Handover date

When is the Samana Barari Lagoons handover date?

Updated 11 October 2026 Samana Barari Lagoons

Short answer

Samana Barari Lagoons has a registered completion date of 31 March 2028, but Samana's own project page now gives Q3 2028. The last Dubai Land Department inspection, on 2 June 2026, recorded the tower 11.84% complete, up about two points since February. Samana's date has moved later since it gave April 2028 in February 2025.

Registered completion date

31 Mar 2028

DLD project register via Continental Club

Latest construction progress

11.84%

DLD inspection, 2 Jun 2026

Developer's stated date

Q3 2028

Samana project page, accessed 11 Oct 2026

Date given in 2025

Apr 2028

Samana via MEP Middle East, 3 Feb 2025

Samana Barari Lagoons handover date: the latest position

Samana Barari Lagoons is registered with the Dubai Land Department (DLD) for completion on 31 March 2028. At the last DLD inspection, on 2 June 2026, the tower was 11.84% complete. Prices, sizes and the payment plan are on the project page: Samana Barari Lagoons.

Samana’s own project page now states an anticipated handover of Q3 2028, up to six months after the registered date. Between February and June 2026 the tower gained 1.97 points, about half a point a month. Reaching 100% by 31 March 2028 would need about four points a month.

Samana Barari Lagoons handover date by building

The project is one tower in Majan (DLD project 3422), filed by Samana Signature Real Estate Developments.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Samana Barari Lagoons (601 units) 11.84% (2 Jun 2026) 31 Mar 2028 Q3 2028 (Samana); Q1 2028 (OffplanCompare and other brokers)

Samana Barari Heights, a separate tower in the same area, is registered for 31 October 2028. Its dates are on the Samana Barari Heights handover date page.

How the Samana Barari Lagoons handover date has changed

Date Event Source
2024 First DLD-registered sales DLD via Continental Club
3 Feb 2025 Samana gives April 2028 handover for 526 apartments MEP Middle East
1 Apr 2025 Construction starts; completion registered for 31 Mar 2028 DLD via Continental Club
3 Feb 2026 DLD inspection: about 9.87% (implied by the later gain) DLD via Continental Club
2 Jun 2026 DLD inspection: 11.84% DLD via Continental Club
1 Oct 2026 Latest registered sale, a 2 bedroom at AED 1,881,411 DLD via Continental Club
Oct 2026 Samana’s page gives Q3 2028 Samana

The registered date sits three years after the start of construction. The tower reached about 10% in its first ten months, then slowed to about half a point a month in early 2026. Samana’s own date has moved from April 2028 to Q3 2028, while the register has not been changed.

What the Samana Barari Lagoons handover date means for payments

Samana’s plan without post-dated cheques takes 20% on booking, 1% a month for 42 months, 10% in month 12 and 5% in month 18, then 0.5% a month for 46 months. Property Finder summarises it as 20% on booking, 56% during construction, 1% on handover and 23% after handover. Because the 1% instalments are counted in months from booking, a buyer who booked in early 2025 would finish them around mid 2028, whether or not the tower is ready by then. The 0.5% monthly tail, 23% of the price, then runs for almost four years.

What to check before relying on the Samana Barari Lagoons date

  1. The completion date in the SPA, since the register says 31 March 2028 and Samana now says Q3 2028.
  2. When the 0.5% monthly instalments start. The SPA should say whether they begin at handover or at a fixed month after booking.
  3. The next DLD inspection. The last published reading is from 2 June 2026.
  4. The unit’s building and DLD project number (3422), to avoid confusion with Samana’s other Barari towers.

Questions buyers also ask

Is Samana Barari Lagoons finished?

No. The DLD inspection of 2 June 2026 recorded the tower 11.84% complete. Its registered completion date is 31 March 2028.

What is the Samana Barari Lagoons completion date?

31 March 2028 on the DLD register (via Continental Club). Samana's own page now gives Q3 2028, and brokers list Q1 2028.

Has the Samana Barari Lagoons handover date been delayed?

Samana's own date has moved. It gave April 2028 in February 2025 (MEP Middle East) and now states Q3 2028. The register still holds 31 March 2028.

Is Samana Barari Lagoons part of Samana Barari Views or Barari Heights?

No. It is a separate DLD project (3422), filed by Samana Signature Real Estate Developments, with its own completion date. Samana Barari Heights is registered for 31 October 2028.

Sources