When is the Azizi David handover date?
Short answer
The registered completion date for Azizi David is 30 September 2028, while Propsearch and broker listings show a Q4 2027 handover. The Dubai Land Department (DLD) recorded the tower 2% complete at its inspection of 24 March 2026, and no later inspection had been published by 5 October 2026. Azizi did not publish a completion date at launch, so the date in each buyer's SPA decides which of the two applies.
Registered completion date (DLD)
30 Sep 2028
DLD register via Continental Club, updated 5 Oct 2026
Latest construction progress
2%
DLD inspection, 24 Mar 2026
Developer's stated date
Q3 2028
Developer-supplied date via Continental Club; none given at launch
Portal estimate
Q4 2027
Propsearch, updated 9 May 2026; broker listings Oct 2026
Azizi David handover date: the latest position
Azizi David has a registered completion date of 30 September 2028 on the Dubai Land Department (DLD) register. Propsearch and most broker listings show Q4 2027 instead. See the Azizi David project page for sizes, prices and the payment plan.
The latest DLD inspection, on 24 March 2026, recorded 2% complete. The register was updated on 5 October 2026 without a newer inspection, so there is no independent progress figure for the six months since.
Azizi David handover date by building
Azizi David is a single tower in Al Jaddaf, described by Propsearch as 20 storeys over three basement levels, with 256 registered units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Azizi David (DLD project 4096) | 2% (24 Mar 2026) | 30 Sep 2028 | Q3 2028 (developer-supplied, via Continental Club); Q4 2027 (Propsearch, broker listings) |
How the Azizi David handover date has changed
| Date | What happened | Source |
|---|---|---|
| 15 Aug 2025 | Azizi announces the launch; no completion date given | Construction Week Online |
| 18 Aug 2025 | Launch event at the Conrad Hotel, units from AED 760,000 | Zawya; Propsearch |
| 16 Sep 2025 | Construction start on the DLD register | Continental Club |
| 18 Sep 2025 | DLD inspection: 0% | Continental Club |
| 24 Mar 2026 | DLD inspection: 2% | Continental Club |
| 9 May 2026 | Propsearch estimates Q4 2027 | Propsearch |
| 5 Oct 2026 | Register shows completion 30 September 2028, no newer inspection | Continental Club |
Because Azizi did not publish a launch date, there is no clear “original promise” to measure against. The Q4 2027 date has circulated on listings since launch. Azizi’s wider record suggests caution with early dates: its Azizi Venice buildings missed the Q1 2026 date given in October 2025, and in September 2026 Azizi said handovers across its projects run “through 2026 and into 2027” (GDN, 15 September 2026).
What the Azizi David handover date means for payments
On the 50/50 plan most listed in 2026, 10% is paid on booking, 40% in four 10% instalments, and 50% on handover. On a AED 826,000 studio the handover payment is AED 413,000. Under the 10/60/30 option, 30% is due on handover. If handover lands in late 2028 rather than late 2027, the largest payment moves back by about a year, but date-based instalments before it do not.
What to check before relying on the Azizi David date
- The completion date in the SPA, since some buyers may hold Q4 2027 in sales material and the register says 30 September 2028.
- The next DLD inspection. Progress was 2% in March 2026, and none has been published since.
- Whether the instalments follow dates or construction stages, so payments do not run far ahead of the build.
- The unit’s position in the tower. Most of the 256 units are studios of 323 to 338 sq ft, so many similar units will hand over at the same time.
Questions buyers also ask
When will Azizi David be completed?
The DLD register gives 30 September 2028. Propsearch and broker listings show Q4 2027, which would require most of the tower to be built in under two years from the March 2026 inspection.
What is the Azizi David completion date?
30 September 2028 is the completion date on the DLD register for project 4096 (DLD register via Continental Club, updated 5 Oct 2026).
Has the Azizi David handover date been delayed?
Azizi has not announced a delay, and it did not publish a date at launch. The gap is between the Q4 2027 date on listings and the 30 September 2028 date on the register.
Has construction started at Azizi David?
Yes. The DLD register records a construction start of 16 September 2025, and the inspection of 24 March 2026 put progress at 2%.