Handover date

When is the Samana Business Hub handover date?

Updated 11 October 2026 Samana Business Hub

Short answer

Samana Business Hub is due for handover in Q3 2029, and the DLD register holds a registered completion date of 30 September 2029. The DLD inspection on 28 September 2026 recorded 0.8% complete. Some broker listings still show Q2 2029, but Samana's own payment schedule ties the handover payment to Q3 2029.

Registered completion date (DLD)

30 Sep 2029

DLD project register via Mitchells, as at 4 Oct 2026

Latest construction progress

0.8%

DLD inspection, 28 Sep 2026

Developer's stated date

Q3 2029

Samana Business Hub sales site, accessed 11 Oct 2026

Earlier portal date

Q2 2029

Binayah and EZRE, accessed 11 Oct 2026

Samana Business Hub handover date: the latest position

Samana Business Hub is due for handover in Q3 2029, and the DLD register holds a registered completion date of 30 September 2029. Prices, office sizes and the payment plan are on the Samana Business Hub page.

The DLD inspection on 28 September 2026 recorded 0.8% complete, about seven months after the registered start of 1 March 2026. The project is at the start of a schedule of about three and a half years.

Samana Business Hub handover date by building

The tower is registered as one DLD project, number 4394, with 323 units in the registered area of Jabal Ali Industrial Second.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Samana Business Hub (307 offices, 16 shops) 0.8%, 28 Sep 2026 30 Sep 2029 Q3 2029 (Samana sales site; Inside Realty); Q2 2029 (Binayah, EZRE)

The office and retail split is from Binayah. The DLD register had recorded 115 sales by 2 October 2026, many of them offices registered in the last week of September 2026 (Mitchells). Most buyers were therefore only a few months into the 30 monthly construction payments when the first inspection was published.

How the Samana Business Hub handover date has changed

Date What happened Source
1 Mar 2026 Construction start recorded DLD register via Mitchells
Jun 2026 Launch, expected handover Q3 2029 Cresco Real Estate, 22 Jul 2026
29 Jul 2026 First booking date in Samana’s payment schedule Samana Business Hub sales site
28 Sep 2026 Inspection records 0.8% DLD register via Mitchells
4 Oct 2026 Registered completion date 30 Sep 2029 DLD register via Mitchells

There has been no change to the developer’s date. The Q2 2029 date on some broker pages appears to be an early estimate; the registered date and Samana’s payment schedule both use Q3 2029.

What the Samana Business Hub handover date means for payments

Under the 60/40 plan, buyers pay 20% on booking and 30% in 30 monthly payments from 29 August 2026, which ends before handover. A further 10% falls due on handover, and the last 40% is paid in 40 monthly payments starting 30 July 2029 (Samana Business Hub sales site). On an Optima office at AED 1.46 million, that is AED 146,000 on handover and about AED 14,600 a month afterwards. If handover slips past Q3 2029, the SPA terms decide whether the post-handover instalments still start on their stated date.

What to check before relying on the Samana Business Hub date

  1. Whether the post-handover instalments are dated or tied to handover, since the sales site gives a fixed start of 30 July 2029.
  2. The completion date and grace period in the SPA, compared with the registered 30 September 2029.
  3. The time needed for fit-out after handover, as offices come in shell and core condition and cannot be occupied or let straight away.

Questions buyers also ask

When will Samana Business Hub be completed?

The registered completion date in the DLD project register is 30 September 2029. Samana gives Q3 2029 for handover.

How far along is construction at Samana Business Hub?

0.8% complete at the DLD inspection on 28 September 2026. The DLD register records the construction start as 1 March 2026 (Mitchells, register as at 4 Oct 2026).

Has the Samana Business Hub handover date been delayed?

No delay has been announced. Some listings from the June 2026 launch period show Q2 2029, while Samana's sales site, the Inside Realty brochure and the DLD register all point to Q3 2029, ending 30 September 2029.

Do the offices and shops hand over at the same time?

Yes, as far as the register shows. The DLD lists the 323 units as one project, number 4394, with one completion date.

Sources

  1. Samana Business Hub sales site, payment plan (opens in a new tab)samana-businesshub.com · accessed 11 Oct 2026
  2. Inside Realty, Samana Business Hub brochure (opens in a new tab)cdn.insiderealty.ae · accessed 11 Oct 2026
  3. Binayah, Samana Business Hub (opens in a new tab)binayah.ae · accessed 11 Oct 2026
Request a Unit Review