Handover date

When is The Valley handover date?

Updated 6 October 2026 The Valley

Short answer

The Valley is partly handed over, and the clusters still under construction have registered completion dates from 31 March 2027 for Rivana to 31 March 2030 for Alva on the Dubai Land Department (DLD) register. Rivana was 93.82% built at its DLD inspection of 5 August 2026, Alana 81.56% on 15 July 2026 against May 2027, and Nima 80.02% on 7 May 2026 against July 2027. Lillia, listed in 2024 for January 2027, was recorded as handed over on 20 July 2026, while 12 more clusters are registered for 2028 and the last ones for 2029 and early 2030.

Next registered completion, Rivana

31 Mar 2027

DLD register, via Continental Club, accessed 1 Oct 2026

Rivana, latest construction progress

93.82%

DLD site inspection, 5 Aug 2026

Latest cluster handed over, Lillia

20 Jul 2026

DLD register, via Continental Club. Listed for Jan 2027 in Oct 2024

Last registered completion, Alva

31 Mar 2030

0% built, DLD inspection 24 Aug 2026, via Dubai Handover

The Valley handover date: the latest position

The Valley is handing over in clusters. Emaar launched the community on 18 November 2019, and Eden, Talia, Nara, Orania, Elora, Farm Gardens and Lillia are handed over. Of the clusters still being built, Rivana is next, with a registered completion date of 31 March 2027 on the Dubai Land Department register, followed by Alana in May 2027 and Nima in July 2027. More on prices and the community is on The Valley page.

Those three are well advanced, at 93.82%, 81.56% and 80.02% at their latest DLD inspections. Behind them, 12 clusters are registered for June to December 2028, between 1.98% and 51.7% built, and the last five, Ovelle, Avelia and Alva 1 to 3, run to late 2029 and early 2030.

The Valley handover date by cluster

Cluster Construction progress (DLD, date) Registered completion date Developer or portal date
Rivana (485 homes) 93.82%, 5 Aug 2026 31 Mar 2027 Q1 2027 (Emaar, via Continental Club)
Alana (322 villas) 81.56%, 15 Jul 2026 May 2027 Q2 2027 (Emaar, via Tohid Fetrat)
Nima (520 townhouses) 80.02%, 7 May 2026 Jul 2027 Q3 2027 (Bayut)
Farm Gardens 2 59.08%, 20 Jul 2026 None on the register Q1 2028 (Property Finder)
Avena 24.47%, 16 Jun 2026 30 Jun 2028 None found
Elea 22.02%, 15 Jul 2026 30 Jun 2028 None found
Avena 2 42.89%, 20 Jul 2026 31 Jul 2028 None found
Velora 2 40.28%, 6 Jul 2026 31 Jul 2028 None found
Kaia 19.13%, 9 Jun 2026 31 Jul 2028 None found
Velora 50.07%, 9 Jun 2026 31 Aug 2028 None found
Venera 51.7%, 5 Aug 2026 30 Sep 2028 None found
Elva 25.86%, 9 Jun 2026 31 Oct 2028 None found
Farm Grove 2 9.77%, 6 Jul 2026 31 Oct 2028 None found
Rivera 3.94%, 6 May 2026 30 Nov 2028 None found
Farm Grove 10%, 15 Jul 2026 31 Dec 2028 None found
Vindera 1.98%, 20 Jan 2026 31 Dec 2028 None found
Ovelle 2.36%, 16 Jun 2026 31 Dec 2029 None found
Avelia 0.27%, 9 Jun 2026 31 Dec 2029 None found
Alva 2 (176 villas) 0%, 28 Jan 2026 28 Feb 2030 None found
Alva (196 villas) 0%, 24 Aug 2026 31 Mar 2030 None found
Alva 3 (156 villas) 0%, 2 Feb 2026 Not found Q1 2030 (Emaar, via Continental Club)
Lillia Handed over 20 Jul 2026 Passed Jan 2027 (2024 listing)
Farm Gardens Completed 6 Apr 2026 Passed Aug 2026 (2024 listing)
Elora Completed 13 Mar 2026 Passed Sep 2026 (2024 listing)
Eden, Talia, Nara, Orania Handed over Passed Delivered; Nara 100% on 25 Nov 2024

Progress and dates are from the DLD register as republished by Continental Club, fäm, Dubai Handover and Real Estate Club Dubai. Nima’s registered date is from fäm’s January 2026 snapshot. Elora and Nara have their own registrations and pages: Elora at The Valley handover date and Nara handover date. Nara’s declared completion date on the register is 30 December 2024 (Data Dubai).

How The Valley handover date has changed

For the clusters tracked since 2024, Emaar has delivered on or ahead of the dates published then.

Date What happened Source
18 Nov 2019 Emaar launches The Valley. Emaar
29 Oct 2024 Published dates: Farm Gardens August 2026, Elora September 2026, Lillia January 2027, Rivana March 2027, Alana May 2027, Nima July 2027. Topluxuryproperty
13 Mar 2026 Elora recorded complete, six months before its 2024 date. DLD register, via Real Estate Club Dubai
6 Apr 2026 Farm Gardens recorded complete, four months early. DLD register, via Real Estate Club Dubai
7 Apr 2026 A community guide lists Rivana with Terra Heights for Q1 to Q2 2028. The register keeps Rivana at 31 March 2027. Real Estate Club Dubai
20 Jul 2026 Lillia handed over, six months before its 2024 date. DLD register, via Continental Club
Aug to Sep 2026 Rivana, Alana and Nima still registered for March, May and July 2027. Continental Club; fäm

What The Valley handover date means for payments

The clusters due next were sold on plans that leave 10% for handover. DataHabibi lists Rivana at 10% on booking, 80% during construction and 10% on handover, Bayut lists Farm Gardens 2 on the same split, and Nima was sold on 90% during construction and 10% on handover (Propsearch; Bayut). For these buyers most of the price is already paid. A 2026 guide to the newer releases describes 80/20, 70/30 and 60/40 plans, the last with 40% spread over two to three years after handover (Real Estate Club Dubai, 7 Apr 2026).

What to check before relying on The Valley date

  1. The exact cluster name. Velora and Velora 2, Avena and Avena 2, and Farm Gardens and Farm Gardens 2 are separate projects with dates up to two years apart.
  2. Farm Gardens 2’s date in your SPA. The register shows no completion date for it, so Emaar’s Q1 2028 is the only published figure.
  3. How recent the inspection is. Vindera’s 1.98% dates from 20 January 2026 and Nima’s 80.02% from 7 May 2026.
  4. Community guides against the register. The April 2026 guide’s 2028 date for Rivana conflicts with the registered 31 March 2027.

Questions buyers also ask

When will The Valley be ready?

Cluster by cluster. Eden, Talia, Nara, Orania, Elora, Farm Gardens and Lillia are handed over. Rivana, Alana and Nima are registered for March, May and July 2027, 12 clusters for 2028, and Ovelle, Avelia and the three Alva phases for late 2029 to early 2030 (DLD register via Continental Club, fäm and Dubai Handover).

What is the Rivana handover date at The Valley?

31 March 2027 on the DLD register. Rivana was 93.82% complete at its inspection of 5 August 2026, up 4.1 points since 22 April 2026 (Continental Club, DLD data). An April 2026 community guide that grouped Rivana with Terra Heights for 2028 does not match the register.

Has Lillia at The Valley been handed over?

Yes. The DLD register records Lillia, project number 2992, as ready and handed over on 20 July 2026 (Continental Club, registry updated 22 Sep 2026). Propsearch, updated 14 July 2026, still showed an estimate of June 2028.

Has The Valley handover date been delayed?

Not for the clusters tracked since 2024. Elora, Farm Gardens and Lillia were handed over in 2026 ahead of the dates listed for them in October 2024, and Rivana, Alana and Nima are still registered for March, May and July 2027, the same months listed then (topluxuryproperty, 29 Oct 2024).

When will Nima and Alana be handed over?

Alana is registered for May 2027 and was 81.56% built on 15 July 2026 (fäm). Nima's registered date is July 2027 and it was 80.02% built on 7 May 2026; Emaar's schedule gives Q3 2027 (fäm; Continental Club; Bayut).

Sources

  1. Continental Club, The Valley Lillia (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 22 Sep 2026
  2. Continental Club, The Valley Nima (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 26 Sep 2026
  3. Continental Club, The Valley Alva 3 (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 26 Sep 2026
  4. fäm Properties, The Valley Alana completion date (DLD) (opens in a new tab)famproperties.com · inspection 15 Jul 2026, accessed 1 Oct 2026
  5. fäm Properties, The Valley Farm Gardens 2 completion date (DLD) (opens in a new tab)famproperties.com · inspection 20 Jul 2026, accessed 1 Oct 2026
  6. Propsearch, Nima at The Valley (opens in a new tab)propsearch.ae · updated 15 Aug 2026
  7. Propsearch, Lillia at The Valley (opens in a new tab)propsearch.ae · updated 14 Jul 2026
  8. Property Finder, Farm Gardens 2 (opens in a new tab)propertyfinder.ae · accessed 1 Oct 2026
  9. Bayut, Nima area guide (opens in a new tab)bayut.com · accessed 1 Oct 2026
  10. DataHabibi, Rivana (opens in a new tab)datahabibi.ae · accessed 1 Oct 2026
Request a Unit Review