When is The Autograph I Series handover date?
Short answer
The Autograph I Series in JVC has a registered completion date of 31 August 2028 in the Dubai Land Department project register, and Green Group gives Q3 2028. The last published DLD inspection, on 23 April 2026, recorded 3.97% complete. Listings at launch in 2025 quoted Q4 2027 or Q2 2028, so the date has already moved back.
Registered completion date (DLD)
31 Aug 2028
DLD project register via Continental Club, registry updated 4 Oct 2026
Latest construction progress
3.97%
DLD inspection, 23 Apr 2026
Developer's stated date
Q3 2028
Developer supplied, via Continental Club; Bayut listings
Earliest date quoted
Q4 2027
in.ae; Prelaunch.ae, 20 Feb 2026
The Autograph I Series handover date: the latest position
The Autograph I Series has a registered completion date of 31 August 2028 in the Dubai Land Department (DLD) project register, and Green Group’s developer-supplied date is Q3 2028. The last published DLD inspection, on 23 April 2026, recorded 3.97% complete. Full project details are on The Autograph I Series page.
The register date sits later than every date quoted when the tower was first marketed in 2025. With no inspection published between April and early October 2026, the April figure is the latest public measure of progress.
The Autograph I Series handover date by building
The Autograph I Series is one tower of 272 units, registered as G+5P+39+R.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| The Autograph I Series (272 units) | 3.97% (23 Apr 2026) | 31 Aug 2028 | Q3 2028 (developer; Bayut) |
Figures from the DLD register via Continental Club, registry updated 4 October 2026. The unit mix is 98 studios, 162 one bedrooms, 10 two bedrooms and 2 other units.
How The Autograph I Series handover date has changed
| Date | What was stated | Source |
|---|---|---|
| 27 Jan 2025 | Listed as “announcing soon”, no date | Optimus Properties |
| 10 Mar 2025 | First DLD inspection at 0% | DLD register via Continental Club |
| 31 Mar 2025 | Registered construction start; completion date 31 August 2028 | DLD register via Continental Club |
| 2025 | Broker listings quote Q4 2027 or Q2 2028 | in.ae; Grand Reve Realty |
| 20 Feb 2026 | Q4 2027 still quoted | Prelaunch.ae |
| 23 Apr 2026 | DLD inspection at 3.97% | DLD register via Continental Club |
| Oct 2026 | Q3 2028 shown on listings | Bayut; Continental Club |
The DLD date has stayed at 31 August 2028. The change is in the dates used to sell the tower, which moved from late 2027 to the third quarter of 2028.
What The Autograph I Series handover date means for payments
The main plan is 10% on booking, 40% during construction and 50% on handover (Grand Reve Realty; Continental Club). Two of the construction instalments, 5% and 10%, are tied to the tower reaching 35% and 45% completion, so slow progress also delays them. Half the price falls due at completion: on a studio at the AED 807,850 median registered price, that is about AED 403,925.
What to check before relying on The Autograph I Series date
- The date written in the SPA. Contracts from 2025 may carry Q4 2027 or Q2 2028, which no longer match the register.
- The next DLD inspection. Reaching 100% by 31 August 2028 needs about 10 points a quarter from the April 2026 level.
- The grace period in the SPA, which sets how far past the contract date completion can run.
Questions buyers also ask
What is The Autograph I Series completion date?
31 August 2028, the completion date for DLD project 3187, The Autograph-I Series (via Continental Club).
Has The Autograph I Series handover date been delayed?
Against early marketing, yes. in.ae and Prelaunch.ae quoted Q4 2027, and several brokers quoted Q2 2028. Green Group and Bayut now give Q3 2028, and the register gives 31 August 2028.
Is The Autograph I Series finished?
No. It was 3.97% complete at the DLD inspection of 23 April 2026, the latest published as of 4 October 2026.
When did construction of The Autograph I Series start?
The DLD register records a construction start on 31 March 2025.