When is the Samana Sky Views handover date?
Short answer
Samana Sky Views has a registered completion date of 31 July 2028, and Bayut and Property Finder list a Q3 2028 handover. The DLD inspection on 16 June 2026 recorded 2.23% complete. Launch listings in July 2025 gave a 2027 completion, so the date has already moved by about a year.
Registered completion date (DLD)
31 Jul 2028
DLD project register via Continental Club
Latest construction progress
2.23%
DLD inspection, 16 Jun 2026
Portal handover date
Q3 2028
Bayut; Property Finder, accessed 11 Oct 2026
Date at launch
2027
Agent launch listings, Jul 2025
Samana Sky Views handover date: the latest position
Samana Sky Views has a registered completion date of 31 July 2028 in the DLD project register, and portals list a Q3 2028 handover. Prices, sizes and the payment plan are on the Samana Sky Views page.
The DLD inspection on 16 June 2026 recorded the building 2.23% complete. Construction was registered as starting on 1 September 2025, and almost no progress was recorded until early 2026. With 25 months from that inspection to the registered date, close to the full build remained.
Samana Sky Views handover date by building
Samana Sky Views is a single tower, registered as DLD project number 3855 with 556 units and its escrow account at ADCB.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Samana Sky Views | 2.23%, 16 Jun 2026 | 31 Jul 2028 | Q3 2028 (Bayut; Property Finder); Q4 2028 (Prop971) |
How the Samana Sky Views handover date has changed
| Date | What happened | Source |
|---|---|---|
| 3 Jul 2025 | Launch listings give studios from AED 689,000 and completion in 2027 | Seven Luxury Real Estate |
| 1 Sep 2025 | Booking start and construction start recorded | Property Finder; DLD register |
| 20 Oct 2025 | Bayut lists Q3 2028 handover | Bayut |
| 5 Feb 2026 | Inspection records almost no progress | DLD register |
| 16 Jun 2026 | Inspection records 2.23% | DLD register |
| 11 Oct 2026 | Property Finder shows expected completion 31 July 2028 | Property Finder |
Launch listings also differ on the building itself, describing 21 or 22 storeys and 458 apartments, while the DLD register holds 556 units. The registered figures are the ones tied to the completion date.
The date moved from 2027 in the first listings to 31 July 2028 by the time the project was registered and portals took it up in autumn 2025. Since then the registered date has held. Progress has been slow: 2.19 points between February and June 2026.
What the Samana Sky Views handover date means for payments
Under the plan listed by Bayut, buyers pay 15% on booking and 10% in month 12, then 1% a month for 75 months. For a booking in mid 2025, 75 monthly instalments run to about late 2031, so roughly 40% of the price falls after a July 2028 handover. Bayut lists the instalments by month from booking, not by construction stage, so a later handover would shorten the part paid after keys rather than delay the instalments.
What to check before relying on the Samana Sky Views date
- The completion date written in the SPA, since 2027, Q3 2028 and Q4 2028 all appear in listings.
- Whether instalments are linked to dates or to construction, given how little was built by June 2026.
- The next DLD inspection, which will show whether work has picked up after the slow start.
Questions buyers also ask
When will Samana Sky Views be completed?
The DLD register holds a registered completion date of 31 July 2028. Bayut and Property Finder list Q3 2028.
Has the Samana Sky Views handover date been delayed?
Compared with launch, yes. Agent listings in July 2025 gave a 2027 completion (Seven Luxury Real Estate; The Luxury Portfolio Dubai). The registered date is now 31 July 2028.
How far has construction got at Samana Sky Views?
The DLD inspection on 16 June 2026 recorded 2.23% complete, up 2.19 points since 5 February 2026. Construction started on 1 September 2025 (DLD project register via Continental Club).
Is Samana Sky Views sold out?
Nearly. Continental Club counts 547 DLD-registered sales against 556 registered units (accessed 11 Oct 2026).