When is the SAAS Hills handover date?
Short answer
SAAS Hills is due in Q4 2027 by the developer's date, recorded by Continental Club and broker listings, while the Dubai Land Department (DLD) register still gives a registered completion date of 31 March 2027. The DLD inspection on 19 May 2026 recorded the two towers 12.98% complete. Property Finder still shows March 2027, so the date a buyer sees depends on the source, and the SPA date is the one that applies.
Registered completion date (DLD)
31 Mar 2027
DLD project register via Mitchell's and Continental Club, as at 4 Oct 2026
Latest construction progress
12.98%
DLD inspection, 19 May 2026
Developer's stated date
Q4 2027
Continental Club (developer supplied); JRE, accessed 11 Oct 2026
Portal estimate
March 2027
Property Finder, accessed 11 Oct 2026
SAAS Hills handover date: the latest position
SAAS Hills is due in Q4 2027 by the developer’s date, while the Dubai Land Department (DLD) register still holds a registered completion date of 31 March 2027 for project 3225. Property Finder still shows March 2027. More on prices and sizes is on the SAAS Hills page.
The DLD inspection on 19 May 2026 recorded 12.98% complete. That is the latest official figure; the register had not logged a newer inspection by early October 2026. SAAS Properties posted a construction update in April 2026 without a percentage.
SAAS Hills handover date by building
SAAS Hills has two towers registered as one DLD project, so the register gives one date and one progress figure for both.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Tower A (B+G+2P+30) | 12.98% for the project, 19 May 2026 | 31 Mar 2027 | Q4 2027 (developer, via Continental Club) |
| Tower B (B+G+2P+32) | 12.98% for the project, 19 May 2026 | 31 Mar 2027 | Q4 2027 (developer, via Continental Club) |
The two towers hold 859 units between them. Floor counts are from offplans.com.
How the SAAS Hills handover date has changed
| Date | What happened | Source |
|---|---|---|
| 8 Aug 2024 | First DLD inspection records 0%. | DLD register via Dubai Data |
| 15 Sep 2024 | Booking opens and the registered construction start. Property Finder gives March 2027. | Property Finder; DLD register |
| 7 Nov 2024 | Project registered with the DLD, completion date 31 March 2027. | DLD register via Dubai Data |
| 20 May 2025 | DLD inspection records 3.8%. | DLD register via Dubai Data |
| 14 Oct 2025 | SAAS Properties completes shoring and piling. | SAAS Properties |
| 10 Nov 2025 | DLD inspection records 6.44%. | Property Finder; Dubai Data |
| 19 May 2026 | DLD inspection records 12.98%. | DLD register via Continental Club |
| Oct 2026 | Developer date recorded as Q4 2027; DLD date unchanged. | Continental Club; JRE |
The move from March 2027 to Q4 2027 adds about nine months. Progress has averaged under one point a month since May 2025 (Dubai Data), so even the Q4 2027 date needs a faster pace than the site has shown so far.
What the SAAS Hills handover date means for payments
The main 40/60 plan takes 20% on booking and 5% every three months during construction, up to 20% in all, and leaves 60% for handover (Continental Club; JRE). On the median 1 bedroom price of AED 1,726,952, the handover payment is about AED 1.04 million; on the median studio at AED 984,368, it is about AED 590,600.
Because the construction instalments are capped at 20%, a later handover mostly delays the 60% payment rather than adding instalments. Plans with 50% or 40% on handover were also sold (offplans.com).
What to check before relying on the SAAS Hills date
- The completion date in the SPA, which may say March 2027 for early buyers even though the developer now gives Q4 2027.
- The grace period and any compensation terms in the SPA, measured against that contract date.
- The next DLD inspection for project 3225, since the last published figure is from May 2026.
- How the 60% handover payment will be funded, including the validity period of any mortgage offer, if handover moves to Q4 2027 or later.
Questions buyers also ask
Is SAAS Hills finished?
No. The DLD inspection on 19 May 2026 recorded 12.98% complete across the two towers. SAAS Properties finished shoring and piling in October 2025.
What is the SAAS Hills completion date?
The DLD registered completion date is 31 March 2027. The developer's date is Q4 2027 (Continental Club, developer supplied), and Property Finder shows March 2027.
Has the SAAS Hills handover date been delayed?
The date in circulation has moved from March 2027, the registered date and the one Property Finder shows, to Q4 2027 from the developer. The DLD register itself has not been updated.
When will SAAS Hills Tower A and Tower B be ready?
Both towers are in one DLD project with one registered completion date, 31 March 2027, and one progress figure, 12.98% on 19 May 2026. No separate date has been published for either tower.