When is the Reportage Hills handover date?
Short answer
The Dubai Land Department (DLD) register holds a completion date of 30 June 2028 for Reportage Hills, while Reportage and Property Finder give Q4 2028 (30 December 2028). The last published DLD inspection, on 4 June 2026, recorded 0.39% construction progress. With so little built two years before the registered date, the date in each SPA and the next inspection figures matter more than either headline date.
Registered completion date (DLD)
30 Jun 2028
DLD register via Mitchell's, 4 Oct 2026
Latest construction progress
0.39%
DLD inspection, 4 Jun 2026
Developer's stated date
Q4 2028
Reportage sales sites, accessed 11 Oct 2026
Portal estimate
30 Dec 2028
Property Finder, accessed 11 Oct 2026
Reportage Hills handover date: the latest position
The Dubai Land Department (DLD) project register holds 30 June 2028 as the completion date for Reportage Hills (project number 3465). The last published DLD inspection, on 4 June 2026, recorded 0.39% construction progress. Prices, sizes and the payment plan are on the Reportage Hills page.
Reportage’s sales sites give a Q4 2028 handover, and Property Finder lists 30 December 2028. The register is six months earlier than the marketed date. With almost nothing built by June 2026, the earlier registered date would need a very fast build over the following two years.
Reportage Hills handover date by building
The DLD register treats Reportage Hills as one project of 905 units. The developer’s own materials count 902 townhouses and do not publish separate dates by cluster.
| Project | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Reportage Hills (905 units) | 0.39%, 4 Jun 2026 | 30 Jun 2028 | Q4 2028 (Reportage); 30 Dec 2028 (Property Finder) |
How the Reportage Hills handover date has changed
| Date | Event | Source |
|---|---|---|
| 2025 | Sales start with a Q4 2028 handover target | Reportage sales sites |
| 30 Jun 2025 | Registered construction start; Property Finder lists bookings from this date | DLD register; Property Finder |
| 3 Feb 2026 | DLD inspection, about 0.2% complete | DLD register via Continental Club |
| 4 Jun 2026 | DLD inspection, 0.39% complete | DLD register via Mitchell’s |
| Oct 2026 | Register still shows 30 Jun 2028; marketing still Q4 2028 | Mitchell’s; Property Finder |
The target has not moved since sales began. The registered date sits at the end of a standard three year construction window from 30 June 2025, while the developer’s target adds about six months. Progress of 0.39% in the first eleven months means the remaining work, about 99.6%, would need roughly 4 percentage points a month to meet 30 June 2028.
What the Reportage Hills handover date means for payments
Reportage’s 30/70 plan puts 20% at booking, 10% during construction and 70% on handover. On a AED 2.59 million 3 bedroom townhouse, the handover payment is about AED 1,813,000. Because most of the price is tied to handover, buyers pay little while construction is slow, but the date of the large final payment depends entirely on when the community completes. Property Finder lists 30% on handover instead, so the exact split is set by each SPA.
What to check before relying on the Reportage Hills date
- The date in the SPA, and whether it says 30 June 2028 or Q4 2028.
- The grace period after that date, since the gap between the two published dates is six months.
- The next DLD inspection figure for project 3465 on the Dubai REST app. Progress of 0.39% in June 2026 is the main sign that dates could move.
- How the 70% handover payment will be funded, whether by cash or a mortgage arranged at completion, since its timing follows the handover date.
Questions buyers also ask
When will Reportage Hills be completed?
The DLD registered completion date is 30 June 2028. Reportage and Property Finder show Q4 2028. Construction was 0.39% complete at the DLD inspection of 4 June 2026.
Has construction started at Reportage Hills?
Yes, on the register. The DLD records a construction start of 30 June 2025 and progress of 0.39% at the 4 June 2026 inspection, up from about 0.2% in February 2026 (Continental Club).
Has the Reportage Hills handover date been delayed?
No delay has been announced. Reportage has given Q4 2028 since sales began in 2025, and the registered date of 30 June 2028 is earlier than that. The low progress figure is the main sign to watch.
Is the Reportage Hills date the same as Reportage Village?
No. Reportage Village 1 has a registered completion date of 31 December 2027 and was 25% complete at its last DLD inspection (Dubai Data, accessed 11 October 2026).