When is the Sukoon by Nuri handover date?
Short answer
Sukoon by Nuri has a registered completion date of 31 December 2026, and the developer gives a Q4 2026 handover. The DLD inspection on 30 June 2026 recorded 46.77% complete. At the pace recorded between February and June 2026, the remaining work would run into mid 2027, though no revised date has been published.
Registered completion date (DLD)
31 Dec 2026
DLD project register via Continental Club
Latest construction progress
46.77%
DLD inspection, 30 Jun 2026
Developer's stated date
Q4 2026
Developer supplied, via Continental Club; Property Finder
Progress, February to June 2026
+17.92 points
DLD inspections, 20 Feb and 30 Jun 2026
Sukoon by Nuri handover date: the latest position
Sukoon by Nuri has a registered completion date of 31 December 2026 in the DLD project register, and the developer gives a Q4 2026 handover. Prices, sizes and the payment plan are on the Sukoon by Nuri page.
The DLD inspection on 30 June 2026 recorded the building 46.77% complete. That left about 53 points of work for six months. No inspection after June had been published by the register update of 4 October 2026.
Sukoon by Nuri handover date by building
Sukoon is a single building with 41 units, registered as DLD project number 3753 in Nad Al Sheba 1. The escrow account is at Al Ahli Bank of Kuwait, Dubai Branch.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sukoon By Nuri | 46.77%, 30 Jun 2026 | 31 Dec 2026 | Q4 2026 (developer, via Continental Club); December 2026 (Property Finder, fäm Properties) |
How the Sukoon by Nuri handover date has changed
| Date | What happened | Source |
|---|---|---|
| 2025 | Sales begin; first DLD sales registered | Continental Club |
| 1 May 2025 | Construction start recorded | DLD register |
| Nov 2025 | Second 10% instalment falls due | The Dubai Lands |
| 20 Feb 2026 | Inspection records about 28.9% | DLD register (derived from the 30 Jun change) |
| Mar 2026 | Third 10% instalment falls due | The Dubai Lands |
| 30 Jun 2026 | Inspection records 46.77% | DLD register |
| 11 Oct 2026 | Portals still show December 2026 or Q4 2026 | Property Finder; fäm Properties |
The date has stayed at the end of 2026 throughout. Progress has been steady at about 4.2 points a month in 2026. At that rate, the remaining work would take about 13 months from the June inspection, to around July 2027. That is a calculation from the register figures, not a date from the developer.
What the Sukoon by Nuri handover date means for payments
The plan puts 30% before handover, in three dated payments of 10% on booking, in November 2025 and in March 2026, and 70% on handover (The Dubai Lands). All the pre-handover payments have fallen due, so the balance is now tied entirely to completion. On a 1 bedroom at the AED 1.5 million starting price, AED 1.05 million is due at handover. A later handover moves this payment back; nothing is due after it.
What to check before relying on the Sukoon by Nuri date
- The SPA completion date and grace period, set against the mid 2027 point implied by the current pace.
- How the developer will give notice of completion, since the 70% balance is due on it.
- Mortgage timing, where the 70% balance is to be financed, so that approval lines up with the completion notice.
Questions buyers also ask
When will Sukoon by Nuri be completed?
The DLD register holds a registered completion date of 31 December 2026, and the developer gives Q4 2026. The building was 46.77% complete on 30 June 2026.
Is Sukoon by Nuri on schedule?
The date has not been changed, but progress is behind it. The building gained 17.92 points between 20 February and 30 June 2026, about 4.2 points a month, and about 53 points remained (DLD project register via Continental Club).
Has the Sukoon by Nuri handover date been delayed?
No revised date has been published. Property Finder, fäm Properties and the DLD register all show December 2026 or Q4 2026 (accessed 11 Oct 2026).
How much is due on handover at Sukoon by Nuri?
70% of the price, under the 30/70 plan of 10% on booking, 10% in November 2025, 10% in March 2026 and 70% on handover (The Dubai Lands).