Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Maison Elysee III by Pantheon handover date?

Updated 11 October 2026 Maison Elysee III by Pantheon

Short answer

Maison Elysee III by Pantheon has a registered completion date of 31 October 2027 in the Dubai Land Department project register, and Pantheon and the portals give Q4 2027. A DLD inspection on 25 June 2026 recorded 4.39% complete. With about 96% of the tower left to build in 16 months, the date has not formally moved but progress is far behind the pace it would need.

Registered completion date (DLD)

31 Oct 2027

DLD project register via Continental Club, registry updated 8 Oct 2026

Latest construction progress

4.39%

DLD inspection, 25 Jun 2026

Developer and portal date

Q4 2027

Pantheon; Property Finder, accessed 11 Oct 2026

Average pace since start

0.28 points a month

Continental Club, from DLD inspections

Maison Elysee III by Pantheon handover date: the latest position

Maison Elysee III has a registered completion date of 31 October 2027 in the Dubai Land Department (DLD) project register, and Pantheon and Property Finder give Q4 2027. The DLD inspection of 25 June 2026 recorded 4.39% complete. Full project details are on the Maison Elysee III by Pantheon page.

No source has published a new date. Continental Club’s projection, based on the pace so far, puts 100% decades away; it labels this an estimate, not a developer commitment. The figure shows how slowly the site has moved, not a forecast.

Maison Elysee III by Pantheon handover date by building

Maison Elysee III is one tower of 379 units. Pantheon’s two earlier Maison Elysee towers in JVC are shown for comparison.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Maison Elysee III (379 units) 4.39% (25 Jun 2026) 31 Oct 2027 Q4 2027 (Pantheon, Property Finder)
Maison Elysee II (352 units) 23.17% (4 Sep 2026) Not stated Q1 2027 (Prop971)
Maison Elysee I 21.12% (6 Jul 2026) 31 Mar 2027 Q1 2027 (Khaleej Times, Mar 2024)

Progress figures are from the DLD project register via Continental Club, accessed 11 October 2026.

How the Maison Elysee III by Pantheon handover date has changed

Date What was stated Source
11 Oct 2024 First DLD inspection at 0% DLD register via Continental Club
1 Nov 2024 Sales and construction start; delivery Q4 2027 Property Finder; DLD register
13 May 2025 DLD inspection at 0.22% DLD register
10 Nov 2025 DLD inspection at 2.30% DLD register
31 Mar 2026 DLD inspection at 3.57% DLD register
25 Jun 2026 DLD inspection at 4.39%; registered date still 31 October 2027 DLD register

The published date has not changed, but the recorded pace of about 0.28 points a month is far below the roughly 6 points a month needed to finish on time.

What the Maison Elysee III by Pantheon handover date means for payments

Pantheon’s pre-launch plan was 20% on booking, 1% a month for 35 months during construction, 10% on completion and 35% over 35 months after handover. Property Finder shows 35% down, 25% during construction, 5% on handover and 35% after handover. Under the monthly version, the 35 construction instalments run to late 2027 on a fixed calendar, so buyers may finish paying the construction share long before the tower is near completion. The 35% post-handover share only starts once the building is handed over, so a late completion pushes that period later as well.

What to check before relying on the Maison Elysee III by Pantheon date

  1. The anticipated completion date and grace period in the SPA, and what the SPA says about compensation or termination if completion runs late.
  2. The next DLD inspection. A reading well above 4.39% would show the pace picking up; Maison Elysee II gained 4.75 points between its July and September 2026 inspections.
  3. How the 1% monthly instalments are defined in the SPA, since they are dated rather than linked to progress.

Questions buyers also ask

What is the Maison Elysee III completion date?

The DLD register records 31 October 2027 for project 3281, Maison Elysee Iii By Pantheon. Property Finder gives the same date.

Has the Maison Elysee III handover date been delayed?

Not formally. Q4 2027 has been the published date since sales began in November 2024. But the tower was 4.39% complete on 25 June 2026, so finishing by 31 October 2027 would need a pace many times faster than recorded so far.

Is Maison Elysee III finished?

No. It was 4.39% complete at the DLD inspection of 25 June 2026.

When will Maison Elysee I and II be ready?

Maison Elysee I has a registered date of 31 March 2027 and was 21.12% complete on 6 July 2026. Maison Elysee II is listed for Q1 2027 and was 23.17% complete on 4 September 2026 (DLD register via Continental Club).

Sources

  1. Pantheon Development, Maison Elysee III pre-launch page (opens in a new tab)maisonelysee3.pantheondevelopment.ae · accessed 11 Oct 2026
  2. Prop971, Maison Elysee II (opens in a new tab)prop971.com · accessed 11 Oct 2026
Request a Unit Review