When is The Orchard Place handover date?
Short answer
Towers A and B at The Orchard Place had a registered completion date of 31 July 2026, which has passed, and Tower C is registered for 31 March 2027. The latest DLD inspections recorded Towers A and B at 42.68% on 11 March 2026 and Tower C at 13% on 7 May 2026. No revised date for Towers A and B had been published by 11 October 2026, and broker listings already show Q4 2027 for Tower C.
Towers A and B, registered completion (DLD)
31 Jul 2026 (passed)
DLD project register via Continental Club
Towers A and B, latest progress
42.68%
DLD inspection, 11 Mar 2026
Tower C, registered completion (DLD)
31 Mar 2027
13% built at the 7 May 2026 DLD inspection
Tower C, broker date
Q4 2027
Dubainary; Lucretia gives 1 Dec 2027
The Orchard Place handover date: the latest position
The Orchard Place has two registered completion dates. Towers A and B were registered for 31 July 2026, and that date has passed with the towers unfinished. Tower C is registered for 31 March 2027. Prices, sizes and payment plans are on The Orchard Place page.
The last DLD inspection of Towers A and B, on 11 March 2026, recorded 42.68% complete. Dubai Handover’s daily copy of the register still showed 31 July 2026 on 9 October 2026, so no new date has been filed. A passed registered date does not mean the towers were handed over. It means the record has not yet been changed.
The Orchard Place handover date by building
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Towers A and B (DLD project 2629, 418 units) | 42.68%, 11 Mar 2026 | 31 Jul 2026 (passed) | Q3 2026 (Property Finder; Continental Club) |
| Tower C (196 units) | 13%, 7 May 2026 | 31 Mar 2027 | Q4 2027 (Dubainary); 1 Dec 2027 (Lucretia) |
Towers A and B share one registration, so their DLD progress figure covers both. Peak Summit’s own update reported the structure 96% complete in each tower by September 2025, with MEP works 90% done to the 25th floor in Tower B. Tower C is a separate registration with its own escrow and date. Data Habibi gives Tower C 191 units and Khaleej Times 193; the register lists 196.
How The Orchard Place handover date has changed
| Date | What happened | Source |
|---|---|---|
| 31 Jul 2023 | Towers A and B sales open; construction start registered; completion registered for 31 Jul 2026 | Property Finder; DLD register |
| 9 Jun 2024 | Tower C launched with a Q4 2026 handover target, from AED 687,000 | Khaleej Times |
| Jun 2024 | Tower C construction starts | Data Habibi |
| 12 Nov 2025 | Developer reports structure 96% complete in Towers A and B | Peak Summit |
| 11 Mar 2026 | DLD inspection records Towers A and B at 42.68% | DLD register |
| 7 May 2026 | DLD inspection records Tower C at 13%; registered date 31 Mar 2027 | DLD register |
| 31 Jul 2026 | Registered date for Towers A and B passes | DLD register |
| Oct 2026 | Tower C marketed for Q4 2027 | Dubainary; Lucretia |
Tower C’s date has moved from Q4 2026 at launch to 31 March 2027 in the register and Q4 2027 in current listings, a slip of about a year. Towers A and B have not yet been given a public replacement for July 2026.
What The Orchard Place handover date means for payments
On Towers A and B, 40% of the price is due on handover under the 60/40 plan, so that payment has not yet fallen due. On a 1 bedroom sold at AED 1,247,634 in May 2026, 40% is about AED 499,000. Tower C’s main plan puts 10% on handover and 30% over 30 months after it (Data Habibi), so a later handover also delays the end of the post-handover instalments.
What to check before relying on The Orchard Place date
- Whether the unit is in Towers A and B or Tower C, since the registered dates are eight months apart.
- The SPA’s completion date and grace period for Towers A and B, now that 31 July 2026 has passed, and any written revised date from Peak Summit.
- The next DLD inspection of Towers A and B, the first since March 2026.
- Tower C’s SPA date against the March 2027 register date and the Q4 2027 broker date.
Questions buyers also ask
Is The Orchard Place finished?
No. Towers A and B were 42.68% complete at the DLD inspection of 11 March 2026, and Tower C was 13% complete on 7 May 2026.
Has The Orchard Place handover date been delayed?
Towers A and B passed their registered completion date of 31 July 2026 without being finished, and no new date had been registered by 11 October 2026. Tower C launched with a Q4 2026 target (Khaleej Times, June 2024), is registered for 31 March 2027 and is now marketed for Q4 2027.
When will The Orchard Place Tower C be completed?
The DLD register gives 31 March 2027. Broker listings give Q4 2027, and Lucretia gives 1 December 2027. Tower C was 13% built on 7 May 2026.
What is The Orchard Place completion date for Tower A and Tower B?
Both towers sit under one DLD registration with a completion date of 31 July 2026, now passed. Peak Summit reported the structure 96% complete in both towers in its September 2025 update.