
Maison Elysee III by Pantheon
Maison Elysee III by Pantheon in JVC: DLD completion date 31 October 2027, only 4.39% built in June 2026, studios from about AED 700,000 and a plan with 35% after handover.
Short answer
Maison Elysee III by Pantheon, a 28 floor tower of 379 apartments in Jumeirah Village Circle, has a registered completion date of 31 October 2027 in the Dubai Land Department (DLD) project register, and Pantheon and the portals give Q4 2027. A DLD inspection on 25 June 2026 recorded only 4.39% complete, 20 months after construction started. Studios were offered from AED 699,900 at pre-launch, with 35% of the price payable over about three years after handover.
- Status
- under construction
- Handover date
- Q4 2027 (Pantheon and portals); registered completion date 31 October 2027 (DLD)
- Construction
- 4.39% complete (DLD inspection, 25 Jun 2026)
- Payment plan
- Post-handover plan: about 65% by handover, 35% over about three years after handover
- Starting price
- From AED 699,900 at pre-launch; AED 819,900 on Property Finder
Registered completion date
31 Oct 2027
DLD project register via Continental Club
Construction progress
4.39%
DLD inspection, 25 Jun 2026
Median studio sale
AED702,900
71 DLD sales, via Continental Club, Oct 2026
Paid after handover
35%
Pantheon and Property Finder
When will Maison Elysee III by Pantheon be handed over?
The Dubai Land Department (DLD) project register lists the tower as Maison Elysee Iii By Pantheon, project number 3281, with a registered completion date of 31 October 2027. Pantheon’s marketing, Property Finder and Binayah all give Q4 2027, so the published dates agree.
Progress is the issue. The DLD inspection of 25 June 2026 recorded 4.39% complete (DLD project register via Continental Club, registry updated 8 October 2026). Reaching 100% by 31 October 2027 would mean building about 96% of a 28 floor tower in 16 months.
Building-by-building dates and how the date has changed: Maison Elysee III by Pantheon handover date.
Maison Elysee III by Pantheon construction update
Sales and construction both started on 1 November 2024 (Property Finder; DLD register). The DLD inspection history is:
| Inspection | Progress |
|---|---|
| 11 Oct 2024 | 0% |
| 13 May 2025 | 0.22% |
| 10 Nov 2025 | 2.30% |
| 31 Mar 2026 | 3.57% |
| 25 Jun 2026 | 4.39% |
That is an average of about 0.28 points a month. Continental Club notes that completed Dubai projects in its data rose by a median of 2.48 points a month. No newer inspection had been published by 11 October 2026.
Maison Elysee III by Pantheon homes and sizes
The register describes one building with two basements, a ground floor, five podium levels, 28 floors and a roof, holding 379 units.
| Home type | Units | Size range |
|---|---|---|
| Studio | 87 | 378 to 400 sq ft |
| 1 bedroom | 257 | 621 to 703 sq ft |
| 2 bedroom | 30 | 713 to 717 sq ft |
| Other | 5 | 474 to 2,759 sq ft |
Ranges exclude the smallest and largest 5% of each type (Continental Club). Property Finder lists some 2 bedroom layouts up to 1,066 sq ft.
Maison Elysee III by Pantheon prices and resale
Pantheon’s pre-launch page offered studios from AED 699,900, and Property Finder lists studios from AED 819,900, 1 bedrooms from AED 1.2 million and 2 bedrooms from AED 1.3 million. By October 2026 the DLD register held 261 sales in the tower, two of them resales (transaction register updated 7 October 2026). Median prices were AED 702,900 for studios (71 sales), AED 1,059,900 for 1 bedrooms (160) and AED 1,279,900 for 2 bedrooms (26). The overall median, about AED 1,726 per sq ft, was down 3% on a year earlier while the JVC median rose 1%.
Maison Elysee III by Pantheon payment plan
Pantheon’s pre-launch page set out a six year plan:
- 20% on booking
- 1% a month for 35 months during construction
- 10% on completion
- 35% over 35 months after handover
Property Finder shows a 35/25/5/35 version, and Binayah describes 65/35 with three years post-handover. All versions leave 35% to pay after handover. The monthly construction instalments run on dates, not progress, so they continue whatever the build stage.
Maison Elysee III by Pantheon developer and delivery record
Pantheon Development was founded by Kalpesh Kinariwala and builds mainly in JVC. In March 2024 it said it had handed over AED 1 billion of projects in JVC, including Pantheon Boulevard and Pantheon Elysee I and II (Khaleej Times). Its current Maison Elysee towers are running behind their dates: Maison Elysee I was 21.12% complete on 6 July 2026 against a registered date of 31 March 2027, and Maison Elysee II was 23.17% on 4 September 2026 against Q1 2027 (DLD register via Continental Club).
What to check before buying at Maison Elysee III by Pantheon
- The completion date and grace period in the SPA, given progress of 4.39% with 16 months to the registered date.
- How the post-handover 35% is scheduled. Its start depends on the handover date, so a late handover moves it later too.
- The name. Maison Elysee III is different from the older Pantheon Elysee towers in JVC.
- Which payment plan version applies. Pantheon, Property Finder and brokers publish different splits before handover.
Maison Elysee III by Pantheon location: Jumeirah Village Circle, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the Maison Elysee III handover date?
Pantheon and the portals give Q4 2027. The DLD register records a completion date of 31 October 2027 (via Continental Club, registry updated 8 Oct 2026).
What is the Maison Elysee III completion date?
The registered completion date is 31 October 2027. The DLD inspection of 25 June 2026 recorded 4.39% complete.
What is the Maison Elysee III price?
Pantheon's pre-launch page offered studios from AED 699,900. Property Finder lists studios from AED 819,900. Registered sales have medians of AED 702,900 for studios, AED 1,059,900 for 1 bedrooms and AED 1,279,900 for 2 bedrooms (DLD data via Continental Club, Oct 2026).
What is the Maison Elysee III payment plan?
Pantheon's pre-launch page set out 20% on booking, 1% a month for 35 months during construction, 10% on completion and 35% over 35 months after handover. Property Finder shows a 35/25/5/35 version. Both leave 35% to pay after handover.
Is Maison Elysee III the same as Pantheon Elysee III?
No. Maison Elysee III went on sale in November 2024. Khaleej Times reported in March 2024 that an earlier Pantheon project, Elysee 3, was due for handover in early 2024.
