Handover date

When is the REEF 1000 handover date, and when do the other REEF buildings complete?

Updated 11 October 2026 REEF

Short answer

REEF 1000 has a registered completion date of 30 December 2026 and the developer gives Q4 2026; a DLD inspection on 5 October 2026 recorded it 67.22% complete. REEF 999 in Al Furjan is due 30 June 2027 (13.21% built on 27 August 2026), REEF 998 30 June 2028, REEF 996 30 September 2028 and REEF 995 30 November 2028. Each building has its own date, so the one in the SPA for the unit's building is the one that applies.

REEF 1000 registered completion date (DLD)

30 Dec 2026

DLD project register via Continental Club, 10 Oct 2026

REEF 1000 latest construction progress

67.22%

DLD inspection, 5 Oct 2026

REEF 1000 developer date

Q4 2026

REEF Luxury Developments, accessed 11 Oct 2026

Latest REEF building due

30 Nov 2028

REEF 995, DLD register

REEF handover date: the latest position

REEF 1000, the first building by REEF Luxury Developments, has a registered completion date of 30 December 2026 and a developer date of Q4 2026. The DLD inspection on 5 October 2026 recorded it 67.22% complete, up from 50% on 14 July 2026. Prices, sizes and payment plans for every building are on the REEF project page.

The developer’s four later buildings each have their own date, from 30 June 2027 for REEF 999 to 30 November 2028 for REEF 995. Only REEF 1000 is past the halfway mark; the others range from 0% to 13.21%.

REEF handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
REEF 1000, DLRC (126 units) 67.22%, 5 Oct 2026 30 Dec 2026 Q4 2026 (developer)
REEF 999, Al Furjan (148 units, 2 buildings) 13.21%, 27 Aug 2026 30 Jun 2027 Q2 2027 (developer)
REEF 998, DLRC (339 units) 2.07%, 27 Aug 2026 30 Jun 2028 Q2 2028 (developer)
REEF 996, Dubai Production City (505 units) 0.1%, 1 Sep 2026 30 Sep 2028 Q3 2028 (developer)
REEF 995, DLRC (347 units) 0%, 22 Dec 2025 30 Nov 2028 Q4 2028 (Continental Club)

Source: DLD project register via Continental Club and Dubai Data, register updated 10 October 2026. The developer also lists REEF 997 on Dubai Islands, 63 homes due Q1 2028, which is not among these register records.

How the REEF handover dates have changed

  • 1 August 2024: REEF 1000 launch date in the DLD record (Dubricks); registered on 9 October 2024 with completion set for 30 December 2026.
  • 1 November 2024: REEF 1000 construction start.
  • 1 April 2025: REEF 999 construction start, completion set for 30 June 2027.
  • 2 July 2025: REEF 998 launched with handover in Q2 2028; registered completion 30 June 2028 (Construction Week; Dubai Data).
  • 1 October 2025: REEF 996 construction start, completion set for 30 September 2028.
  • 9 February 2026: REEF 1000 at 23.06%.
  • 24 April 2026: REEF 1000 at 30.76%.
  • 14 July 2026: REEF 1000 at 50%.
  • 27 August 2026: REEF 999 at 13.21%, up from 6% on 8 June; REEF 998 at 2.07%.
  • 15 September 2026: REEF 995 registered with DLD, completion set for 30 November 2028.
  • 5 October 2026: REEF 1000 at 67.22%.

None of the registered dates has changed since each building was registered. For REEF 1000, the July to October pace of about 6 points a month would bring it to 100% around March 2027. Meeting 30 December 2026 would need more than 11 points a month for the rest of the year.

What the REEF handover date means for payments

REEF 1000 and REEF 999 were sold on a 60/40 plan: 20% down payment, 40% during construction and 40% on handover (Continental Club). On a REEF 1000 studio at the median registered price of AED 620,620, about AED 248,000 is due on handover, and a 1 bedroom at the AED 1,249,580 median leaves about AED 500,000. REEF 998 buyers on the 3 year plan pay their last 30% on handover in 2028; those on the 5.5 year plan pay it after handover.

What to check before relying on a REEF date

  1. The building named in the SPA. REEF numbers are separate projects with separate dates, escrow accounts and areas.
  2. The REEF 1000 completion date and grace period in the SPA, given that the recorded pace points to early 2027.
  3. New DLD inspections for each building, through the DLD project status service, particularly REEF 999 ahead of its June 2027 date.

Questions buyers also ask

Is REEF 1000 finished?

Not yet. It was 67.22% complete at the DLD inspection on 5 October 2026, against a registered completion date of 30 December 2026.

Will REEF 1000 be handed over on time?

It is close. REEF 1000 gained 17.22 points between 14 July and 5 October 2026. At that pace the last 33 points would take a little over five months, to about March 2027, a few months after the registered date.

When will REEF 999 be ready?

REEF 999, a two building project in Al Furjan, has a registered completion date of 30 June 2027 and a developer date of Q2 2027. It was 13.21% complete on 27 August 2026, up from 6% in June.

What is the REEF 998 completion date?

30 June 2028 in the DLD register, the same Q2 2028 date given at launch in July 2025. It was 2.07% complete on 27 August 2026.

When will REEF 996 and REEF 995 be completed?

REEF 996 in Dubai Production City is registered for 30 September 2028 (0.1% built on 1 September 2026). REEF 995 in DLRC is registered for 30 November 2028 and had not started at its first recorded inspection.

Sources

  1. Continental Club, Reef 1000 (DLD register) (opens in a new tab)continentalclub.ae · registry updated 7 Oct 2026
  2. Continental Club, Reef 999 (opens in a new tab)continentalclub.ae · accessed 11 Oct 2026
  3. Continental Club, Reef 996 (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  4. Continental Club, Reef 995 (opens in a new tab)continentalclub.ae · accessed 11 Oct 2026