
When is the Sunset Bay Grand handover date?
Short answer
Imtiaz Developments targets a December 2027 handover for Sunset Bay Grand, while the DLD register records a completion date of 15 February 2028. The last DLD inspection, on 17 August 2026, recorded the building 16.29% complete. The SPA date for each unit decides which date applies, and the 40% completion payment is tied to it.
Registered completion date (DLD)
15 Feb 2028
DLD register via Continental Club
Latest construction progress
16.29%
DLD inspection, 17 Aug 2026
Developer's stated date
December 2027
Imtiaz Developments project page
Portal date
31 Dec 2027
Property Finder, accessed 11 Oct 2026
Sunset Bay Grand handover date: the latest position
Imtiaz Developments targets a December 2027 handover for Sunset Bay Grand, and Property Finder lists expected completion on 31 December 2027. The Dubai Land Department (DLD) register records a completion date of 15 February 2028, about six weeks later. Full project details are on the Sunset Bay Grand page.
The last DLD inspection, on 17 August 2026, recorded the building 16.29% complete. Imtiaz’s own project page shows a lower overall figure of 14%.
Sunset Bay Grand handover date by building
Sunset Bay Grand is one building of 98 apartments on Dubai Islands, registered as DLD project 3868.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sunset Bay Grand | 16.29% (17 Aug 2026) | 15 Feb 2028 | December 2027 (Imtiaz); 31 Dec 2027 (Property Finder) |
| DLD inspection | Progress |
|---|---|
| 7 Jul 2025 | 0% |
| 12 Nov 2025 | 1.7% |
| 20 Feb 2026 | 4.2% |
| 20 May 2026 | 10.3% |
| 17 Aug 2026 | 16.29% |
Source: DLD register via Dubai Data and Continental Club.
How the Sunset Bay Grand handover date has changed
| Date | What happened | Source |
|---|---|---|
| 30 Sep 2025 | Registered with the DLD | DLD register via Dubai Data |
| Oct 2025 | Fact sheet sets 40% on completion in December 2027 | Imtiaz fact sheet |
| 15 Oct 2025 | Registered construction start; bookings open | DLD register; Property Finder |
| 20 May 2026 | 10.3% complete | DLD register |
| 17 Aug 2026 | 16.29% complete; registered date 15 Feb 2028 | DLD register via Continental Club |
| 11 Oct 2026 | Imtiaz still shows Q4 2027, December 2027 | Imtiaz project page |
No change to either date has been reported. The difference is between Imtiaz’s December 2027 and the 15 February 2028 in the register.
What the Sunset Bay Grand handover date means for payments
Sunset Bay Grand uses fixed dates, not construction milestones. After 20% on booking, six instalments of 5%, 5%, 10%, 10%, 5% and 5% fall due between 15 February 2026 and 15 July 2027 whatever the progress on site. The last 40% is due “on completion December 2027” (Imtiaz fact sheet). By the final dated instalment in July 2027, buyers will have paid 60% of the price. If completion moves towards the registered February 2028 date or later, only the 40% balance moves with it.
What to check before relying on the Sunset Bay Grand date
- The anticipated completion date in the SPA, and whether it says December 2027 or follows the DLD’s 15 February 2028.
- The grace period in the SPA, which sets how far beyond that date completion can slip.
- Progress at the next DLD inspection. Since February 2026 the building has added about 2 points a month, which would need to more than double to finish by December 2027.
Questions buyers also ask
When will Sunset Bay Grand be completed?
Imtiaz gives December 2027. The DLD register gives 15 February 2028. The building was 16.29% complete on 17 August 2026.
Has the Sunset Bay Grand handover date been delayed?
No delay has been announced. Imtiaz has given Q4 2027, specifically December 2027, since the launch fact sheet in October 2025. The DLD date of 15 February 2028 is later, but there is no record of either date being changed.
How far along is Sunset Bay Grand?
16.29% at the DLD inspection on 17 August 2026, up from 10.3% on 20 May 2026 and 4.2% on 20 February 2026 (Dubai Data).
Is Sunset Bay Grand on track for December 2027?
Recent progress was about 2 points a month. At that pace the remaining 84 points would take longer than the 16 months to December 2027, so faster work will be needed to meet either date.
