Sunset Bay Grand
A 98 apartment Imtiaz building on Dubai Islands. Imtiaz targets December 2027, the DLD register says 15 February 2028, and it was 16.29% built in August 2026.
Short answer
Imtiaz Developments gives Sunset Bay Grand an estimated completion of December 2027, while the DLD register records a completion date of 15 February 2028. A DLD inspection on 17 August 2026 recorded the 98 unit Dubai Islands building 16.29% complete. Imtiaz lists starting prices of AED 1.95 million for a 1 bedroom, and registered sales in the year to September 2026 had a median of AED 2.40 million, or AED 2,304 per sq ft. 40% of the price is due on completion.
- Status
- under construction
- Handover date
- Registered completion 15 Feb 2028 (DLD); Imtiaz targets December 2027
- Construction
- 16.29% complete (DLD inspection, 17 Aug 2026)
- Payment plan
- 20% on booking, 40% in six dated instalments to July 2027, 40% on completion
- Starting price
- From AED 1.95 million (Imtiaz); AED 2.34 million on the Sep 2026 price list
Registered completion date
15 Feb 2028
DLD project register via Continental Club
Construction progress
16.29%
DLD inspection, 17 Aug 2026
Developer's completion date
December 2027
Imtiaz Developments project page
Median registered sale price
AED 2.40 million
AED 2,304 per sq ft, 12 months to Sep 2026, Dubai Data
When will Sunset Bay Grand be handed over?
Imtiaz Developments gives Sunset Bay Grand an anticipated handover in Q4 2027, specifically December 2027, and its payment plan puts the final 40% “on completion December 2027”. The Dubai Land Department (DLD) register records a later completion date of 15 February 2028. Property Finder lists expected completion on 31 December 2027.
At the last DLD inspection, on 17 August 2026, the building was 16.29% complete. That leaves about 84% of the work for the 18 months to the registered date.
Building-by-building dates and how the date has changed: Sunset Bay Grand handover date.
Sunset Bay Grand construction update
The register records construction starting on 15 October 2025, the same week Property Finder lists as the booking start. Progress has picked up through 2026.
| DLD inspection | Recorded progress |
|---|---|
| 7 Jul 2025 | 0% |
| 12 Nov 2025 | 1.7% |
| 20 Feb 2026 | 4.2% |
| 20 May 2026 | 10.3% |
| 17 Aug 2026 | 16.29% |
Source: DLD register via Dubai Data and Continental Club. The last two intervals each added about 6 points in three months. Imtiaz’s own project page shows overall progress of 14%, with the super-structure at 23%, a figure that trails the August DLD inspection. The escrow bank is First Abu Dhabi Bank and the DLD project number is 3868.
Sunset Bay Grand homes and sizes
Sunset Bay Grand is a ground plus two parking levels plus ten floor building with a rooftop sky pool with a glass floor. All homes are delivered fully furnished with 3.2 metre ceilings (Imtiaz).
| Home type | Units | Size | Imtiaz starting price |
|---|---|---|---|
| 1 bedroom | 51 | 845 to 1,121 sq ft | AED 1.95 million |
| 2 bedroom | 43 | 1,356 to 1,661 sq ft | AED 2.91 million |
| 3 bedroom duplex | 4 | Not published | AED 4.71 million |
Unit counts and starting prices are from Imtiaz’s project page. Sizes are from the developer price list dated 21 September 2026, via OffPlan Insider.
Sunset Bay Grand prices and resale
Imtiaz’s project page lists starting prices of AED 1.95 million for a 1 bedroom. The developer price list dated 21 September 2026 started higher, at AED 2,343,960 for a 1 bedroom and AED 3,317,618 for a 2 bedroom (OffPlan Insider), so the AED 1.95 million figure looks like an early launch price.
The DLD recorded 82 sales in the 12 months to September 2026 at a median of AED 2.40 million, or AED 2,304 per sq ft (Dubai Data). The 45 sales of 1 bedroom homes had a median of AED 2.29 million for a median size of 935 sq ft. Sales slowed after April 2026, when 25 were registered; from July to September 2026 only three sales were recorded in total. All were off-plan sales from the developer.
Sunset Bay Grand payment plan
The fact sheet sets a 60/40 plan with fixed dates rather than construction milestones: 20% on booking, 5% on 15 February 2026, 5% on 15 May 2026, 10% on 15 September 2026, 10% on 15 December 2026, 5% on 15 March 2027 and 5% on 15 July 2027, then 40% on completion in December 2027. OffPlan Insider also reports a portfolio wide Imtiaz offer of 35/65 with a 5% discount. The 4% DLD fee is extra.
Sunset Bay Grand developer and delivery record
Imtiaz Developments says it has delivered more than 40 projects, including Westwood by Imtiaz in Al Furjan, handed over in November 2023. The developer is registered for this project as Imtiaz GHD Real Estate Development. Imtiaz has several other buildings on Dubai Islands, including Wynwood and Beach Walk.
What to check before buying at Sunset Bay Grand
- The completion date in the SPA. Imtiaz markets December 2027, but the DLD register says 15 February 2028.
- The dated instalments already passed. By October 2026, a buyer on the original plan would have paid 40% under the fact sheet schedule.
- The current price list. Developer prices rose from AED 1.95 million to AED 2.34 million for the entry 1 bedroom.
Sunset Bay Grand location: Dubai Islands, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Sunset Bay Grand handover date?
Imtiaz Developments gives an anticipated handover of Q4 2027, specifically December 2027. The DLD register shows a completion date of 15 February 2028, about six weeks later.
What is the Sunset Bay Grand completion date?
The registered completion date is 15 February 2028 (DLD register via Continental Club). Property Finder lists expected completion on 31 December 2027. The building was 16.29% complete at the DLD inspection on 17 August 2026.
What is the Sunset Bay Grand price?
Imtiaz lists starting prices of AED 1.95 million for 1 bedrooms, AED 2.91 million for 2 bedrooms and AED 4.71 million for 3 bedroom duplexes. A developer price list dated 21 September 2026 started at AED 2,343,960 for a 1 bedroom (OffPlan Insider). Registered sales had a median of AED 2.40 million in the year to September 2026 (Dubai Data).
What is the Sunset Bay Grand payment plan?
20% on booking, then 5%, 5%, 10%, 10%, 5% and 5% on fixed dates between 15 February 2026 and 15 July 2027, and 40% on completion in December 2027 (Imtiaz fact sheet).
Is Sunset Bay Grand the same as Sunset Bay?
No. Sunset Bay Grand is a separate 98 unit building registered as DLD project 3868. Imtiaz uses the Sunset Bay name for several projects on Dubai Islands.