
When is the Taraf 3 Residence handover date?
Short answer
Taraf 3 Residence has a registered completion date of 31 March 2028 at the Dubai Land Department (DLD), and Property Finder lists Q1 2028. The DLD inspection on 5 May 2026 recorded 5.88% complete, up from no recorded progress on 9 November 2025. Some brokers quote Q3 2028, so the date in the SPA is the one that applies.
Registered completion date (DLD)
31 Mar 2028
DLD project 4192, via Continental Club
Latest construction progress
5.88%
DLD inspection, 5 May 2026
Portal date
Q1 2028
Property Finder, accessed 11 Oct 2026
Other broker date
Q3 2028
Driven Properties; Grand Reve Realty
Taraf 3 Residence handover date: the latest position
Taraf 3 Residence, a 151 unit apartment building in Jumeirah Village Circle (JVC) District 10, has a registered completion date of 31 March 2028 at the Dubai Land Department (DLD). Property Finder lists the same date and a Q1 2028 handover. Full project details are on the Taraf 3 Residence page.
The DLD inspection on 5 May 2026 recorded 5.88% complete (DLD project register via Continental Club, inspection 5 May 2026). An earlier inspection on 9 November 2025 had recorded no progress. Some brokers quote Q3 2028, later than the register.
Taraf 3 Residence handover date by building
Taraf 3 Residence is a single building, filed with DLD as one project.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Taraf 3 Residence (DLD project 4192, 151 units) | 5.88%, 5 May 2026 | 31 Mar 2028 | Q1 2028 (Property Finder); Q3 2028 (Driven Properties, Grand Reve) |
How the Taraf 3 Residence handover date has changed
| Date | Event | Source |
|---|---|---|
| 18 Nov 2019 | Land purchase registered against the project | Continental Club (DLD) |
| 1 Nov 2025 | Booking opens from AED 760,400; construction start on the DLD register; completion date 31 Mar 2028 | Property Finder; Mitchells (DLD) |
| 9 Nov 2025 | DLD inspection: no progress recorded | Continental Club |
| 20 Nov 2025 | Launch date recorded by fäm Properties, handover 31 Mar 2028 | fäm Properties |
| 5 May 2026 | DLD inspection: 5.88% | DLD via Continental Club |
| Oct 2026 | Register unchanged at 31 Mar 2028; brokers quote Q1 or Q3 2028 | Mitchells; Property Finder; Driven Properties |
The registered date has not changed since construction started. The register allows about 29 months from start to completion for a building of a basement, ground floor, four podium parking levels and 13 residential floors (CVTEC). The May 2026 reading came six months in, leaving about 94% of the work for the remaining 23 months.
What the Taraf 3 Residence handover date means for payments
Brokers list a 40/60 plan, with 60% of the price due on handover (Driven Properties; Grand Reve Realty). The dates of the 40% paid before handover are not published. Because most of the price is tied to completion, a later handover also delays the largest payment. On a launch-price studio of AED 760,400, the 60% handover payment is about AED 456,000; on a 2 bedroom registered at AED 1.82 million in December 2025, it is about AED 1.09 million. Payments go into the project escrow account at First Abu Dhabi Bank (Mitchells).
What to check before relying on the Taraf 3 Residence date
- Which date the SPA states. The register holds 31 March 2028; Q3 2028 on some broker pages would be six months later.
- The grace period. With 5.88% recorded in May 2026, any delay would run into the SPA’s grace period.
- The latest DLD inspection. No reading after 5 May 2026 appeared in the register extract of 4 October 2026.
Questions buyers also ask
Is Taraf 3 Residence finished?
No. The DLD inspection on 5 May 2026 recorded 5.88% complete, and the register still listed it as under construction on 4 October 2026 (Mitchells).
What is the Taraf 3 Residence completion date?
31 March 2028, the completion date on file at DLD for project 4192. Property Finder gives the same date as its expected completion.
Has the Taraf 3 Residence handover date been delayed?
Not on the register. The 31 March 2028 date has been on file since construction started on 1 November 2025. Broker pages quoting Q3 2028 differ from the register rather than reflecting a change.
How long is left until Taraf 3 Residence is completed?
From the May 2026 inspection, about 23 months remained to the registered date, with about 94% of the work still to do on DLD's figure.

