When is the Elysian Mansions handover date?
Short answer
Majid Al Futtaim's target for Elysian Mansions was completion by mid-2026, and the DLD register still carries a registered completion date of 31 March 2025. The latest DLD inspection, on 14 August 2026, recorded 95.02% complete, and the project was still listed as under construction on 4 October 2026. Both dates have passed, so the completion date in each buyer's SPA, and its grace period, is the one that applies.
Registered completion date (DLD)
31 Mar 2025
DLD project 2054, via Mitchells Commercial Realty; passed, not updated
Latest construction progress
95.02%
DLD inspection, 14 Aug 2026
Developer's stated date
Mid-2026
Majid Al Futtaim, 22 Jan 2024
Portal date change since launch
Q4 2025 to Q2 2026
Data Habibi
Elysian Mansions handover date: the latest position
Elysian Mansions, the lagoon-front mansion cluster in Tilal Al Ghaf, had a developer target of mid-2026. Majid Al Futtaim set that date on 22 January 2024, when it named Innovo Build as main contractor. The Dubai Land Department register carries an earlier registered completion date, 31 March 2025, which has passed without being updated. Prices, sizes and the payment plan are on the Elysian Mansions page.
The latest DLD inspection, on 14 August 2026, recorded 95.02% complete. On 4 October 2026 the register still listed project 2054 as under construction. Handover preparation has started on site: a moving company reported walk-through surveys at three Elysian units in April 2026, and an agent described the cluster as entering its handover phase on 4 September 2026. Majid Al Futtaim has not announced completion.
Elysian Mansions handover date by building
| Project | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Elysian Mansions (DLD 2054, 35 homes registered) | 95.02%, 14 Aug 2026; under construction at 4 Oct 2026 | 31 Mar 2025, not updated | Mid-2026 (Majid Al Futtaim, Jan 2024); Q2 2026 (Data Habibi, Propsearch) |
DLD holds Elysian Mansions as a single project, so all mansions share one progress figure. Majid Al Futtaim sold it in two phases in March 2022: 33 homes in phase 1 (8 Lagoonside, 5 Hilltop, 20 Park Lane) and 59 in phase 2. The register counts 35 homes, against 92 villas in its own description and 94 in the developer’s 2024 release.
How the Elysian Mansions handover date has changed
| Date | What happened | Source |
|---|---|---|
| 1 Sep 2018 | Project start on the DLD register | DLD via Mitchells |
| 29 Mar 2022 | Launch of 92 mansions in two phases, AED 18M to AED 35M | The National |
| At launch | Handover quoted for Q4 2025 | Data Habibi; Bayut |
| 22 Jan 2024 | Innovo Build appointed; completion targeted for mid-2026 | Majid Al Futtaim |
| 31 Mar 2025 | Registered completion date passes | DLD register |
| 12 Jun 2026 | Majid Al Futtaim says buyer notices on supply chains do not change timelines | Gulf News |
| 14 Aug 2026 | DLD inspection records 95.02% | DLD via Mitchells |
| 4 Oct 2026 | Still listed as under construction | DLD via Mitchells |
Data Habibi describes the move from Q4 2025 to Q2 2026 as a six month postponement. Q2 2026 has also passed.
What the Elysian Mansions handover date means for payments
The handover date decides when most of the price falls due. Data Habibi lists the plan as 10% at booking, 30% during construction and 60% on handover. Bayut’s area guide lists 10% down, 60% during construction and 40% in instalments over five years after handover. On a mansion bought at the launch entry price of AED 18 million, 60% on handover would be AED 10.8 million, while the Bayut version would put AED 7.2 million into post-handover instalments.
What to check before relying on the Elysian Mansions date
- The SPA completion date and grace period. Both the DLD date and the developer’s mid-2026 target have passed, so the contract terms decide what applies.
- Which plan the unit was sold on. The two published plans put very different amounts due at handover.
- The phase and plot type. Phase 1 and phase 2 homes, and Lagoonside, Hilltop and Park Lane plots, may not be finished and handed over together.
- The DLD status of project 2054 on the Dubai REST app, to see when it changes from under construction to completed.
Questions buyers also ask
When will Elysian Mansions be completed?
Majid Al Futtaim's target was mid-2026 (22 January 2024). The DLD inspection on 14 August 2026 recorded 95.02%, and the register still listed the project as under construction on 4 October 2026.
Is Elysian Mansions finished?
Not on the DLD register. Project 2054 was listed as under construction on 4 October 2026, at 95.02% from the 14 August 2026 inspection. Agents and a moving company reported walk-throughs and handover preparations in 2026, but Majid Al Futtaim has not announced completion.
Has the Elysian Mansions handover date been delayed?
Yes, against earlier dates. Data Habibi records a Q4 2025 promise moved to Q2 2026, and the registered completion date of 31 March 2025 has passed. Majid Al Futtaim's own target of mid-2026, set in January 2024, has also passed.
Why does DLD show only 35 homes at Elysian Mansions?
The DLD register counts 35 registered homes for project 2054, while its own description lists 92 villas. Majid Al Futtaim launched 92 mansions in March 2022 and named 94 in January 2024. The register count does not match the developer's figures.