Samana Sky Views
Samana Sky Views in Dubai Production City: handover and completion date of 31 July 2028, DLD progress of 2.23%, launch prices from AED 689,000 and the post-handover payment plan.
Short answer
Samana Sky Views has a registered completion date of 31 July 2028, and portals list a Q3 2028 handover. The DLD inspection on 16 June 2026 recorded 2.23% complete, nine and a half months after the registered construction start. The building launched in July 2025 from about AED 689,000, and its main plan spreads most of the price over 75 monthly instalments of 1% that run well past handover.
- Status
- under construction
- Handover date
- Q3 2028 (Bayut, Property Finder); DLD registered completion date 31 Jul 2028
- Construction
- 2.23% complete (DLD inspection, 16 Jun 2026)
- Payment plan
- 15% booking, 10% in month 12, then 1% a month for 75 months, most of it after handover (Bayut)
- Starting price
- From AED 689,000 at launch (Jul 2025); AED 941,007 on Property Finder
DLD registered completion date
31 Jul 2028
DLD project register via Continental Club
Construction progress
2.23%
DLD inspection, 16 Jun 2026
Units
556
DLD register; launch listings said 458
Launch price
From AED689,000
Agent launch listings, Jul 2025
When will Samana Sky Views be handed over?
Samana Sky Views has a registered completion date of 31 July 2028 in the DLD project register. Bayut and Property Finder both list a Q3 2028 handover, and Property Finder gives the expected completion as 31 July 2028.
That is later than the date given at launch. Agent listings in July 2025 said completion was expected in 2027 (Seven Luxury Real Estate, 3 July 2025). Some listings now show Q4 2028, so portals do not fully agree.
Building-by-building dates and how the date has changed: Samana Sky Views handover date.
Samana Sky Views construction update
The DLD register records construction starting on 1 September 2025. At the inspection on 5 February 2026 progress was close to zero, and by 16 June 2026 it had reached 2.23%. That is a gain of 2.19 points in just over four months. The escrow account is held at ADCB, under DLD project number 3855.
To reach completion by 31 July 2028, about 98% of the work would need to be done in the 25 months after the June 2026 inspection.
Samana Sky Views homes and sizes
The tower offers studios, 1 bedroom and 2 bedroom apartments, each with a private pool. Launch listings described 21 or 22 storeys and 458 apartments; the DLD register lists 556 units, so counts differ between sources.
| Home type | Size | Listed price |
|---|---|---|
| Studio | From about 420 to 446 sq ft | From AED 689,000 at launch; AED 941,007 on Property Finder |
| 1 bedroom | About 769 to 872 sq ft | From about AED 999,000 at launch; AED 1.36 million for 769 sq ft (Prop971) |
| 2 bedroom | Up to about 1,250 sq ft | From about AED 1.43 million at launch |
Launch prices are from agent listings dated July 2025. Current figures are from Property Finder and Prop971, accessed 11 October 2026.
Samana Sky Views prices and resale
The building sold quickly. Continental Club counts 547 DLD-registered sales against 556 units. Entry prices have moved up: the studio price quoted at launch in July 2025 was AED 689,000, while Property Finder now shows AED 941,007 for a 446 sq ft studio. Prop971 lists a 769 sq ft 1 bedroom on the 21st floor at AED 1.36 million, about AED 1,762 per sq ft. No resale price history is available yet for a building at this stage.
Samana Sky Views payment plan
Bayut lists two plans (20 October 2025):
- 15% on booking with post-dated cheques, 10% in month 12, then 1% a month for 75 months
- 20% on booking without post-dated cheques, 10% in month 12, then 1% a month for 70 months
With the first plan, 25% is paid in the first year. The monthly instalments then run for more than six years from booking, so a large part falls after a July 2028 handover. Property Finder summarises the plan as 15% at launch and 85% later.
Samana Sky Views developer and delivery record
Samana Developers markets private pools across most of its buildings. It handed over Samana Santorini in Dubai Studio City on 16 April 2026 and said then that it had delivered more than 1,300 units (Business Today Middle East). Real Estate Club Dubai notes that Santorini completed about a year after the target given at launch. Sky Views has already moved from a 2027 target to July 2028.
What to check before buying at Samana Sky Views
- The completion date in the SPA, since 2027, Q3 2028 and Q4 2028 all appear in listings.
- The number of post-handover instalments left, which a resale buyer takes over with the unit.
- The next DLD inspection figure, after only 2.23% was recorded in June 2026.
- The service charge estimate, as every unit has its own pool to maintain.
Samana Sky Views location: Dubai Production City, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Samana Sky Views handover date?
Bayut and Property Finder list Q3 2028, and the DLD project register holds a registered completion date of 31 July 2028. Launch listings in July 2025 gave 2027 (Seven Luxury Real Estate, 3 Jul 2025).
What is the Samana Sky Views completion date?
The registered completion date is 31 July 2028. The building was 2.23% complete at the DLD inspection on 16 June 2026 (DLD project register via Continental Club).
What is the Samana Sky Views price?
Launch listings in July 2025 gave studios from AED 689,000, 1 bedrooms from about AED 999,000 and 2 bedrooms from about AED 1.43 million. Property Finder now lists studios of about 446 sq ft from AED 941,007.
What is the Samana Sky Views payment plan?
Bayut lists 15% on booking with post-dated cheques, 10% in month 12, then 1% a month for 75 months. A second option is 20% on booking, 10% in month 12 and 1% a month for 70 months. Property Finder summarises the plan as 15/85.