Handover date

When is the Azizi Raffi handover date?

Updated 11 October 2026 Azizi Raffi

Short answer

Azizi Raffi has a registered completion date of 15 January 2028, and Property Finder lists Q1 2028. The Dubai Land Department (DLD) recorded the building 2% complete at its inspection of 25 March 2026, with no later figure published by 5 October 2026. Azizi's launch date of September 2026 has passed, so buyers who signed early may hold a different date in their SPA.

Registered completion date (DLD)

15 Jan 2028

DLD register via Continental Club, updated 5 Oct 2026

Latest construction progress

2%

DLD inspection, 25 Mar 2026

Developer's date at launch

Sep 2026

Azizi Developments, 23 Dec 2024

Portal date now

Q1 2028

Property Finder, accessed 11 Oct 2026

Azizi Raffi handover date: the latest position

Azizi Raffi is registered for completion on 15 January 2028, according to the Dubai Land Department (DLD) register, and Property Finder lists Q1 2028. Azizi’s own launch date was September 2026, which has passed. See the Azizi Raffi project page for sizes, prices and the payment plan.

The DLD recorded the building 2% complete at its inspection of 25 March 2026. That is the latest published figure; the register was updated on 5 October 2026 without a newer inspection.

Azizi Raffi handover date by building

Azizi Raffi is one 12 storey building in Al Furjan with 171 registered units, listed in DLD sales records as “Raffi by Azizi”.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Azizi Raffi (DLD project 3508) 2% (25 Mar 2026) 15 Jan 2028 September 2026 (Azizi, at launch); Q1 2028 (Property Finder); September 2026 (Propsearch, updated 18 Feb 2026)

Propsearch had not updated its September 2026 estimate when last revised in February 2026, so it now lags the register.

How the Azizi Raffi handover date has changed

Date What happened Source
23 Dec 2024 Azizi launches Raffi, completion scheduled for September 2026 Azizi Developments
15 Jan 2025 Construction start on the DLD register Continental Club
22 Jan 2025 DLD inspection: 0% dxbpropy (DLD register)
18 Feb 2026 Propsearch still estimates September 2026 Propsearch
18 Mar 2026 DLD inspection: 2% dxbpropy (DLD register)
25 Mar 2026 DLD inspection: 2% Continental Club
Sep 2026 Launch completion date passes Azizi Developments
Oct 2026 Register shows completion 15 January 2028; Property Finder lists Q1 2028 Continental Club; Property Finder

The registered date is about 16 months after the launch date. The register’s completion date of 15 January 2028 is exactly three years after its construction start of 15 January 2025. Progress reached 2% in the first 14 months after that start. Azizi’s wider guidance in September 2026 was that handovers across its projects would run “through 2026 and into 2027” (GDN, 15 September 2026); Raffi was not named.

What the Azizi Raffi handover date means for payments

Listings in 2026 put 60% of the price at handover: 10% on booking and 30% during construction (OffplanIndex), or 20% and 20% (Property Finder). At launch, Propsearch recorded 50% during construction and 50% on handover. On a AED 660,000 studio, the 60% handover payment is AED 396,000. A move from September 2026 to January 2028 pushes that payment back by more than a year, which helps cash flow but delays any rental income.

What to check before relying on the Azizi Raffi date

  1. The date in the SPA. Buyers from the December 2024 launch may have September 2026 in their contract, which has now passed.
  2. The SPA’s grace period and delay terms, since the launch date has gone and the register date is 15 January 2028.
  3. A DLD inspection after March 2026, through DLD’s project status service, to confirm work is moving.
  4. Which payment plan the unit was sold on, since the share due on handover ranges from 50% to 60%.

Questions buyers also ask

When will Azizi Raffi be completed?

The DLD register gives 15 January 2028 and Property Finder lists Q1 2028. The building was 2% complete at the DLD inspection of 25 March 2026.

What is the Azizi Raffi completion date?

15 January 2028 is the completion date on the DLD register for project 3508. At launch Azizi gave September 2026.

Has the Azizi Raffi handover date been delayed?

Yes, against the launch date. Azizi announced completion for September 2026 on 23 December 2024. That month has passed with the building at 2% at the last DLD inspection, and the register now gives 15 January 2028, about 16 months later.

How much of Azizi Raffi is built?

2% at the DLD inspections of 18 and 25 March 2026, up from 0% on 22 January 2025 (dxbpropy and Continental Club, from the DLD register).

Sources

  1. DLD project register via Continental Club, Azizi Raffi (opens in a new tab)continentalclub.ae · inspection 25 Mar 2026, register updated 5 Oct 2026
  2. Propsearch, Azizi Raffi (opens in a new tab)propsearch.ae · updated 18 Feb 2026
  3. OffplanIndex, Azizi Raffi payment plans (opens in a new tab)offplanindex.com · accessed 11 Oct 2026