When is the 08 Life Residences handover date?
Short answer
08 Life Residences had a registered completion date of 31 May 2026, and that date has passed. The last Dubai Land Department inspection, on 26 August 2026, recorded the building 64.87% complete. No revised date had been filed by October 2026; some listings give Q4 2026, while Continental Club's estimate from the recent pace is mid 2027.
Registered completion date
31 May 2026 (passed)
DLD project register via Continental Club
Latest construction progress
64.87%
DLD inspection, 26 Aug 2026
Developer's stated date
Q2 2026
Continental Club (developer supplied); Westgate Dubai
Latest portal date
Q4 2026
emirates.estate, accessed 11 Oct 2026
08 Life Residences handover date: the latest position
08 Life Residences was registered with the Dubai Land Department (DLD) for completion on 31 May 2026. That date has passed. At the last DLD inspection, on 26 August 2026, the building was 64.87% complete, and the register still showed the May 2026 date in October 2026. Prices, sizes and the payment plan are on the project page: 08 Life Residences.
The developer’s stated date was Q2 2026, and Property Finder still shows May 2026. emirates.estate has moved to Q4 2026. None of these later dates is on the DLD register.
08 Life Residences handover date by building
08 Life is one building with 107 units, registered as “08 Life Residences” (DLD project 3590) in International City Phase 2, DLD district Al Warsan 4.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| 08 Life Residences (107 units, G + 2 podium + 7 floors) | 64.87% (26 Aug 2026) | 31 May 2026 (passed) | Q2 2026 (developer, via Continental Club; Westgate Dubai); May 2026 (Property Finder); Q4 2026 (emirates.estate) |
How the 08 Life Residences handover date has changed
| Date | Event | Source |
|---|---|---|
| 5 Oct 2024 | Sales and construction start; completion registered for 31 May 2026 | Property Finder; DLD via Continental Club |
| 25 Mar 2025 | DLD inspection recorded | DLD via Continental Club |
| 13 May 2025 | Launch event held in Dubai | Gulf News |
| 22 Dec 2025 | DLD inspection: 35.82% | DLD via Continental Club |
| 30 Apr 2026 | DLD inspection: 48.03% | DLD via Continental Club |
| 31 May 2026 | Registered completion date passes | DLD via Continental Club |
| 26 Aug 2026 | DLD inspection: 64.87% | DLD via Continental Club |
| Oct 2026 | Register unchanged; emirates.estate lists Q4 2026 | Continental Club; emirates.estate |
The original plan gave about 20 months from construction start to completion. By the registered date the building was about half built: 48.03% at the inspection a month earlier. Progress has since sped up: about three points a month from December 2025 to April 2026, then about four points a month from April to August 2026. Finishing by 31 December 2026 would need about eight points a month from September, about double the recent rate. Continental Club’s projection at the recent pace is about 15 June 2027.
What the 08 Life Residences handover date means for payments
Under the 60/40 plan listed by emirates.estate, 10% is paid on booking, 10% on signing the SPA and 40% during construction. The last 40% is due on handover at 100% completion. That large final payment moves with the actual completion, so the delay pushes it back rather than bringing it forward. Buyers using a mortgage for the handover payment would need the bank’s approval to hold until the new date.
What to check before relying on the 08 Life Residences date
- Whether DLD has registered a new completion date. The 31 May 2026 date has passed and no revision had been filed by October 2026.
- The completion date and grace period in the SPA. Contracts signed in late 2024 and in 2025 may carry May 2026 or Q2 2026.
- The next DLD inspection, to see whether the April to August 2026 pace of about four points a month holds.
Questions buyers also ask
Is 08 Life Residences finished?
No. The DLD inspection of 26 August 2026 recorded the building 64.87% complete, after its registered completion date of 31 May 2026 had passed.
When will 08 Life Residences be completed?
No new date has been filed with DLD. emirates.estate lists Q4 2026. Continental Club's straight-line estimate from the April to August 2026 pace is about 15 June 2027, which is a calculation, not a developer date.
Has the 08 Life Residences handover date been delayed?
Yes, against the register. The DLD date of 31 May 2026 and the developer's Q2 2026 date both passed with the building about half built. Listings have since moved to Q4 2026.
How much is due on handover at 08 Life Residences?
40% of the price under the 60/40 plan listed by emirates.estate, payable at 100% completion.