When is the St. Regis Residences Downtown Dubai handover date?
Short answer
St. Regis The Residences in Downtown Dubai has a registered completion date of 25 December 2026, and Emaar's handover date is Q4 2026. The latest DLD inspection, on 2 June 2026, recorded 76.05% complete. Continental Club's projection from the recent pace reaches 100% around 26 January 2027, so handover could run a few weeks past the registered date.
Registered completion date (DLD)
25 Dec 2026
DLD project register via Continental Club
Latest construction progress
76.05%
DLD inspection, 2 Jun 2026
Developer's stated date
Q4 2026
Emaar, via Property Finder, accessed 11 Oct 2026
Trend estimate from recent pace
26 Jan 2027
Continental Club; not a developer date
St. Regis Residences Downtown Dubai handover date: the latest position
The DLD project register holds a registered completion date of 25 December 2026 for St. Regis The Residences, and Emaar’s handover date is Q4 2026. Prices, sizes and the payment plan are on the St. Regis Residences Downtown Dubai page.
The latest DLD inspection, on 2 June 2026, recorded 76.05% complete. Progress averaged about 3 points a month over the previous year, and Continental Club’s projection from that pace reaches 100% around 26 January 2027. That projection is arithmetic, not a revised date from Emaar.
St. Regis Residences Downtown Dubai handover date by building
The register lists DLD project 1816 as 3 buildings with 1,108 units, under one progress figure and one date. Sales records name Tower 1 and Tower 2.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| St. Regis Tower 1 (67 storeys) | 76.05%, 2 Jun 2026 (whole project) | 25 Dec 2026 | Q4 2026 (Property Finder; Dubizzle) |
| St. Regis Tower 2 (43 storeys) | 76.05%, 2 Jun 2026 (whole project) | 25 Dec 2026 | Q4 2026 (Property Finder) |
Storey counts are from Propsearch. Dubizzle’s Tower 1 page showed an older figure of 66% complete.
How the St. Regis Residences Downtown Dubai handover date has changed
| Date | What happened | Source |
|---|---|---|
| Dec 2021 | First DLD inspection on record | DLD register |
| Early 2022 | Emaar launches Tower 2 | Metropolitan, 11 Mar 2022 |
| 11 Mar 2022 | Emaar launches Tower 1 | Metropolitan |
| Jan 2024 | Enabling works nearly complete | Propsearch |
| Feb 2025 | Tower 1 reaches level 18 slab | Propsearch |
| 10 Jun 2025 | DLD inspection records 40.22% | DLD register |
| 1 Oct 2025 | DLD inspection records 50.55% | DLD register |
| 3 Feb 2026 | DLD inspection records 65.58% | DLD register |
| 2 Jun 2026 | DLD inspection records 76.05% | DLD register |
The handover date has been given as Q4 2026 throughout. Property Finder’s project page still has one line saying Q4 2025, which conflicts with the rest of that page and with the register. The register also gives 28 February 2017 as the construction start, an early land date that predates the 2022 launch.
What the St. Regis Residences Downtown Dubai handover date means for payments
The plan is 10% at booking, 60% in eight instalments during construction and 30% on handover (Property Finder; Dubizzle). On a 1 bedroom at the DLD median of AED 2,350,000 the handover payment is about AED 705,000. On a 2 bedroom at AED 3,541,888 it is about AED 1,062,566 (Continental Club, register updated 8 October 2026). With the registered date in late December, that payment may fall in early 2027 if the trend estimate proves right.
What to check before relying on the St. Regis Residences Downtown Dubai date
- The completion date and grace period in the SPA, compared with 25 December 2026 in the register.
- The next DLD inspection. A figure near 90% would support a December finish.
- Emaar’s handover notice for the specific tower, since the 30% payment and any mortgage drawdown follow that notice.
Questions buyers also ask
When will St. Regis Residences Downtown Dubai be completed?
The DLD project register gives a registered completion date of 25 December 2026, and Emaar's date is Q4 2026. Continental Club's projection from recent progress is about 26 January 2027.
Is St. Regis Residences Downtown Dubai finished?
No. It was 76.05% complete at the DLD inspection on 2 June 2026, and no handover had been announced by 11 October 2026.
Has the St. Regis Residences handover date been delayed?
Emaar has not announced a delay, and the date has stayed at Q4 2026. Property Finder's project page carries one older Q4 2025 reference, but the rest of that page and the register show 25 December 2026.
Do Tower 1 and Tower 2 hand over at the same time?
The DLD register lists one project with 3 buildings and one completion date. Emaar has not published separate tower dates. Propsearch reported in February 2025 that Tower 1 was slightly ahead of Tower 2.