When is the Saray Prime Residence handover date?
Short answer
Saray Prime Residence has a registered completion date of 31 October 2027, and Unique Saray markets a Q4 2027 handover. The latest DLD inspection, on 21 September 2026, recorded the building 2.22% complete, up from 1.7% in June. With nearly all the work still to do 13 months before the registered date, a later handover is possible, and the date in each buyer's SPA is the one that counts.
Registered completion date (DLD)
31 Oct 2027
DLD register via Continental Club
Latest construction progress
2.22%
DLD inspection, 21 Sep 2026
Developer's stated date
Q4 2027
Unique Saray launch listings, Nov 2025
Portal date
Dec 2027
Property Finder, accessed 11 Oct 2026
Saray Prime Residence handover date: the latest position
Saray Prime Residence is registered with the Dubai Land Department (DLD) for completion on 31 October 2027. Unique Saray has marketed a Q4 2027 handover since the launch in November 2025, and Property Finder lists December 2027. Full project details are on the Saray Prime Residence page.
The building was 2.22% complete at the DLD inspection on 21 September 2026. Progress since the first inspection in November 2025 has averaged about 0.2 percentage points a month. The registered date is unchanged, but the site has a long way to go.
Saray Prime Residence handover date by building
Saray Prime Residence is a single building of 121 units in Wadi Al Safa 5, Dubailand Residence Complex, registered as DLD project 4058. The escrow account is held at Emirates NBD, and the plot covers 6,823 square metres (Dubai Data).
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Saray Prime Residence (2B+G+11+R) | 2.22% (21 Sep 2026) | 31 Oct 2027 | Q4 2027 (Unique Saray); Dec 2027 (Property Finder, Data Habibi) |
How the Saray Prime Residence handover date has changed
| Date | What happened | Source |
|---|---|---|
| 5 Nov 2025 | First DLD inspection, 0% | DLD register via Dubai Data |
| 15 Nov 2025 | Registered construction start; launch listings give Q4 2027 | DLD register; Kotook |
| 21 Nov 2025 | Registered with the DLD, completion date 31 Oct 2027 | DLD register via Dubai Data |
| 11 Jun 2026 | DLD inspection, 1.7% | DLD register via Dubai Data |
| 21 Sep 2026 | DLD inspection, 2.22% | DLD register via Continental Club |
| 11 Oct 2026 | Property Finder lists December 2027 | Property Finder |
The dates have stayed in the same window since launch: Q4 2027 in marketing, 31 October 2027 in the register and December 2027 on two portals. No revision has been announced.
What the Saray Prime Residence handover date means for payments
Every published version of the plan leaves 40% of the price due on handover. Binayah and Proprain describe the first 60% as paid through 1% monthly instalments; Data Habibi lists 10% down and 50% during construction. If the plan is tied to monthly dates rather than construction stages, buyers could pay most of the 60% before the building is much further along. The 40% balance moves with the handover date.
What to check before relying on the Saray Prime Residence date
- Whether instalments are time based or milestone based. With progress at 2.22%, a monthly plan runs ahead of the site.
- The anticipated completion date and grace period in the SPA, since Q4 2027, 31 October 2027 and December 2027 are all in circulation.
- The next DLD inspection, which will show whether the pace has picked up from about 0.2 percentage points a month.
Questions buyers also ask
When will Saray Prime Residence be completed?
The DLD register gives 31 October 2027. Unique Saray markets Q4 2027, and Property Finder and Data Habibi list December 2027.
Has construction started at Saray Prime Residence?
Yes, but it is at an early stage. The register records a construction start on 15 November 2025, and inspections recorded 1.7% on 11 June 2026 and 2.22% on 21 September 2026 (Dubai Data).
Has the Saray Prime Residence handover date been delayed?
No change has been announced. Q4 2027 has been the date since launch in November 2025, and 31 October 2027 is the registered date. The progress so far makes a later handover possible.
Is Saray Prime Residence on track for 2027?
Hard to say yet. Progress has averaged about 0.2 percentage points a month since November 2025. The building, two basements plus 12 floors and a roof, would need much faster work to finish by October 2027.