan has a registered completion date of 30 July 2027 on the Dubai Land Department (DLD) register, and Property Finder lists July 2027. The DLD inspection of 5 October 2026 recorded 38.53% construction progress, up from 17.05% on 13 April 2026. To finish on time the building must add about 61 points in under ten months, faster than its pace so far.

Registered completion date (DLD)

30 Jul 2027

DLD register via Continental Club, 9 Oct 2026

Latest construction progress

38.53%

DLD inspection, 5 Oct 2026

Portal date

Jul 2027

Property Finder, accessed 11 Oct 2026

Progress in six months

+21.48 points

17.05% on 13 Apr 2026 to 38.53% on 5 Oct 2026

Azizi Neila handover date: the latest position

The Dubai Land Department (DLD) project register holds a registered completion date of 30 July 2027 for Azizi Neila, project number 3203, in Al Furjan. Property Finder lists the same month. More on prices and homes is on the Azizi Neila page.

The DLD inspection of 5 October 2026 recorded 38.53% construction progress. That is the newest inspection, and the biggest single step so far: 21.48 points in less than six months.

Azizi Neila handover date by building

Azizi Neila is one building with 274 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Azizi Neila (274 units) 38.53%, 5 Oct 2026 30 Jul 2027 July 2027 (Property Finder)

Progress and dates are from the DLD register as republished by Continental Club, registry updated 9 October 2026.

How the Azizi Neila handover date has changed

Date Event Source
23 Jul 2024 Bookings open and construction is registered as starting; completion date 30 July 2027. Property Finder; DLD register
20 Aug 2024 First DLD inspection. DLD register, via Continental Club
11 Feb 2025 Azizi says 99% of units are sold. Gulf Construction Online
9 Dec 2025 DLD inspection: 12.18%. DLD register, via Continental Club
13 Apr 2026 DLD inspection: 17.05%. DLD register, via Continental Club
5 Oct 2026 DLD inspection: 38.53%. DLD register, via Continental Club

The registered date has stayed at 30 July 2027 since construction was registered. The progress record suggests a tight finish. From October 2026, the building needs more than 6 points a month to reach 100% by the end of July 2027. Its best recent stretch, April to October 2026, averaged about 3.7 points a month. Continental Club’s trend estimate, built from the past year of inspections, puts completion around 3 September 2028; it states this is not a developer commitment.

What the Azizi Neila handover date means for payments

Property Finder lists a 10/40/50 plan: 10% on booking, 40% during construction and 50% on handover. With a studio median of AED 566,000 in registered sales (Continental Club, to 8 October 2026), the handover payment on a typical studio is about AED 283,000. If completion slips past July 2027, that payment moves with it.

What to check before relying on the Azizi Neila date

  1. The SPA completion date and grace period, as sources give both Q2 2027 and July 2027.
  2. The next DLD inspection. Meeting July 2027 needs more than 6 points of progress a month, so the next reading shows whether the date is holding.
  3. Paid-up instalments on a resale. Most units were sold by February 2025, so the developer’s statement of which construction payments the seller has made matters on a resale.

Questions buyers also ask

When will Azizi Neila be completed?

The DLD registered completion date is 30 July 2027. The building was 38.53% complete at the DLD inspection of 5 October 2026.

Is Azizi Neila finished?

No. It is under construction, at 38.53% on 5 October 2026 (DLD register via Continental Club).

Has the Azizi Neila handover date been delayed?

Not on the register, which has kept 30 July 2027 and has not passed. Property Finder lists July 2027, while its project description mentions Q2 2027. Continental Club's pace estimate points to a later finish, around September 2028, but that is not a developer date.

How much is due at Azizi Neila handover?

On the 10/40/50 plan listed by Property Finder, 50% of the price is due on handover.