Handover date

When is The Orchard Place handover date?

Updated 11 October 2026 The Orchard Place

Short answer

Towers A and B at The Orchard Place had a registered completion date of 31 July 2026, which has passed, and Tower C is registered for 31 March 2027. The latest DLD inspections recorded Towers A and B at 42.68% on 11 March 2026 and Tower C at 13% on 7 May 2026. No revised date for Towers A and B had been published by 11 October 2026, and broker listings already show Q4 2027 for Tower C.

Towers A and B, registered completion (DLD)

31 Jul 2026 (passed)

DLD project register via Continental Club

Towers A and B, latest progress

42.68%

DLD inspection, 11 Mar 2026

Tower C, registered completion (DLD)

31 Mar 2027

13% built at the 7 May 2026 DLD inspection

Tower C, broker date

Q4 2027

Dubainary; Lucretia gives 1 Dec 2027

The Orchard Place handover date: the latest position

The Orchard Place has two registered completion dates. Towers A and B were registered for 31 July 2026, and that date has passed with the towers unfinished. Tower C is registered for 31 March 2027. Prices, sizes and payment plans are on The Orchard Place page.

The last DLD inspection of Towers A and B, on 11 March 2026, recorded 42.68% complete. Dubai Handover’s daily copy of the register still showed 31 July 2026 on 9 October 2026, so no new date has been filed. A passed registered date does not mean the towers were handed over. It means the record has not yet been changed.

The Orchard Place handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Towers A and B (DLD project 2629, 418 units) 42.68%, 11 Mar 2026 31 Jul 2026 (passed) Q3 2026 (Property Finder; Continental Club)
Tower C (196 units) 13%, 7 May 2026 31 Mar 2027 Q4 2027 (Dubainary); 1 Dec 2027 (Lucretia)

Towers A and B share one registration, so their DLD progress figure covers both. Peak Summit’s own update reported the structure 96% complete in each tower by September 2025, with MEP works 90% done to the 25th floor in Tower B. Tower C is a separate registration with its own escrow and date. Data Habibi gives Tower C 191 units and Khaleej Times 193; the register lists 196.

How The Orchard Place handover date has changed

Date What happened Source
31 Jul 2023 Towers A and B sales open; construction start registered; completion registered for 31 Jul 2026 Property Finder; DLD register
9 Jun 2024 Tower C launched with a Q4 2026 handover target, from AED 687,000 Khaleej Times
Jun 2024 Tower C construction starts Data Habibi
12 Nov 2025 Developer reports structure 96% complete in Towers A and B Peak Summit
11 Mar 2026 DLD inspection records Towers A and B at 42.68% DLD register
7 May 2026 DLD inspection records Tower C at 13%; registered date 31 Mar 2027 DLD register
31 Jul 2026 Registered date for Towers A and B passes DLD register
Oct 2026 Tower C marketed for Q4 2027 Dubainary; Lucretia

Tower C’s date has moved from Q4 2026 at launch to 31 March 2027 in the register and Q4 2027 in current listings, a slip of about a year. Towers A and B have not yet been given a public replacement for July 2026.

What The Orchard Place handover date means for payments

On Towers A and B, 40% of the price is due on handover under the 60/40 plan, so that payment has not yet fallen due. On a 1 bedroom sold at AED 1,247,634 in May 2026, 40% is about AED 499,000. Tower C’s main plan puts 10% on handover and 30% over 30 months after it (Data Habibi), so a later handover also delays the end of the post-handover instalments.

What to check before relying on The Orchard Place date

  1. Whether the unit is in Towers A and B or Tower C, since the registered dates are eight months apart.
  2. The SPA’s completion date and grace period for Towers A and B, now that 31 July 2026 has passed, and any written revised date from Peak Summit.
  3. The next DLD inspection of Towers A and B, the first since March 2026.
  4. Tower C’s SPA date against the March 2027 register date and the Q4 2027 broker date.

Questions buyers also ask

Is The Orchard Place finished?

No. Towers A and B were 42.68% complete at the DLD inspection of 11 March 2026, and Tower C was 13% complete on 7 May 2026.

Has The Orchard Place handover date been delayed?

Towers A and B passed their registered completion date of 31 July 2026 without being finished, and no new date had been registered by 11 October 2026. Tower C launched with a Q4 2026 target (Khaleej Times, June 2024), is registered for 31 March 2027 and is now marketed for Q4 2027.

When will The Orchard Place Tower C be completed?

The DLD register gives 31 March 2027. Broker listings give Q4 2027, and Lucretia gives 1 December 2027. Tower C was 13% built on 7 May 2026.

What is The Orchard Place completion date for Tower A and Tower B?

Both towers sit under one DLD registration with a completion date of 31 July 2026, now passed. Peak Summit reported the structure 96% complete in both towers in its September 2025 update.

Sources

  1. Dubai Handover, The Orchard Place (opens in a new tab)dubaihandover.com · snapshot 9 Oct 2026
  2. Lucretia International, The Orchard Place Tower C (opens in a new tab)lucretia-international.com · accessed 11 Oct 2026