08 Life Residences
Deniz Development's 107-unit building in International City Phase 2. Registered completion date of 31 May 2026 has passed; 64.87% built on 26 August 2026. Prices, sizes and the 60/40 payment plan.
Short answer
08 Life Residences, a 107-unit building by Deniz Development in International City Phase 2, had a registered completion date of 31 May 2026, and that date has passed. The last Dubai Land Department (DLD) inspection, on 26 August 2026, recorded it 64.87% complete. The developer's stated date was Q2 2026, and some listings now show Q4 2026. 1 bedrooms were listed from AED 877,019, and DLD sales have a median of about AED 1,038 per sq ft.
- Status
- under construction
- Handover date
- DLD registered completion 31 May 2026 (passed); developer Q2 2026; some portals now Q4 2026
- Construction
- 64.87% complete (DLD inspection, 26 Aug 2026)
- Payment plan
- 60/40: 10% on booking, 10% on SPA, 40% during construction, 40% on handover (emirates.estate)
- Starting price
- 1 bedrooms from AED 877,019 (Property Finder)
Registered completion date
31 May 2026 (passed)
DLD project register via Continental Club
Construction progress
64.87%
DLD inspection, 26 Aug 2026
Homes
107
13 studios, 62 one bed, 24 two bed, 8 other (DLD register via Continental Club)
Median registered price per sq ft
About AED 1,038
97 DLD sales since 2025, Continental Club, transactions to 7 Oct 2026
When will 08 Life Residences be handed over?
The Dubai Land Department (DLD) register gave 08 Life Residences a completion date of 31 May 2026. That date has passed. The last DLD inspection, on 26 August 2026, recorded the building 64.87% complete. The developer’s stated date was Q2 2026 (Continental Club, developer supplied; Westgate Dubai), and Property Finder still shows May 2026. emirates.estate now lists Q4 2026.
Between April and August 2026 the building gained about 17 points in four months. At that pace Continental Club estimates 100% around 15 June 2027. That is a calculation, not a developer commitment, and a passed registered date only means the register has not been updated.
Building-by-building dates and how the date has changed: 08 Life Residences handover date.
08 Life Residences construction update
Construction started on 5 October 2024 (DLD project number 3590). DLD inspections recorded 35.82% on 22 December 2025, 48.03% on 30 April 2026 and 64.87% on 26 August 2026 (DLD register via Continental Club, registry updated 8 October 2026). Progress rose by about 12 points in the four months to April 2026 and by about 17 points in the four months to August, so the pace has picked up.
The building has a ground floor, two podium levels and seven residential floors, in concrete with blockwork. It is in Al Warsan 4, the DLD district that covers International City Phase 2, next to Dubai Silicon Oasis (Gulf News). The escrow bank is Emirates NBD.
08 Life Residences homes and sizes
| Home type | Units | Size |
|---|---|---|
| Studio | 13 | 404 to 474 sq ft |
| 1 bedroom | 62 | 758 to 917 sq ft |
| 2 bedroom | 24 | 1,317 to 1,437 sq ft |
| Other | 8 | 281 to 419 sq ft |
Unit counts and sizes are from the DLD register via Continental Club. Westgate Dubai lists 12 shared facilities, including a pool, a covered gym, a yoga deck, a children’s play area and retail units.
08 Life Residences prices and resale
Property Finder lists 1 bedrooms from AED 877,019 and 2 bedrooms from AED 1.4 million, with studio prices not published. emirates.estate showed remaining 1 bedrooms of about 929 sq ft at AED 1.03 million to AED 1.05 million and 2 bedrooms at AED 1.45 million to AED 1.72 million, accessed 11 October 2026. Westgate Dubai marks the project sold out.
Continental Club counts 97 DLD sales since 2025, all bought from the developer, at a median of AED 11,176 per square metre, about AED 1,038 per sq ft (transactions to 7 October 2026). By type, medians were about AED 1,086 per sq ft for studios, AED 1,048 for 1 bedrooms and AED 992 for 2 bedrooms. Recent registered sales were:
- a studio of 405 sq ft for AED 437,194 on 28 January 2026 (Property Finder)
- a 1 bedroom of about 925 sq ft for AED 971,712 on 2 February 2026
- a 2 bedroom of about 1,316 sq ft for AED 1,328,320 on 2 February 2026
Continental Club records the building’s median price per square metre down 1% over the past year, against a 4% rise for the district.
08 Life Residences payment plan
emirates.estate lists a 60/40 plan: 10% on booking, 10% on signing the SPA (plus the 4% DLD fee, an AED 5,250 admin fee and VAT), 40% in instalments during construction and 40% on handover at 100% completion. Property Finder and Westgate Dubai do not publish the percentages. Under this plan the final 40% is tied to completion, so it has moved later with the missed May 2026 date.
08 Life Residences developer and delivery record
Deniz Development, registered with DLD as Deniz Properties, describes itself as a developer with Central Asian roots (Gulf News, 14 May 2025). Mimar designed the building and supervises construction, and Seeniun Properties leads sales. Sources disagree on the launch date: Property Finder gives 5 October 2024, the same day construction started, while Gulf News reported a launch event on 13 May 2025. Deniz has since launched a second building with Seeniun, 09 Life Residences in Dubailand Residence Complex. On 08 Life, both the registered 31 May 2026 date and the developer’s Q2 2026 date were missed.
What to check before buying at 08 Life Residences
- A revised completion date on the DLD register, since 31 May 2026 has passed and no new date had been filed by October 2026.
- The handover clause and grace period in the SPA, as listings now range from May 2026 to Q4 2026.
- What is still owed. Under the 60/40 plan, 40% falls due on handover, so a resale buyer should confirm what the seller has paid.
- Price per sq ft against DLD sales. Registered sales have clustered around AED 1,000 to AED 1,100 per sq ft.
08 Life Residences location: International City Phase 2, Dubai
Map shows the area. Check the exact plot in the developer's site plan or the DLD project record. Check any project's DLD status.
Questions buyers also ask
What is the 08 Life Residences handover date?
The DLD register gave a completion date of 31 May 2026, which has passed. At the DLD inspection of 26 August 2026 the building was 64.87% complete (DLD register via Continental Club). The developer's stated date was Q2 2026; emirates.estate now lists Q4 2026.
What is the 08 Life Residences completion date?
The registered completion date is 31 May 2026, but the building was not complete by then. At the pace recorded between April and August 2026, Continental Club estimates 100% around 15 June 2027. That is a calculation, not a developer date.
What is the 08 Life Residences price?
Property Finder lists 1 bedrooms from AED 877,019 and 2 bedrooms from AED 1.4 million. DLD-registered sales include a 1 bedroom of about 925 sq ft for AED 971,712 and a 2 bedroom of about 1,316 sq ft for AED 1,328,320 on 2 February 2026 (Continental Club).
What is the 08 Life Residences payment plan?
emirates.estate lists a 60/40 plan: 10% on booking, 10% on signing the SPA, 40% during construction and 40% on handover. Property Finder does not publish the percentages.