Handover date

When is the Sakura Gardens handover date?

Updated 11 October 2026 Sakura Gardens

Short answer

The registered completion date for Sakura Gardens in the DLD project register is 30 June 2029, while HRE Development gives Q1 2029. The latest DLD inspection, on 21 September 2026, recorded the project 3.58% complete. Dates differ across sources, from Q4 2028 at groundbreaking to June 2029 in the register, so the date in each buyer's SPA is the one that applies.

Registered completion date (DLD)

30 Jun 2029

DLD register via Continental Club, updated 7 Oct 2026

Latest construction progress

3.58%

DLD inspection, 21 Sep 2026

Developer's stated date

Q1 2029

HRE Development; Q4 2028 at groundbreaking, May 2026

Portal estimate

Dec 2028

Property Finder, accessed 11 Oct 2026

Sakura Gardens handover date: the latest position

The Dubai Land Department (DLD) project register lists a registered completion date of 30 June 2029 for Sakura Gardens (DLD register via Continental Club, updated 7 October 2026). HRE Development’s own materials give Q1 2029, and Property Finder lists December 2028. Prices, sizes and the plan are on the project page: Sakura Gardens.

Construction is at an early stage. The last DLD inspection, on 21 September 2026, recorded 3.58% progress, up from 1.43% at the previous inspection on 11 June 2026. At groundbreaking in May 2026, HRE still targeted Q4 2028, so the developer’s own date has moved back by one quarter since then, while the registered date sits a further quarter later.

Sakura Gardens handover date by building

HRE describes four G+9 buildings, DAYA, CIRA, BINA and AYA, around a central park. The DLD register lists them under one project, number 4111, with 1,429 units and one completion date.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Sakura Gardens, all four buildings (DAYA, CIRA, BINA, AYA) 3.58% (21 Sep 2026) 30 Jun 2029 Q1 2029 (HRE); Dec 2028 (Property Finder)

How the Sakura Gardens handover date has changed

  • October 2025: the project is registered with the DLD.
  • November 2025: HRE launches Sakura Gardens at an event at Emirates Golf Club (Gulf News, 20 November 2025). Launch listings show handover in Q4 2028 (Dubai Sales Office).
  • 1 March 2026: construction start recorded in the DLD register.
  • 18 May 2026: groundbreaking, with completion targeted for Q4 2028 (Gulf News).
  • 11 June 2026: DLD inspection at about 1.4%.
  • 21 September 2026: DLD inspection at 3.58%. Registered completion date 30 June 2029.
  • October 2026: HRE’s materials and OffPlan Insider (6 October 2026) give Q1 2029.

What the Sakura Gardens handover date means for payments

Under HRE’s 20/35/10/35 plan, buyers pay 20% within 60 days of booking and 1% a month for 35 months during construction. A further 10% is due on handover, and the last 35% is paid at 1% a month for 35 months after handover (HRE Development). On the AED 874,000 median studio price, that is about AED 87,400 at handover and about AED 8,740 a month afterwards. Because the construction instalments run on a fixed 35 month schedule, a later completion date does not stop them; it only moves the handover payment and the start of the post-handover instalments.

What to check before relying on the Sakura Gardens date

  1. The completion date written into the SPA, since Q4 2028, Q1 2029 and 30 June 2029 all appear in sources.
  2. The building name (DAYA, CIRA, BINA or AYA) on the unit, in case HRE phases handover by building later.
  3. The construction instalment calendar, since the 35 monthly payments of 1% continue on schedule whichever completion date applies.
  4. The DLD inspection history, which showed progress of about 2 points over the three months to September 2026.

Questions buyers also ask

When will Sakura Gardens be ready?

The DLD register lists 30 June 2029 as the registered completion date. HRE gives Q1 2029. The project was 3.58% complete on 21 September 2026.

What is the Sakura Gardens completion date?

The registered completion date is 30 June 2029 (DLD register via Continental Club). At its groundbreaking on 18 May 2026, HRE said completion was targeted for the fourth quarter of 2028 (Gulf News).

Has the Sakura Gardens handover date been delayed?

HRE has not announced a delay. The dates in circulation have moved later over time, from Q4 2028 at launch and groundbreaking to Q1 2029 on HRE's current materials, with 30 June 2029 in the DLD register.

Do all four Sakura Gardens buildings have the same date?

The DLD register lists Sakura Gardens as one project with four buildings and a single completion date of 30 June 2029. HRE has not published separate dates for DAYA, CIRA, BINA and AYA.