Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Valores Residences handover date?

Updated 11 October 2026 Valores Residences

Short answer

Valores Residences has a registered completion date of 31 August 2026 on the Dubai Land Department (DLD) project register. A DLD inspection on 31 August 2026 recorded the building 98.36% complete, up from about 70.62% on 6 April 2026. The registered date has passed without the building being recorded at 100%, and the developer-supplied handover on Continental Club reads Q3 2027, so the SPA date for each unit is the one to confirm.

Registered completion date (DLD)

31 Aug 2026

DLD register via Continental Club, updated 5 Oct 2026

Latest construction progress

98.36%

DLD inspection, 31 Aug 2026

Developer-supplied handover

Q3 2027

Continental Club, accessed 11 Oct 2026

Original estimate

Aug 2026

Propsearch, updated 24 Sep 2026

Valores Residences handover date: the latest position

Valores Residences, DLD project 3068 in Al Furjan, has a registered completion date of 31 August 2026. The DLD inspection held on that same date recorded the building 98.36% complete (DLD register via Continental Club, updated 5 October 2026). Prices, sizes and the payment plan are on the Valores Residences page.

The date has passed with the building close to finished. Continental Club also lists a developer-supplied handover of Q3 2027 beside the 31 August 2026 registry date. Propsearch says the estimated handover “was” August 2026 and gives no new date. No handover announcement from the developer had been published by 11 October 2026.

Valores Residences handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Valores Residences (90 units) 98.36%, 31 Aug 2026 31 Aug 2026 Q3 2027 (developer-supplied, Continental Club); Aug 2026 (Propsearch)

It is a single building of ground floor, two podium levels, seven residential floors and a roof. The DLD register counts 90 units; the developer announced 87 homes in January 2025.

How the Valores Residences handover date has changed

Date Event Source
31 Aug 2024 Construction starts; completion registered for 31 August 2026 DLD register via Continental Club
20 Jan 2025 Developer says nearly all 87 homes are sold CBNME
Feb 2025 Sales launch recorded, with August 2026 as estimated handover Propsearch
6 Apr 2026 DLD inspection: about 70.62% Continental Club (98.36% less the 27.74 point gain)
31 Aug 2026 DLD inspection: 98.36%; registered date reached DLD register via Continental Club
Oct 2026 Registry shows 31 August 2026; developer-supplied handover Q3 2027 Continental Club, updated 5 Oct 2026

The building moved at about 5.9 points a month between April and August 2026. At that pace the final 1.64 points would take well under a month, so the main open item is the formal completion record rather than the structure. The Q3 2027 developer date is the one figure that points to a much later handover, and no source explains it.

What the Valores Residences handover date means for payments

The developer-supplied plan on Continental Club is 10% down payment, 40% during construction and 50% on handover. Propsearch lists 20% during construction and 80% on handover. On either version, at least half the price falls due at handover. For a 2 bedroom at the DLD median of AED 1,627,850, half is about AED 813,900, and the handover notice from the developer sets when it is due.

What to check before relying on the Valores Residences date

  1. Whether the DLD has recorded 100%. The register still showed 98.36% from the 31 August 2026 inspection in its 5 October 2026 update.
  2. Which date the SPA states. Registry and developer-supplied dates sit a year apart, at 31 August 2026 and Q3 2027.
  3. The handover notice and final payment amount, given the 50% versus 80% gap between sources.

Questions buyers also ask

Is Valores Residences finished?

Almost. The DLD inspection on 31 August 2026 recorded 98.36% progress. The building had not been recorded at 100% on the DLD register by the registry update of 5 October 2026.

What is the Valores Residences completion date?

The registered completion date is 31 August 2026 (DLD register via Continental Club). Propsearch gives the same month as the original estimate.

Has the Valores Residences handover date been delayed?

The registered date of 31 August 2026 has passed with the building at 98.36%. Continental Club also shows a developer-supplied handover of Q3 2027, which would be about a year later, though it does not say when that date was set.

How much is paid at Valores Residences handover?

Continental Club lists 50% on handover, after 10% down and 40% during construction. Propsearch lists 80% on handover. The SPA sets the figure for each unit.

Sources

  1. Propsearch, Valores Residences (opens in a new tab)propsearch.ae · updated 24 Sep 2026
Request a Unit Review