When is the Azizi Amir handover date?
Short answer
Azizi Amir has a registered completion date of 17 June 2027, while most portals now show Q4 2027. The DLD recorded 2.35% progress on 18 March 2026, nine months into a registered two year build. Azizi has not published its own date for the building, so the SPA date and its grace period are what apply.
Registered completion date (DLD)
17 Jun 2027
DLD register via Mitchells, 4 Oct 2026
Latest construction progress
2.35%
DLD inspection, 18 Mar 2026
Portal date
Q4 2027
Springfield, OffPlanIndex, Equity Edge, Oct 2026
Date at sales launch
Jun 2027
Property Finder timeline, bookings from 17 Jun 2025
Azizi Amir handover date: the latest position
Azizi Amir is registered for completion on 17 June 2027 under DLD project number 3844, two years to the day after its registered construction start. Most portals now show Q4 2027 instead, and Azizi has not published a date of its own for the building. Full project details are on the Azizi Amir page.
The progress figure makes the June 2027 date hard to meet. The DLD recorded 2.35% on 18 March 2026, nine months into the build, leaving about 98 points to complete in 15 months to meet the registered date. No newer DLD inspection had been published by early October 2026.
Azizi Amir handover date by building
Azizi Amir is one building with 104 homes. Azizi Sakandar, launched alongside it in June 2025, is a separate project with its own registration.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Azizi Amir (104 units) | 2.35% (18 Mar 2026) | 17 Jun 2027 | June 2027 (Property Finder); Q4 2027 (Springfield, OffPlanIndex, Equity Edge) |
How the Azizi Amir handover date has changed
| Date | Event | Source |
|---|---|---|
| 17 Jun 2025 | Bookings open; registered construction start; expected completion 17 Jun 2027 | Property Finder; DLD register |
| 19 Jun 2025 | DLD inspection, 0% | DLD register via Continental Club |
| 28 Jun 2025 | Azizi announces Azizi Ameer and Azizi Sakandar | Azizi release via Mid-East.Info |
| 18 Mar 2026 | DLD inspection, 2.35% | DLD register via Continental Club |
| Oct 2026 | Register still shows 17 Jun 2027; most portals show Q4 2027 | Mitchells; portals |
Azizi’s launch release did not state a handover date. The June 2027 date comes from the register and Property Finder’s launch timeline; the Q4 2027 date on later listings is the only revision seen, and Azizi has not explained it. Across its portfolio, Azizi said in September 2026 that handovers run “through 2026 and into 2027” (GDN, 15 September 2026).
What the Azizi Amir handover date means for payments
Under the standard 50/50 plan, 10% is paid on booking and 10% each within 60, 180, 300 and 420 days, so a buyer who booked in June 2025 had paid 50% by about August 2026 (Tanami Properties). Those instalments run on fixed days, not construction stages. The other 50% is due on handover, so a later completion pushes back only that final payment. On a 1 bedroom at about AED 1.3 million, the handover payment is about AED 650,000.
What to check before relying on the Azizi Amir date
- The completion date in the SPA, since the register says 17 June 2027 and most portals say Q4 2027.
- The grace period in the SPA, with the building at 2.35% in March 2026.
- A newer DLD inspection in the Dubai REST app for project 3844, as the March 2026 figure is seven months old.
Questions buyers also ask
When will Azizi Amir be completed?
The registered completion date is 17 June 2027 (DLD register via Mitchells, 4 October 2026). Most portals show Q4 2027. The DLD recorded 2.35% progress on 18 March 2026.
Has the Azizi Amir handover date been delayed?
Not formally. The register still holds 17 June 2027. Portals have moved to Q4 2027, about six months later, and progress of 2.35% in March 2026 leaves little room to meet the June 2027 date.
Is Azizi Amir handover in June 2027 or Q4 2027?
The DLD register and Property Finder say June 2027. Springfield, OffPlanIndex and Equity Edge say Q4 2027. Azizi has not published a date for this building.
How much is paid before Azizi Amir is handed over?
50%. Under the standard plan, 10% is paid on booking and four 10% instalments within 420 days; the other 50% is due on handover, with nothing after.