Handover date

When is the Samana Boulevard Heights handover date?

Updated 1 October 2026 Samana Boulevard Heights

Short answer

The Samana Boulevard Heights handover date is 31 December 2028, the registered completion date on the Dubai Land Department (DLD) register for project 3205, and Property Finder gives the same Q4 2028. The DLD site inspection of 1 June 2026 put construction at 2.50% complete, up from 0.76% on 17 January 2026. Propsearch's August 2027 and some agents' Q3 2027 are earlier dates the register does not support, and Samana's own project page gives no date.

Registered completion date (DLD)

31 Dec 2028

DLD register, project 3205, via Mitchells, accessed 1 Oct 2026

Latest construction progress

2.50%

DLD site inspection, 1 Jun 2026

Developer's stated date

Not published

Samana Developers project page, accessed 28 Sep 2026

Portal estimate

Aug 2027

Propsearch, accessed 28 Sep 2026; not supported by the DLD register

Samana Boulevard Heights handover date: the latest position

Samana Boulevard Heights is registered for completion on 31 December 2028. That is the date the Dubai Land Department holds for project number 3205, and Property Finder shows the same date. Samana Developers’ own project page does not state a handover date. More on prices and the payment plan is on the Samana Boulevard Heights page.

The DLD site inspection of 1 June 2026 recorded the tower 2.50% complete, 11 months after the registered construction start of 1 July 2025. The inspection before it, on 17 January 2026, recorded 0.76%. Sales have moved much faster than construction: 485 sales were registered against the project’s 541 homes between 28 April 2025 and 28 September 2026 (DLD data, via Mitchells).

Samana Boulevard Heights handover date by building

Samana Boulevard Heights is a single tower, so one registered date applies to every unit. The DLD register describes it as basement, ground, 3 podium levels and 17 floors, with 541 homes.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Samana Boulevard Heights (B + G + 3P + 17, 541 homes) 2.50%, 1 Jun 2026 31 Dec 2028 Q4 2028 (Property Finder); Aug 2027 (Propsearch); none (Samana)

The Propsearch date is the outlier. Propsearch traces the project to around July 2024 and estimates August 2027, but the register shows construction starting on 1 July 2025.

How the Samana Boulevard Heights handover date has changed

The registered date has not changed. The earlier 2027 dates come from marketing and portal estimates, not from the register.

Date What happened Source
Around Jul 2024 Propsearch’s first trace of the project, with an estimated handover of August 2027. Propsearch
Undated Agent listing shows completion in Q3 2027. Excel Properties
1 Jul 2025 Booking opened and the DLD registered construction start. Completion date 31 December 2028. Property Finder; DLD register
17 Jan 2026 0.76% complete at the DLD site inspection. DLD register, via Al Ranim Properties
1 Jun 2026 2.50% complete at the DLD site inspection. DLD register, via Mitchells
Sep 2026 Registered completion date still 31 December 2028. No newer inspection on file. DLD register, via Mitchells

What the Samana Boulevard Heights handover date means for payments

Samana’s published plans do not put a lump sum on handover. Both options take 10% at booking and 10% at month 12. The PDC plan then takes 5% at month 1 and 1% a month for 75 months; the non-PDC plan takes 10% at month 1 and 1% a month for 70 months.

That means the payment schedule runs to a calendar, not to completion. For a buyer who booked when sales opened in July 2025, monthly payments continue until about 2031, roughly three years after the registered completion date. On a studio listed from AED 786,000, each 1% instalment is AED 7,860. If completion moves, the instalments continue on the same calendar, so the share paid before handover changes, not the monthly amount.

What to check before relying on the Samana Boulevard Heights date

  1. Which date your SPA states. Some sales material still shows Q3 2027 or August 2027, while the register holds 31 December 2028.
  2. How many monthly instalments remain after 31 December 2028 under your plan, PDC or non-PDC, since the plan runs past completion.
  3. The DLD progress for project 3205, through DLD’s project status enquiry service. The register showed inspections on 17 January and 1 June 2026, and none newer by late September 2026.

Questions buyers also ask

What is the Samana Boulevard Heights completion date?

31 December 2028, the registered completion date for DLD project number 3205 (DLD register, via Mitchells, accessed 1 Oct 2026). Property Finder lists the same expected completion. Samana Developers' own project page does not state a date.

Is Samana Boulevard Heights finished?

No. Construction started on 1 July 2025 on the DLD register, and the site inspection of 1 June 2026 put it at 2.50% complete. No newer inspection was on the register by 27 September 2026.

Has the Samana Boulevard Heights handover date been delayed?

No revision has been announced. Earlier dates do circulate: Propsearch shows August 2027 and one agent, Excel Properties, shows Q3 2027. The DLD register, with a construction start of 1 July 2025, holds 31 December 2028, and Property Finder has shown that date since booking opened on 1 July 2025.

When will Samana Boulevard Heights be ready?

The registered completion date is 31 December 2028. At 2.50% complete in June 2026, about 97.5% of the 541 unit tower remained to be built in 31 months.

Do payments continue after the Samana Boulevard Heights handover?

Yes, on Samana's published plans. Both options take 10% at booking and 10% at month 12, then 1% a month for 70 or 75 months, so a buyer who booked at launch in July 2025 is still paying monthly for roughly three years after the registered completion date (Samana Developers, accessed 28 Sep 2026).