Nuve by Zoya

Nuve by Zoya in DLRC: Q2 2028 handover and 30 June 2028 completion date, 0.79% DLD progress, launch and DLD prices, sizes and the 50/50 post-handover payment plan.

Furnished studios, 1 and 2 bedroom apartments Updated 11 October 2026

Short answer

Nuve by Zoya is due for handover in Q2 2028, and its registered completion date with DLD is 30 June 2028. The DLD inspection on 20 July 2026 recorded 0.79% complete, three months after the registered construction start of 15 April 2026. Zoya Developments launched the 232 home building in March 2026 from AED 695,000 on a 50/50 plan, with 40% of the price paid over three years after handover.

Status
under construction
Handover date
Q2 2028 (Zoya Developments); DLD registered completion date 30 Jun 2028
Construction
0.79% complete (DLD inspection, 20 Jul 2026)
Payment plan
50/50: 10% on booking, 10% within 45 days, 30% at 1% a month, 10% on handover, 40% after handover over 3 years
Starting price
From AED 695,000 at launch (Mar 2026)

DLD registered completion date

30 Jun 2028

DLD project register via Mitchells, register as at 4 Oct 2026

Construction progress

0.79%

DLD inspection, 20 Jul 2026

Launch price

From AED695,000

Zoya Developments via Zawya, Mar 2026

Median DLD price, studio

AED 1,602 per sq ft

Mitchells, 41 sales to 5 Oct 2026

When will Nuve by Zoya be handed over?

Nuve by Zoya is scheduled for handover in Q2 2028, the date Zoya Developments gave at launch in March 2026 (Zawya). The Dubai Land Department (DLD) register, where it is listed as “Nuve By Zoya” in Wadi Al Safa 5 (the registered area that covers Dubailand Residence Complex), holds a registered completion date of 30 June 2028.

The DLD inspection on 20 July 2026 recorded the project 0.79% complete. That was about three months after the registered construction start of 15 April 2026, leaving just under two years to the registered date.

Building-by-building dates and how the date has changed: Nuve by Zoya handover date.

Nuve by Zoya construction update

The DLD register records construction starting on 15 April 2026 and lists the project as under construction, DLD project number 4290 (Mitchells, register as at 4 October 2026). The only published DLD inspection, on 20 July 2026, recorded 0.79% complete, which is consistent with site preparation and foundation works. Zoya has not published its own construction update for Nuve.

Nuve by Zoya homes and sizes

Nuve is a single mid-rise building with fully furnished homes and smart home systems. The launch release lists 232 residences; the DLD register lists 234.

Home type Units (Zoya) Size
Studio 169 414 to 519 sq ft
1 bedroom 51 770 to 899 sq ft
2 bedroom 12 1,177 sq ft

Unit counts and sizes are from Zoya’s launch release (Zawya, 17 March 2026). Studios make up about 73% of the building, so most units will compete in the DLRC studio rental market after handover. Amenities listed include an infinity pool, plunge pool, jacuzzi, indoor and outdoor gyms, a children’s play area and a rooftop deck.

Nuve by Zoya prices and resale

Zoya launched Nuve in March 2026 with prices from AED 695,000 and a total project value of AED 202 million (Zawya). Grand Reve Realty listed studios from AED 687,000, 1 bedrooms from AED 912,000 and 2 bedrooms from AED 1,459,000 (accessed 11 October 2026).

The DLD register shows 179 sales registered to 4 September 2026. Across 51 sales in the detailed data, the median was about AED 693,000, or AED 1,506 per sq ft, for a median size of 432 sq ft. Studios had a median of AED 1,602 per sq ft over 41 sales, 1 bedrooms AED 1,201 per sq ft and 2 bedrooms AED 1,273 per sq ft over fewer sales (Mitchells, to 5 October 2026). Mitchells puts the project about 4% above the DLRC off-plan median of AED 1,445 per sq ft. All recorded sales so far are off-plan purchases.

Nuve by Zoya payment plan

Zoya markets Nuve on a 50/50 plan with 1% monthly instalments:

  • 10% on booking, plus the 4% DLD fee
  • 10% within 45 days of booking
  • 30% during construction, 1% a month
  • 10% on handover
  • 35% after handover, 1% a month for 35 months
  • 5% final instalment, within 36 months of handover

The schedule is from Zoya’s brochure and Grand Reve Realty. Half the price is paid by handover and the rest over three years after it.

Nuve by Zoya developer and delivery record

Zoya Developments is an Indian developer that announced its entry into Dubai in January 2026, with more than AED 2 billion allocated for the following three years (Zoya Developments, January 2026). Its launch release says the group has more than 14 years in the UAE market. In Dubai it has launched several projects in quick succession, including Pristine by Zoya in Al Furjan, Miorah by Zoya in Dubai South and Izel by Zoya in DLRC, which opened sales in February 2026 with a Q3 to Q4 2028 handover (CBNME, 22 May 2026). None of its Dubai projects had been completed by October 2026, so Nuve’s delivery cannot yet be judged against a Dubai track record.

What to check before buying at Nuve by Zoya

  1. The completion date in the SPA and how it relates to the registered 30 June 2028 date, including any grace period.
  2. The post-handover schedule, since 40% is paid over three years after handover and the developer has not yet delivered a Dubai project.
  3. The furniture package included in the price, as Zoya sells every unit furnished.
  4. DLD inspection figures over the next year, which will show whether the building is on course for mid 2028.

Nuve by Zoya location: Dubailand Residence Complex, Dubai

Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.

Questions buyers also ask

What is the Nuve by Zoya handover date?

Zoya Developments gives Q2 2028 (Zawya, March 2026). The DLD register holds a registered completion date of 30 June 2028, the last day of that quarter.

What is the Nuve by Zoya completion date?

30 June 2028 in the DLD project register. The DLD inspection on 20 July 2026 recorded 0.79% complete (Mitchells, register as at 4 Oct 2026).

What is the Nuve by Zoya price?

Prices started from AED 695,000 at launch in March 2026 (Zawya). DLD-registered sales to 5 October 2026 had a median of about AED 693,000, or AED 1,506 per sq ft, mostly for studios (Mitchells).

What is the Nuve by Zoya payment plan?

A 50/50 plan: 10% on booking, 10% within 45 days, 30% at 1% a month during construction, 10% on handover, then 35% at 1% a month for 35 months and a final 5% within 36 months of handover (Zoya brochure; Grand Reve Realty).

How many units are in Nuve by Zoya?

Zoya's launch release lists 232 residences: 169 studios, 51 one bedroom and 12 two bedroom units. The DLD register lists 234 units.

Sources