Palm Jebel Ali Frond P
Palm Jebel Ali Frond P handover date: registered for 29 September 2027 on the DLD register, with the frond's 90 villas 34.65% built at the 4 August 2026 inspection. Progress history, DLD villa sales and the 80/20 payment plan.
Short answer
The Palm Jebel Ali Frond P handover date on the Dubai Land Department (DLD) register is 29 September 2027. Frond P is DLD project 2590, a group of 90 villas by Nakheel, and it was 34.65% complete at the DLD inspection on 4 August 2026, up from 26.67% on 30 April 2026 (Continental Club, registry updated 25 Sep 2026). Nakheel says the first Palm Jebel Ali villas will be handed over in phases from late 2026 through 2027, but it has not said which fronds come first. Frond P is the least advanced of Fronds K to P.
- Status
- under construction
- Handover date
- Registered completion date 29 Sep 2027 (DLD); Nakheel says first Palm Jebel Ali villa handovers run from late 2026 through 2027
- Construction
- 34.65% complete (DLD inspection, 4 Aug 2026)
- Payment plan
- 20/60/20: 20% on booking, 60% during construction, 20% on handover
- Starting price
- From AED 18M at launch (Sep 2023, Property Finder)
Registered completion date (DLD)
29 Sep 2027
DLD project 2590, via Continental Club and fäm Properties
Construction progress
34.65%
DLD inspection, 4 Aug 2026
Villas on the DLD register
90
Continental Club, registry updated 25 Sep 2026
Median DLD sale price
About AED 2,517 per sq ft
AED 27,091 per sq m, 101 sales since 2023 (Continental Club)
When will Palm Jebel Ali Frond P be handed over?
The Frond P handover date on the Dubai Land Department (DLD) register is 29 September 2027. Frond P is one of the villa fronds of Palm Jebel Ali, Nakheel’s second palm island, and it is registered as its own project, number 2590, with 90 villas. Property Finder and fäm Properties show the same September 2027 date (accessed 6 October 2026).
Nakheel has not given a date for Frond P on its own. It said on 20 August 2026 that the first villas on the island would be handed over in phases from late 2026 and through 2027, and that the 728 villas on Fronds K to P had entered internal and external finishing. It did not say which fronds come first. By 6 October 2026 no completed handover on Frond P had been announced.
Frond P shares the earliest registered date on the island with Frond O. It is, however, the least built of Fronds K to P. Frond O was 55.70% complete at its August 2026 inspection, against 34.65% for Frond P.
Building-by-building dates and how the date has changed: Palm Jebel Ali Frond P handover date.
Palm Jebel Ali Frond P construction update
The DLD register records construction on Frond P starting on 13 September 2023. Progress picked up in 2026:
| Date | Progress | Inspection |
|---|---|---|
| 27 Jan 2026 | 15.60% | RERA, via Nakheel |
| 10 Mar 2026 | 20.50% | Nakheel internal inspection |
| 30 Apr 2026 | 26.67% | DLD |
| 4 Aug 2026 | 34.65% | DLD |
Sources: Nakheel construction progress page (17 June 2026); Continental Club, DLD registry updated 25 September 2026. The DLD figure was unchanged when Palm Observer rechecked the register on 3 September 2026.
Between the April and August 2026 inspections, Frond P gained 7.98 points, about 2.5 points a month. To reach 100% by 29 September 2027, it would need to average about 4.7 points a month from August 2026. Nakheel’s progress page puts the whole Fronds K to P group at 93.27% for substructure, 68.40% for superstructure and 18.76% for MEP work (17 June 2026).
Palm Jebel Ali Frond P homes and sizes
Property Finder describes Frond P as a collection of 6 bedroom villas, and Nakheel describes Fronds K to P as its Beach and Coral Collection. Villa sizes recorded in DLD sales on Frond P fall into a few groups:
| Size in DLD sales | About | Example |
|---|---|---|
| 686.6 sq m | 7,390 sq ft | AED 19.8 million, 18 Mar 2026 |
| 709.8 sq m | 7,640 sq ft | AED 20 million, 9 Jun 2026 |
| 1,218.8 sq m | 13,120 sq ft | AED 32.07 million, 14 Jan 2026 |
| 1,259.4 sq m | 13,560 sq ft | AED 29.8 million, 29 Apr 2026 |
Source: Continental Club, DLD transaction registry updated 23 September 2026. The DLD records do not name the villa type.
Palm Jebel Ali Frond P prices and resale
Frond P went on sale on 13 September 2023, and Property Finder gives a launch price from AED 18 million. Continental Club counts 101 DLD-registered sales since 2023, at a median of AED 27,091 per square metre, about AED 2,517 per sq ft.
The smaller villas have moved little in price. A 7,640 sq ft villa sold for AED 19.12 million on 26 December 2023, and one of the same size sold for AED 20 million on 9 June 2026. The larger 13,120 sq ft villas sold for AED 32.63 million in January 2025 and AED 32.07 million in January 2026 (Continental Club, DLD transactions).
Palm Jebel Ali Frond P payment plan
Property Finder and Continental Club list a 20/60/20 plan: 20% on booking, 60% during construction and 20% on handover. On a villa at the AED 18 million launch price, AED 3.6 million falls due at handover. The 4% DLD fee is paid on top.
Palm Jebel Ali Frond P developer and delivery record
The DLD register names The Palm Jebel Ali Co. (L.L.C) as the developer, and the villas are sold by Nakheel. Nakheel, now part of Dubai Holding, built Palm Jumeirah. On Palm Jebel Ali, it awarded Dh5 billion of contracts in 2024 for the Beach and Coral Collection villas across Fronds K to P (Nakheel, 16 June 2026). No villa on the island had a confirmed handover by 6 October 2026.
What to check before buying at Palm Jebel Ali Frond P
- The completion date and grace period in the SPA for the villa, since Nakheel has not tied its late 2026 start to Frond P.
- The next DLD inspection for project 2590 in the DLD project status service, to see whether progress is keeping pace with the September 2027 date.
- The villa’s size and type, since DLD sales on Frond P range from about 7,390 sq ft to more than 13,000 sq ft.
- How much of the price is still owed to Nakheel on a resale, including the 20% due at handover.
Palm Jebel Ali Frond P location: Palm Jebel Ali, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Frond P handover date at Palm Jebel Ali?
The DLD register gives Palm Jebel Ali Frond P a registered completion date of 29 September 2027 (Continental Club; fäm Properties, accessed 6 Oct 2026). Property Finder shows the same date. Nakheel's own guidance is that the first villas on the island hand over in phases from late 2026 through 2027, without naming Frond P.
How far along is construction on Frond P?
34.65% at the DLD inspection on 4 August 2026. It was 15.60% at the RERA inspection of 27 January 2026, 20.50% at Nakheel's internal inspection of 10 March 2026 and 26.67% at the DLD inspection of 30 April 2026.
How many villas are on Frond P?
The DLD register lists 90 villas on Frond P, on a project area of 86,140.88 square metres, with construction recorded as starting on 13 September 2023 (Continental Club, registry updated 25 Sep 2026).
What do Frond P villas sell for?
DLD-registered sales in 2026 include a villa of about 7,640 sq ft at AED 20 million on 9 June and one of about 7,390 sq ft at AED 19.8 million on 18 March. Larger villas of about 13,560 sq ft sold for AED 29.8 million on 29 April 2026 (Continental Club, DLD transactions).