MAS Barsha Residency

MAS Barsha Residency in Al Barsha 1: handover and completion date, prices and the 60/40 payment plan. 26.34% built in August 2026 against a registered date of 21 November 2026.

1, 2 and 3 bedroom apartments Updated 11 October 2026

Short answer

MAS Barsha Residency has a registered completion date of 21 November 2026 on the DLD register, but it was only 26.34% complete at the DLD inspection on 3 August 2026, so that date will not be met. Propsearch shows the estimate revised from November 2026 to Q3 2027. The 242 unit building in Al Barsha 1 sells 1 to 3 bedroom apartments from AED 1.8 million on a 60/40 plan. DLD-registered sales in 2026 were mostly at about AED 1,800 per sq ft, with a median of AED 1.91 million for a 1 bedroom.

Status
under construction
Handover date
Registered completion 21 Nov 2026; Propsearch shows a revised Q3 2027
Construction
26.34% complete (DLD inspection, 3 Aug 2026)
Payment plan
60% during construction, 40% on handover
Starting price
From AED 1.8M (1 bed, Continental Club and Binayah)

Construction

26.34%

DLD inspection, 3 Aug 2026

Registered completion date

21 Nov 2026

DLD register via Continental Club

Revised estimate

Q3 2027

Propsearch, updated 2 Jun 2026

Median 2 bedroom price

AED2.83M

27 sales, DLD data via Continental Club

When will MAS Barsha Residency be handed over?

The DLD register gives MAS Barsha Residency, project 3399, a registered completion date of 21 November 2026, two years after the registered start on 21 November 2024. Broker pages still list Q4 2026 (Binayah).

That date will not be met. The DLD inspection on 3 August 2026 put the building at 26.34% complete. Propsearch records that the estimated handover of November 2026 was revised to Q3 2027. Continental Club’s pace estimate, based on the past year of inspections, points to 100% in March 2030. MAS Development has not announced a new date.

Building-by-building dates and how the date has changed: MAS Barsha Residency handover date.

MAS Barsha Residency construction update

DLD inspections show steady but slow progress: 10.46% on 23 October 2025, 16.02% on 11 November 2025, 23.84% on 19 June 2026 and 26.34% on 3 August 2026 (Continental Club). That is about 1.7 points a month over the past year. Dubai Handover dates the 26.3% figure to an inspection on 21 July 2026, so trackers differ slightly on the inspection date.

The building is ground, four parking levels, 12 residential floors and roof, with shops at the base. The main contractor is Al Serh Al Kabeer Construction and the consultant is Future Art Engineering Consultancy. The developer filed a project value of AED 134.7 million with DLD (Propsearch).

MAS Barsha Residency homes and sizes

The building has 242 units: 108 one bedroom, 114 two bedroom and 12 three bedroom apartments, plus 8 commercial units (Binayah).

Home type Units Sizes in DLD sales
1 bedroom 108 About 948 to 1,061 sq ft
2 bedroom 114 About 1,551 to 1,954 sq ft
3 bedroom 12 About 2,094 to 2,899 sq ft

Sizes are converted from DLD-registered sales between February and August 2026 (Continental Club; Propsearch). Amenities include an infinity pool, gym, sauna, yoga room, cinema, co-working space and a children’s play area.

MAS Barsha Residency prices and resale

Prices start from AED 1.8 million for a 1 bedroom (Continental Club; Binayah). Continental Club counts 64 DLD-registered sales, only one of them a resale. The medians are AED 1,910,376 for a 1 bedroom of about 98 square metres, AED 2,832,426 for a 2 bedroom of about 146 square metres and AED 4,466,718 for a 3 bedroom of about 231 square metres. Most sales register at about AED 1,800 per sq ft, the rate Propsearch shows for sales in February and March 2026.

Recent sales include a 1 bedroom of 98.2 square metres at AED 2,108,530 on 13 August 2026 and a 2 bedroom of 144.1 square metres at AED 2,791,746 on 20 August 2026. A unit of 194.1 square metres sold for AED 5,850,264 on 27 August 2026.

MAS Barsha Residency payment plan

The plan is 60/40: 60% during construction and 40% on handover, with the handover payment due at 100% completion (Continental Club). On a AED 1.8 million 1 bedroom, AED 720,000 falls due at handover. Binayah’s page mentions possible post-handover options, but no post-handover schedule has been published.

What to check before buying at MAS Barsha Residency

  1. The completion date and grace period in the SPA, since the registered date of 21 November 2026 cannot be met at 26.34% progress.
  2. How the construction instalments are scheduled. If the 60% is tied to dates rather than progress, most of it may be paid long before the building is finished.
  3. The price paid against DLD sales, which cluster at about AED 1,800 per sq ft.
  4. The escrow account, held at Mashreq Bank, against project 3399 on the Dubai REST app.

MAS Barsha Residency location: Al Barsha 1, Dubai

Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.

Questions buyers also ask

What is the MAS Barsha Residency handover date?

The DLD register shows a registered completion date of 21 November 2026. Construction was 26.34% complete at the DLD inspection on 3 August 2026, so that date will not be met. Propsearch shows a revised estimate of Q3 2027.

What is the MAS Barsha Residency completion date?

The completion date on the DLD register is 21 November 2026, for project 3399, with construction registered as starting on 21 November 2024 (Continental Club).

What is the MAS Barsha Residency payment plan?

The plan is 60/40: 60% during construction and 40% on handover, with the handover payment due at 100% completion (Continental Club; Binayah).

What is the price of MAS Barsha Residency?

Prices start from AED 1.8 million for a 1 bedroom. DLD-registered sales show medians of AED 1.91 million for a 1 bedroom, AED 2.83 million for a 2 bedroom and AED 4.47 million for a 3 bedroom (Continental Club, DLD data to 6 Oct 2026).