When is the Tilal Al Ghaf handover date?

Updated 6 October 2026 Tilal Al Ghaf

Short answer

Tilal Al Ghaf has no single handover date: Elan, Aura and Harmony are handed over, Alaya's registered completion date was 20 July 2026 and Lanai Island's 30 September 2026, Amara and Plagette 32 are listed for Q4 2026, and Serenity Mansions and Bo Monde for Q4 2027. At DLD inspections between 13 August and 9 September 2026, Elysian Mansions was 95.02% complete, Alaya 91.45%, Amara 70.80%, Plagette 32 60.57%, Lanai Island 60.56% and Serenity Mansions 32.40%. Alaya's register status changed to finished on 30 September 2026, while Lanai Island reached its registered date at about 61% built, and Majid Al Futtaim says the SPA schedule for each phase is the one that applies.

Registered completion dates (DLD)

20 Jul 2026 (Alaya), 30 Sep 2026 (Lanai)

DLD register via Mitchells Commercial Realty. Amara, Plagette 32 and Serenity have none on file

Latest construction progress, six clusters

32% to 95%

DLD inspections, 13 Aug to 9 Sep 2026

Developer's stated date, Alaya and Elysian Mansions

Early to mid-2026

Majid Al Futtaim, 22 Jan 2024

Latest portal dates

Q4 2027

Serenity Mansions and Bo Monde. Property Finder; Propsearch

Tilal Al Ghaf handover date: the latest position

Tilal Al Ghaf is built and handed over cluster by cluster, so there is no single handover date. Elan, Aura and Harmony are handed over. Alaya’s registered completion date was 20 July 2026, and its DLD register status changed to finished on 30 September 2026. Lanai Island’s registered date was also 30 September 2026. Amara and Plagette 32 are listed for Q4 2026, and Serenity Mansions and Bo Monde for Q4 2027. Prices, the payment plan and service charges are on the Tilal Al Ghaf page.

The DLD inspections in August and September 2026 put six clusters between 32.40% (Serenity Mansions) and 95.02% (Elysian Mansions) complete. Lanai Island reached its registered date at 60.56% built, so the date in each buyer’s SPA, and its grace period, is what applies there.

Tilal Al Ghaf handover date by cluster

Cluster Construction progress (DLD, date) Registered completion date Developer or portal date
Elan, Aura, Harmony Handed over Passed Delivered 2021 to 2024
Alaya (DLD 2322) 91.45%, 14 Aug 2026; status finished 30 Sep 2026 20 Jul 2026 Early 2026 (Majid Al Futtaim, Jan 2024)
Alaya Gardens 91% (Data Habibi, undated) Not published Q3 2026, moved from Q4 2025 (Data Habibi)
Elysian Mansions (DLD 2054) 95.02%, 14 Aug 2026 31 Mar 2025, not updated Mid-2026 (Majid Al Futtaim, Jan 2024)
Lanai Island (DLD 2498) 60.56%, 9 Sep 2026 30 Sep 2026 Q3 2026 (Property Finder)
Amara (DLD 2858) 70.80%, 13 Aug 2026 Not filed Q4 2026 (Property Finder)
Plagette 32 (DLD 2827) 60.57%, 13 Aug 2026 Not filed Q4 2026 (Property Finder)
Serenity Mansions (DLD 2718) 32.40%, 7 Sep 2026 Not filed Q4 2027 (Property Finder)
Bo Monde (13 mansions) Not published Not published Q4 2027 (Propsearch, Property Finder)

DLD figures are from the register as republished by Mitchells Commercial Realty, with Alaya’s status change from dubaihandover.com. Alaya and Elysian Mansions each have their own page with dates, payment terms and the date history: Alaya handover date and Elysian Mansions handover date. Unit counts on the register do not always match Majid Al Futtaim’s own: DLD project 2322 lists 45 homes for Alaya, against 130 villas in the developer’s January 2024 release, and Elysian Mansions is registered with 35 homes against 94 units named when its contract was awarded (Zawya, 12 Jun 2026).

How the Tilal Al Ghaf handover date has changed

Date What happened Source
Jan 2020 Elan launched; 300 townhouses sold in three weeks Majid Al Futtaim
2021 to 2024 Elan, Aura and Harmony delivered Propsearch
22 Jan 2024 AED 3 billion of contracts awarded; Alaya due early 2026, Elysian Mansions mid-2026 Majid Al Futtaim
28 Apr 2025 AED 736 million contract for Amara and Plagette 32 (148 villas); no date given Majid Al Futtaim
12 Jun 2026 Buyer notices on supply chain pressure; developer says no change to timelines Gulf News
20 Jul 2026 Alaya’s registered completion date passes DLD register
13 to 14 Aug 2026 Elysian 95.02%, Alaya 91.45%, Amara 70.80%, Plagette 32 60.57% DLD inspections
30 Sep 2026 Alaya status changes to finished; Lanai Island’s registered date passes at 60.56% DLD register, via dubaihandover.com

What the Tilal Al Ghaf handover date means for payments

Amara and Plagette 32 both use 10% at booking, 50% during construction and 40% on handover, and no current Tilal Al Ghaf phase offers a post-handover plan. On an Amara villa at the listed entry price of AED 6.7 million, AED 2.68 million falls due at handover. Older phases such as Elan sold on different terms, including a six year plan with payments after handover.

What to check before relying on the Tilal Al Ghaf date

  1. The cluster and DLD project number on the SPA. Alaya and Alaya Gardens are listed separately, with different dates, and clusters range from handed over to 32% built.
  2. Whether a registered completion date exists. Amara, Plagette 32 and Serenity Mansions have none on file with DLD, so the SPA date is the only written one.
  3. For Lanai Island and Elysian Mansions, the grace period. Both are past a stated date, Lanai at about 61% built.
  4. Any June 2026 supply chain notice. If one was received, Majid Al Futtaim’s written reply for that phase shows whether its SPA date still stands.

Questions buyers also ask

Is Tilal Al Ghaf finished?

No. Elan, Aura and Harmony are handed over and Alaya's DLD status changed to finished on 30 September 2026 (dubaihandover.com). Elysian Mansions, Lanai Island, Amara, Plagette 32 and Serenity Mansions were still under construction at their latest DLD inspections in August and September 2026, and Bo Monde is listed for Q4 2027.

When will Alaya at Tilal Al Ghaf be handed over?

Alaya's registered completion date was 20 July 2026. The DLD inspection on 14 August 2026 recorded 91.45%, and its register status changed to finished on 30 September 2026 (dubaihandover.com). Majid Al Futtaim gave early 2026 when it awarded the contract in January 2024. Data Habibi lists Alaya Gardens separately, with a Q3 2026 target moved from Q4 2025.

When will Amara and Plagette 32 be completed?

Property Finder lists both for Q4 2026. The DLD inspections on 13 August 2026 recorded Amara at 70.80% and Plagette 32 at 60.57%. Neither has a registered completion date on file, and Majid Al Futtaim's April 2025 contract award for both gave no date.

Has the Tilal Al Ghaf handover date been delayed?

Some clusters are past their dates. Alaya passed 20 July 2026 before its status changed to finished, Elysian Mansions passed Majid Al Futtaim's mid-2026 target at 95.02% built, and Lanai Island reached its registered date of 30 September 2026 at 60.56%. In June 2026 Majid Al Futtaim said notices sent to buyers about supply chain pressure did not change delivery timelines (Gulf News, 12 Jun 2026).

Does Tilal Al Ghaf have a post-handover payment plan?

Not on current published terms. Amara and Plagette 32 use 10% at booking, 50% during construction and 40% on handover, so the balance is due when the unit is delivered.

Sources

  1. Propsearch, Tilal Al Ghaf (opens in a new tab)propsearch.ae · accessed 28 Sep 2026
  2. Mitchells Commercial Realty, Alaya DLD registry (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  3. Mitchells Commercial Realty, Lanai Island DLD registry (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  4. Mitchells Commercial Realty, Amara DLD registry (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  5. Mitchells Commercial Realty, Plagette 32 DLD registry (opens in a new tab)mitchellscommercialrealty.com · accessed 1 Oct 2026
  6. Dubai Handover, Alaya (DLD register, daily) (opens in a new tab)dubaihandover.com · status as at 30 Sep 2026
  7. Data Habibi, Alaya Gardens (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026
  8. Propsearch, Bo Monde (opens in a new tab)propsearch.ae · updated 28 Jun 2025